Are you aware of why they didn't do this first time around?There may not be much capacity potential in this, but closing Stocks Lane LC, then adjusting the OHLE to reinstate 125mph through Steventon would I think help
Are you aware of why they didn't do this first time around?There may not be much capacity potential in this, but closing Stocks Lane LC, then adjusting the OHLE to reinstate 125mph through Steventon would I think help
GWR quadrupled the section through Challow to Wantage Road stations in 1932, so trains could be overtaken in platforms or anywhere between.Was this section 4-track over a much longer stretch in the past before being rationalised? That might help determine how easy future quadrupling is to carry out.
Yes at stated above, rebuilt in 1932 as part of long loops to/from Challow, so trains calling could be passed by fast trains. But always ideal to have loop extend further so train can leave station and be ready to accelerate as soon as signal clears, not start the door closing sequence when signal clears which takes about extra half minuteI assume any reopening of the station at Wantage and Grove would be dependant on finding ways to increase capacity on this stretch?
Have you seen what it’s like when the ‘Berks & Hants’ via Newbury is unavailable?In 12.00 to 13.00 - _west_ bound there was _one_ freight today. Between 13:00 and 18:00 there were only three _in total_ westbound - and eastbound there were none.
There may be that many _paths_ for freights, but a heck of a lot are 'runs as required' slots (some workings are overlapped with other as required workings), that are rarely used.
That's obviously going to happen - but have you seen what happens when Penrith is out? Or Weaver Jct? We don't run fewer trains on WCML for the rest of the year, just in case one of those places is out! Out come the buses...Have you seen what it’s like when the ‘Berks & Hants’ via Newbury is unavailable?
As we saw when Penrith was out for the Clifton bridge renewal and indeed more recent work that has seen Preston-Lancaster closed, the intermodal traffic has to divert to the ECML (because the Settle & Carlisle isn’t gauge cleared). With the ECML being ‘full’ like Didcot-Swindon but over much longer distances this causes significant problems.That's obviously going to happen - but have you seen what happens when Penrith is out? Or Weaver Jct? We don't run fewer trains on WCML for the rest of the year, just in case one of those places is out! Out come the buses...
Is the route to the West of England Waterloo- Exeter no longer a 'diversionary opportunity'? for some?As we saw when Penrith was out for the Clifton bridge renewal and indeed more recent work that has seen Preston-Lancaster closed, the intermodal traffic has to divert to the ECML (because the Settle & Carlisle isn’t gauge cleared). With the ECML being ‘full’ like Didcot-Swindon but over much longer distances this causes significant problems.
Freight can’t get on a bus and thus has to be diverted or lost, probably permanently. There are only two routes to the West of England so the GWML has to be the alternative to the Newbury route (and vice versa).
It has been used in some diversions for B&H services, but there is almost no resilience on the line in its current form. When Taunton was shut a few years ago for a week, some diversions from Castle Cary-Exeter had to take the paths of SWR services in order to fit.Is the route to the West of England Waterloo- Exeter no longer a 'diversionary opportunity'? for some?
Indeed, we need to get away from filling every piece of white space to earn money from it.
Bearing in mind that I was referring to large amounts of freight that can't 'get on a bus' I'm not sure. I suppose that Westbury (reverse)-Salisbury-Basingstoke-Reading might be feasible. Perhaps someone more local can comment how often it has been done rather than the more usual Melksham-GWML alternative that causes problems on its own?Is the route to the West of England Waterloo- Exeter no longer a 'diversionary opportunity'? for some?
Or does it lose money from those who choose not to use rail again as its unreliable?Does the industry earn more money from
- 1000 slightly disgruntle passengers, or
- 800 happy passengers?
Basingstoke to Reading isn't exactly overflowing with spare capacity, with the local, XC and Southampton traffic already. Though it does share tracks with the B&H through Reading West so maybe those paths might extend to Basingstoke.Bearing in mind that I was referring to large amounts of freight that can't 'get on a bus' I'm not sure. I suppose that Westbury (reverse)-Salisbury-Basingstoke-Reading might be feasible. Perhaps someone more local can comment how often it has been done rather than the more usual Melksham-GWML alternative that causes problems on its own?
Reality is that there are many important arteries in the system that have terrible or no viable diversionary routes. We can't operate a railway by planning every route to have a diversion that can fit all the normal traffic of the diverted route and its own - and hence run at around 50%!As we saw when Penrith was out for the Clifton bridge renewal and indeed more recent work that has seen Preston-Lancaster closed, the intermodal traffic has to divert to the ECML (because the Settle & Carlisle isn’t gauge cleared). With the ECML being ‘full’ like Didcot-Swindon but over much longer distances this causes significant problems.
Freight can’t get on a bus and thus has to be diverted or lost, probably permanently. There are only two routes to the West of England so the GWML has to be the alternative to the Newbury route (and vice versa).
I am certainly not advocating a 50% utilisation policy on routes that can act as a diversion for a nearby route, in case it is needed as such.Reality is that there are many important arteries in the system that have terrible or no viable diversionary routes. We can't operate a railway by planning every route to have a diversion that can fit all the normal traffic of the diverted route and its own - and hence run at around 50%!
Am thinking it'd be pretty bad to lose anything at Carlisle or Newcastle.. Port Talbot, or Ely (divert via full WCML?), etc!
Probably 800 passengers, if it's operating costs are lower from running less trains and it's paying out less delay repay.Does the industry earn more money from
- 1000 slightly disgruntle passengers, or
- 800 happy passengers?
I guess in some cases it is 800 happy passengers (on more trains) or 800 unhappy passengers (crammed into fewer trains)? The railway isn't exactly reliable as it is, yet we still get lots of passengers. It seems like a question of policy.Does the industry earn more money from
- 1000 slightly disgruntle passengers, or
- 800 happy passengers?