DLRnotDave
Member
Testing should be resuming during some of the closures next month, reintroduction still looks unlikely to be before the second half of the year
reintroduction still looks unlikely to be before the second half of the year
Testing should be resuming during some of the closures next month, reintroduction still looks unlikely to be before the second half of the year
Any idea if testing will restart on the Beckton - Stratford International route?Testing should be resuming during some of the closures next month, reintroduction still looks unlikely to be before the second half of the year
Should they not be relaxed about running 3-car trains, or is there something I'm missing here?And yet TfL seem pretty relaxed about running 3-car trains on the Bank-Lewisham service. My daily walk on the Isle of Dogs, including weekends, follows the course of the DLR between Crossharbour and Canary Wharf. During that walk I see 6 to 8 trains (and I'm confident I'm not counting the same train twice), all of which have so far been 3-car trains.
A number of trains are due to be replaced, but technical problems have delayed the new trains.Should they not be relaxed about running 3-car trains, or is there something I'm missing here?
Hi, yes reasonable question and tbh I don't know as I didn't see any other services on my one-stop river crossing freebie, but I got a TFL email this morning announcing 2 car services from the 16th-19th. So maybe for me xmas came early. Or half-term anyway.
Regarding cutting down to 2-car outside travel peaks, I understood one of the issues with the current fleet is wear on the couplers due to uncoupling and joining, maybe they have a supply issue with overhauling them, so possibly a need to minimise the number of coupling-ups made.
Announcement that Bank to Lewisham will be down to 2-car weekdays next week 16 February:
No sign of any activity with the new trains since their withdrawal last autumn. Have any of them turned a wheel? One really has to wonder if DLR just don't know what to do/have given up. Any questions about this at the London Assembly are just glossed over with "New Trains ... rhubarb rhubarb rhubarb ... next question?". Have the engineers involved quit for different opportunities?
Regarding cutting down to 2-car outside travel peaks, I understood one of the issues with the current fleet is wear on the couplers due to uncoupling and joining, maybe they have a supply issue with overhauling them, so possibly a need to minimise the number of coupling-ups made.
I mean, they were built by CAF, so I really don't know what people expected. An increase in the sales of sellotape, maybe?No sign of any activity with the new trains since their withdrawal last autumn. Have any of them turned a wheel? One really has to wonder if DLR just don't know what to do/have given up.
Rhubarb?Any questions about this at the London Assembly are just glossed over with "New Trains ... rhubarb rhubarb rhubarb ... next question?".
Well, cars will need to be uncoupled from their partner(s) for things like maintenance and overhaul and then recoupled. A 3-car unit has 4 couplers in use, while a 2-car unit only has 2 couplers in use, so it stands to reason that reducing the length of the trains will probably reduce the amount of coupling required by a not insignificant amount.Not sure what you mean here. DLR trains are never (and I think can never) be coupled/uncoupled outside of the Depots so have to remain 3-car (or 2-car) trains for the entire day.
Announcement that Bank to Lewisham will be down to 2-car weekdays next week 16 February:
No sign of any activity with the new trains since their withdrawal last autumn. Have any of them turned a wheel? One really has to wonder if DLR just don't know what to do/have given up. Any questions about this at the London Assembly are just glossed over with "New Trains ... rhubarb rhubarb rhubarb ... next question?". Have the engineers involved quit for different opportunities?
Regarding cutting down to 2-car outside travel peaks, I understood one of the issues with the current fleet is wear on the couplers due to uncoupling and joining, maybe they have a supply issue with overhauling them, so possibly a need to minimise the number of coupling-ups made.
B23 trains have been out for testing on the mainline during engineering hours over the past couple of weeks.No sign of any activity with the new trains since their withdrawal last autumn. Have any of them turned a wheel?
The comment was about weekends, and I was referring to minimising uncoupling overall.Not sure what you mean here. DLR trains are never (and I think can never) be coupled/uncoupled outside of the Depots so have to remain 3-car (or 2-car) trains for the entire day.
They have? Would’ve thought to have seen one go right past my window as they come out and go back into the Beckton Depot. Unless those moves are done at like 3am…B23 trains have been out for testing on the mainline during engineering hours over the past couple of weeks.
The 2-car running on the Bank-Lewisham route on Sunday/Monday was because of an issue in Poplar depot messing with the morning runout.As far as I could see, 2-car trains restarted on the Bank-Lewisham service on Sunday 8th and all the ones I saw or have been on this morning are 2-car. I also got that e-mail about 2-car services next week, the school holidays, but nothing about why they've done that this week
They've definitely been out testing. First one since the fleet withdrawal was out on the night of 24/25 Jan. More nights since then.They have? Would’ve thought to have seen one go right past my window as they come out and go back into the Beckton Depot. Unless those moves are done at like 3am…
I assume the Mayor isn't trying to take "credit" for thisAnnouncement that Bank to Lewisham will be down to 2-car weekdays next week 16 February:
No sign of any activity with the new trains since their withdrawal last autumn. Have any of them turned a wheel? One really has to wonder if DLR just don't know what to do/have given up. Any questions about this at the London Assembly are just glossed over with "New Trains ... rhubarb rhubarb rhubarb ... next question?". Have the engineers involved quit for different opportunities?
Regarding cutting down to 2-car outside travel peaks, I understood one of the issues with the current fleet is wear on the couplers due to uncoupling and joining, maybe they have a supply issue with overhauling them, so possibly a need to minimise the number of coupling-ups made.
Presumably because the B07 sets released by doing this are, or soon will be, needed to cover for B90 sets that have already run out their allowed mileage?Why do the B07 trains need to be reduced to 2 cars? Surely the issue with the mileage is limited to the stock planning to be withdrawn so it’d be better to have the trains staying 3 cars?
And to add to the exciting plot twists, DLR seems to be running normal 3 car trains this week, despite saying it would be 2 car. Again, this is from a sample pool of one.The 2-car running on the Bank-Lewisham route on Sunday/Monday was because of an issue in Poplar depot messing with the morning runout.
Indeed. *MOST* of the Bank-Lewisham trains I've seen so far this week have been 3-cars but I have spotted a couple of 2-car trains. And some of the 3-car trains have been B90/B92 stock. As a data-cruncher, I'd really like to know how many km per day these units travel, how many total km they have accumulated since their last major overhaul and what their "drop dead" limit is before they have to be taken out of service for their next service or be withdrawn.And to add to the exciting plot twists, DLR seems to be running normal 3 car trains this week, despite saying it would be 2 car. Again, this is from a sample pool of one.
New DLR trains returning to customer service by late summer
DLR customers will benefit from the return of the network’s new trains, with a phased reintroduction expected by late summer. This follows significant progress by engineering teams in carrying out detailed investigations, testing, and assurance to ensure the fleet is ready to enter to service safely and reliably. Further detail of the reintroduction will be provided in spring.
- Customers will see the new DLR trains back in service by this summer, following strong progress in investigation, testing and assurance work
- CAF and TfL engineers are introducing a series of improvements to make sure the trains return safely and reliably
- The new fleet will transform journeys with walk-through carriages, air-conditioning and more capacity
In late 2025, a train stopped past its intended stopping point - the only time this occurred after the new trains were introduced - but safety is TfL’s number one priority, so all three new trains were withdrawn as a precautionary measure. TfL has since been working closely with CAF, the manufacturer, to identify the root cause and safely and reliably reintroduce the new trains.
To support the safe return of the trains, engineers are introducing a focused package of improvements - including braking software upgrades to improve performance in the type of specific low rail adhesion conditions experienced during the incident. These are currently being tested on the manufacturer’s test track before further testing on the DLR network. Some network closures will be needed to facilitate this testing, so it is recommended customer check before they travel by using the TfL Go app or Journey Planner on the TfL website.
Once fully rolled out, the new fleet will replace the oldest trains on the DLR and boost overall capacity by more than 50 per cent. Customers will benefit from modern walkthrough carriages, air-conditioning, improved accessibility, real time travel information and enhanced safety features, all designed to make journeys more comfortable, easier and more reliable.
Stuart Harvey, TfL’s Chief Capital Officer, said: “We know customers are looking forward to travelling on these new trains, and we will provide a further update in the spring, with the trains being reintroduced by summer. Our engineers, together with CAF and our franchisee KeolisAmey Docklands, have worked tirelessly to ensure they return safely and reliably. We are confident customers will welcome the extra space, improved accessibility, real‑time travel information and air‑conditioning these trains provide.”
More information on improvements across the DLR network is available at:
https://tfl.gov.uk/modes/dlr/improving-the-dlr