Electrification may have some benefits. But when it goes wrong, it goes wrong in a big way.

1600 KX-Ab not due in until after 0200.
 

silentone

Member
Joined
16 Mar 2010
Messages
283
It was thought a set brought down the wires, on inspection it was found that the set had not brought the wires down but a large metal cable was seen hanging from the overheads at the feeder station near Marshall Meadows.

That observation was correct. Single line working between Berwick and Grantshouse/Reston.

The reason behind the hanging cable still seems unknown as the set in question had no damage.

There was also the usual common gripes with how things were/are being handled.
 