Just been looking through the
CP5 Enhancements Delivery Plan which is dated December 2014 but which I understand was published last week
I was interested with the sections relating to East West Rail and Electric Spine. The main section related to East West Rail is on pp40-41. For Phase 2, i.e. work between Bicester and Bletchley, GRIP 3 completion and option selection is scheduled for November 2015. GRIP 6 start of work is indicated for August 2017 with infrastructure completed and ready for use by March 2019.
Phase 2
Upgrading the existing Bicester Town to Bletchley freight line as a double-track 100mph multi-functional railway capable of accommodating three passenger services each way per hour and two additional paths per hour for freight and inter-regional services.
Upgrading the existing Aylesbury to Claydon Junction freight line as a single-track 100mph passenger railway capable of accommodating one passenger service and one freight service each way per hour.
Minor upgrading of the existing Bletchley Bedford passenger railway to accommodate one additional fast passenger service each way per hour.
New station at Winslow.
New high-level platforms and track remodelling at Bletchley.
New and enhanced overline structures to be constructed to W10 or W12 + electrification loading gauge.
I'm not sure what exactly is meant by W10
or W12 + electrification loading gauge - is the work not yet defined? W12 is slightly wider from what I can gather but presumably this means some existing structures could only be cleared for W10. For once we have the foresight to do the additional works for East West Phase 2 whilst the Phase 1 works for the Chiltern Oxford-Marylebone project are going on but does it not make sense to do everything to W12 while there is the chance?
Also of interest is the following note conceding the project milestones for Phase 2...
It is noted that the East West Rail Consortium and DfT have a target date for the core East West Rail train service to operate from December 2017. However, the project is at an early stage of development, and the outputs and scope are therefore unconfirmed.
I can't see December 2017 being possible though I guess the 15 month delay to March 2019 has to be officially agreed. It would also mean finding some DMUs from somewhere to operate the service.
Electrification in relation to East West Rail is covered under Electric Spine - pp53-55 - and the good news is that is still happening at the same time as EWR Phase 2.
So can we be reasonably confident that Oxford - Bletchley at least is still planned to be completed and electrified by March 2019 i.e. within CP5. A major benefit of being able to do the EWR work without having to work within the constraints of a live railway!
Other parts of Electric Spine which are being prioritised are Southcote Jn (Reading) - Basingstoke; Sheffield - ECML at Doncaster & South Kirby; and Leamington - Coventry.
MML electrification from Bedford to Kettering / Corby is due for completion by December 2017; and Kettering - Nottingham / Derby by December 2019. Electrification between Derby and Sheffield is due to be completed December 2020. North of Sheffield to ECML electrification follows on and is pencilled in for completion for June 2021.
The Leamington - Coventry electrification schedule is not yet defined but it probably makes the cut on the grounds of needing juice for an extended EMU stopping service beyond Coventry to serve Kenilworth & Leamington rather than freight. Southcote Jn - Basingstoke electrification schedule is also undefined (but is being progressed with Thames Valley branches electrification project).
DC / AC conversion south of Basingstoke to Southampton; electrification from Oxford - Leamington; Bletchley - Bedford and Coventry - Nuneaton are a lower priority. The cynic in me might think some of these possibly get binned if the new government needs to save money come May.