No, only a fraction of the line will be wired. Initially it was only going to be from Tweedbank to the south end of Bowshank tunnel. They now also propose to also do a short length at the northern end, from the existing wires at Newcraighall to Sheriffhall Mains, not far north of the bridge under the City Bypass. There's a thread about it here.I know the Fife route is, but I thought borders was supposed to be continuous?
The point is not to do everything that's easy. The point is to do no more than necessary, at least at first, then do another line.Doesn't seem like it would be the hardest line ever to do in full.
I don't think it's true that waiting for enhancement to power supplies at the Edinburgh end is the issue. The current "six-pack" contract for six feeder stations includes one at Currie, one at Portobello and one at Tweedbank, all of which will be in place long before the BEMUs are delivered. Then I think no more feeder stations will be required around Edinburgh for the foreseeable future.Power supply closer to Edinburgh is the issue (NatGrid long lead time) so the plan is to electrify the southern end and bridge the gap with battery till the Edinburgh area power supply gets enhanced so wires could be powered.
As I've said several times, running a line with BEMUs requires roughly as much power supplies as running it with EMUs. Each train draws power for less of the time, but draws more of it, to charge the batteries as well as move the train.
Last edited: