redreni
Established Member
Even after reading and contributing to numerous threads on the subject, I still don't think I've seen a definitive answer to these questions:
I have also heard it said that these "which TOC is responsible?" questions are no concern of the passenger's, because you just claim from whichever operator and they forward it if necessary. I disagree, because different TOCs have different delay thresholds.
If I experience a delay of 15-29 minutes on a journey involving a mixture of DR15 and DR30 operators, I would like to know what the rules are so I can push back if I am delayed by a DR15 operator but they try to say a DR30 operator is responsible. Conversely, if I experience a delay of 15-29 minutes and a DR30 TOC is responsible, I don't want to waste my or anybody else's time putting in a claim.
I currently have a claim in with GWR for a 16 minute delay and they have said TfL (Elizabeth Line) is responsible. Obviously, I thought GWR was responsible, which is why I claimed from them. Who is right? Well, in this particular case, it depends on the answer to question (1), above.
I used a GWR train that was 9 mins late into Paddington, which fouled the MCT for my intended Elizabeth Line train to Abbey Wood (or would have done had it been on time), but as it happened, that Elizabeth Line train was also late so I did have exactly 15 minutes (which is the MCT) available to catch it and did catch it. But because it was late, I arrived at Abbey Wood later than scheduled, missed my connection there and arrived at my final destination 16 mins late.
The first delay was GWR's, but it only fouled the intended connection, not the actual connection, because the second train was also late. If the delay is GWR's fault I am owed compensation. If the delay is TfL's fault I am not owed compensation.
Is there any chance of getting clarity on this? I really think if a consistent approach were taken to these things, we wouldn't have the level of delay repay ping-pong we have currently.
I would like to understand the rules not only so I can argue my case confidently if a valid claim is rejected, but also to ensure I won't inadvertently submit any claims that aren't valid. I do a lot of journeys that include a mixture of DR15 and DR30 operators (the latter being the Elizabeth Line and London Overground).
Final question: what is the point of GWR forwarding my claim to TfL in the circumstances described above? Don't they know that the Elizabeth Line is a DR30 operator? Surely if GWR believes the delay was TfL's fault, it should just reject it, since the delay claimed for was below 30 minutes? I wouldn't knowingly waste TfL's time by claiming from them for a 16 minute delay on the Elizabeth Line - why are TOCs wasting each other's time in this way?
- Is operator A responsible for delaying a passenger if its train arrives at an interchange station late enough that it would have fouled the MCT for the intended connection to operator B's train had operator B's train departed on time, but because operator B's train departs the interchange station late, the passenger has enough time (i.e. at least the MCT) to make the connection?
- Is operator A deemed responsible for delaying a passenger if its train arrives at an interchange station late enough to foul the connection to operator B's train, but the passenger makes a sub-MCT connection and departs the interchange station on operator B's train on time and is then delayed after that?
I have also heard it said that these "which TOC is responsible?" questions are no concern of the passenger's, because you just claim from whichever operator and they forward it if necessary. I disagree, because different TOCs have different delay thresholds.
If I experience a delay of 15-29 minutes on a journey involving a mixture of DR15 and DR30 operators, I would like to know what the rules are so I can push back if I am delayed by a DR15 operator but they try to say a DR30 operator is responsible. Conversely, if I experience a delay of 15-29 minutes and a DR30 TOC is responsible, I don't want to waste my or anybody else's time putting in a claim.
I currently have a claim in with GWR for a 16 minute delay and they have said TfL (Elizabeth Line) is responsible. Obviously, I thought GWR was responsible, which is why I claimed from them. Who is right? Well, in this particular case, it depends on the answer to question (1), above.
I used a GWR train that was 9 mins late into Paddington, which fouled the MCT for my intended Elizabeth Line train to Abbey Wood (or would have done had it been on time), but as it happened, that Elizabeth Line train was also late so I did have exactly 15 minutes (which is the MCT) available to catch it and did catch it. But because it was late, I arrived at Abbey Wood later than scheduled, missed my connection there and arrived at my final destination 16 mins late.
The first delay was GWR's, but it only fouled the intended connection, not the actual connection, because the second train was also late. If the delay is GWR's fault I am owed compensation. If the delay is TfL's fault I am not owed compensation.
Is there any chance of getting clarity on this? I really think if a consistent approach were taken to these things, we wouldn't have the level of delay repay ping-pong we have currently.
I would like to understand the rules not only so I can argue my case confidently if a valid claim is rejected, but also to ensure I won't inadvertently submit any claims that aren't valid. I do a lot of journeys that include a mixture of DR15 and DR30 operators (the latter being the Elizabeth Line and London Overground).
Final question: what is the point of GWR forwarding my claim to TfL in the circumstances described above? Don't they know that the Elizabeth Line is a DR30 operator? Surely if GWR believes the delay was TfL's fault, it should just reject it, since the delay claimed for was below 30 minutes? I wouldn't knowingly waste TfL's time by claiming from them for a 16 minute delay on the Elizabeth Line - why are TOCs wasting each other's time in this way?