I'm abroad at the moment and can't see all the document, but I see NW electrification is still unrealistic.
Manchester-Preston and Stalybridge are still Dec 2017, but are "indicative" ie not committed.
Preston-Blackpool is just "CP5", so anyone's guess
Not impressed.
 

GRALISTAIR

Established Member
Joined
11 Apr 2012
Messages
10,492
Location
Preston Lancs
I'm abroad at the moment and can't see all the document, but I see NW electrification is still unrealistic.
Manchester-Preston and Stalybridge are still Dec 2017, but are "indicative" ie not committed.
Preston-Blackpool is just "CP5", so anyone's guess
Not impressed.

I live in the USA -so bookmarked, printed and will read tonight. Thanks for posting OP
 

snowball

Established Member
Joined
4 Mar 2013
Messages
8,144
Location
Leeds
I'm abroad at the moment and can't see all the document, but I see NW electrification is still unrealistic.
Manchester-Preston and Stalybridge are still Dec 2017, but are "indicative" ie not committed.

On page 11, Manchester to Preston and Stalybridge appear as 10 Dec 2017 both in the middle column (GRIP 6 completion, indicative) and the right-hand column (entry into service, regulated output).

Many of us have been saying these dates seem unrealistic in relation to observed progress on the ground, yet Joseph Locke said on 6th September

I see no programme issues beyond those associated with the timing of the Bolton Blockade.
 

GRALISTAIR

Established Member
Joined
11 Apr 2012
Messages
10,492
Location
Preston Lancs
---- I see NW electrification is still unrealistic. Manchester-Preston and Stalybridge are still Dec 2017, but are "indicative" ie not committed.
Preston-Blackpool is just "CP5", so anyone's guess. Not impressed.

So logically these all get done first so Bolton -Wigan originally complete by 2017 will not get done. I see this update says GRIP 3 only complete by March 2017 and all else is indicative.

At least GOBLIN electrification looks like it will be complete and EIS in under 1 year

(sorry OT and don't want to start another North-South argument) - that is in London area!!!
 
Last edited:

LNW-GW Joint

Veteran Member
Joined
22 Feb 2011
Messages
21,914
Location
Mold, Clwyd
I see much of the detail in this report applies to June 2016 as the most recent update for individual projects.
So recent developments/milestone achievements since then (eg live testing on the Tilehurst-Didcot section) is not included.
 