Really - I don't know anyone that was in favour of the full EGIP scheme, it was widely agreed the 6 trains per hour was unworkable and no-one wanted thier service moved away from Edinburgh Park either.
There were loads of companies and organisations that were in favour of the original EGIP scheme
Yes, some had raised concerns, but these were minor and caused by oversights in the way the documentation was put together and so fragmented
There haven't been that many responses to the revised scheme, so far, but the majority I have read are unfavourable
So far the only completely favourable one is Network Rail
I guess keeping the line open isn't as important now to be honest, the route via Bathgate is a reasonable alternative now.I know us from the Central belt still suffer when it floods but the main market is OK. They can still reverse at both Polmont and Linlithgow now.
Keeping the line open is still as important and a priority
Yes, diverting passengers on to the Bathgate route is an option, but it is only practical for those travelling between the main stations
I can't remember any recent blockades at Winchburgh, but the default does seem to be dump the four trains per hour to two trains per hour, via Falkirk High, and keep the service at least operating
There also seems to be confusion over which types of units are to be used
The original Glasgow QS program was to lengthen platforms 2 to 7 for longer 6 coach trains
However several news items advise the services will use 8 coach trains