Other 701 Updates:
Today, there is a 20-car set of units on test, consisting of 701025 + 701044. Is testing really going that bad?
How would a 20-car set fit into Waterloo? Have you considered that it is likely to be a case of a set swap with the original set not being de-allocated and the data feeds showing both?
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

norbitonflyer

Established Member
Joined
24 Mar 2020
Messages
5,845
Location
SW London
Other 701 Updates:
Today, there is a 20-car set of units on test, consisting of 701025 + 701044. Is testing really going that bad?
Round the Hounslow loop
Is that testing/practicing emergency pushouts?
 

GW43125

Established Member
Joined
8 Dec 2014
Messages
2,313
Round the Hounslow loop
Is that testing/practicing emergency pushouts?
No. It's a set swap that hasn't been properly deallocated/hasn't pulled through to RTT. Saw it pass me at Twickenham and was most definitely a single unit!
 

TEW

Established Member
Joined
16 May 2008
Messages
6,228
The 5Q paths round the Hounslow Loop are for driver training rather than any kind of testing generally.
 

swr444

Member
Joined
26 Aug 2008
Messages
1,020
Location
London
We now have a train crew bulletin saying phase 4 is to Hampton court from 28th October. As mentioned previously in this thread. No mention of what diagram it is yet
 

SWT_USER

Member
Joined
29 Aug 2010
Messages
1,183
Location
Ashford Middx
We now have a train crew bulletin saying phase 4 is to Hampton court from 28th October. As mentioned previously in this thread. No mention of what diagram it is yet
Good news in theory, but I'm not confident it will make much difference on the ground given they can't even reliably run the current diagrams.
 

TT-ONR-NRN

Veteran Member
Joined
30 Dec 2016
Messages
12,905
Location
Cambridge
So they're calling it a new phase for Shepperton and Hampton Court, even though both times the routes got like one or two a day? I think that's quite pathetic.
 
Joined
2 Jun 2023
Messages
1,096
Location
Richmond
So they're calling it a new phase for Shepperton and Hampton Court, even though both times the routes got like one or two a day? I think that's quite pathetic.
Can't wait for Phase 20,532 when all the units have been rolled out, coincidently occurring in the year 2053
 

Stephen42

Member
Joined
6 Aug 2020
Messages
810
Location
London
Good news in theory, but I'm not confident it will make much difference on the ground given they can't even reliably run the current diagrams.
For Hampton Court there is the peak extra which would free up a pair of 455s and would only require a single driver/guard. The evening Shepperton is the problem and it's plausible another Windsor diagram could be introduced more reliably. Assuming it would be the peak extra to avoid having to replan a bunch of services would only be running:
Y08996 5J90 0635 WIMBLEDON PARK DEPOT SDGS - LONDON WATERLOO 0651
Y08997 5J92 0707 LONDON WATERLOO - SURBITON 0745
Y08995 2J92 0752 SURBITON - LONDON WATERLOO 0824
Y08998 5J93 0838 LONDON WATERLOO - HAMPTON COURT 0859
Y08999 5Y52 0910 HAMPTON COURT - WIMBLEDON PARK DEPOT SDGS 0942
Two potential moves from Long Marston to Wimbledon have appeared for tomorrow and Thursday. From RTT maybe a bit of reshuffling between SWR locations as well this week though hard to tell whether it's 701s or something else.
 

swtrains

Member
Joined
30 May 2024
Messages
193
Location
London
20?? That would have certainly bene a sight to behold. Is it on RTT?
And for those wondering, that's 406.22m long!
Knew you'd be gullible enough to believe that.

== Doublepost prevention - post automatically merged: ==

Today's testing:
5T90 - Clapham Yard - Guildford U.C.H.S - Goes to Waterloo, then to Guildford via Epsom.
5T91 - Guildford U.C.H.S - Clapham Yard - Reverses at Guildford, then heads back to Clapham via Epsom.
This testing also takes place in the evening, finishing up at around half past midnight.
 
Last edited:

moley

Member
Joined
12 Jun 2011
Messages
409
When the bridge over the orchestral pit was built, wasn’t some of the track lifted and filled to create the gate line thus the train stops moved countryward?
 

Big Jumby 74

Established Member
Joined
12 Feb 2022
Messages
2,254
Location
UK
Platforms 20-24 have an operational length (inside signals) that allows for a 12 car (eg 450) maximum, or other types that amount to shorter than that. Unlike many other platforms at Waterloo, there is also no platform sharing permitted in 20-24.
 

Goldfish62

Veteran Member
Joined
14 Feb 2010
Messages
13,231
When the bridge over the orchestral pit was built, wasn’t some of the track lifted and filled to create the gate line thus the train stops moved countryward?
I believe they were also shortened at the "country" end.
 

Big Jumby 74

Established Member
Joined
12 Feb 2022
Messages
2,254
Location
UK
I believe they were also shortened at the "country" end
Correct, P24 most notably AFAIR, the trackside 'face' of p21 being the one that remains mostly as it was originally built (from memory again, so will stand corrected!). They were shortened in order to allow for a more domestic style track layout to be installed (crossovers etc) between the inbound home signal gantry (in to P21-24) and the platform ends. Said gantry is itself positioned London side of Carlisle Lane Junction, ie: on the short section of self contained (international) station approach roads, hence the platforms had to be shortened at the Country end.
The old Eurostar track layout that once existed in the International throat, London side of Carlisle Lane, was completely un-compatible with the requirements of the planned domestic services that were to use those platforms.
 

DMckduck

Member
Joined
26 Jul 2020
Messages
488
Is that also why the stop signs on platform 24 (only) are placed quite a way back from the buffer stops?
If the Stop car mark on 24 was at the end of the track like it usually is at terminus stations it would be breach the gateline.

Creating a gateline at a different angle specifically for 24 would have intruded on the lifts and potentially a dangerous crowding issue which could impact turnaround times.
 
Joined
2 Feb 2019
Messages
1,039
Platforms 20-24 have an operational length (inside signals) that allows for a 12 car (eg 450) maximum, or other types that amount to shorter than that. Unlike many other platforms at Waterloo, there is also no platform sharing permitted in 20-24.
So how did the 20 car double Arterio train fit into the former Eurostar platforms on the test run?
 

Notchapple

Member
Joined
4 Mar 2022
Messages
49
Location
London
So how did the 20 car double Arterio train fit into the former Eurostar platforms on the test run?
I think it was stated that it was a data error after the set was swapped out last minute and was in fact just 1 x 10 car.
As expected 2J92 is booked as a 701 from next Monday 28th.
Thanks, slightly off topic, but do you know why the set has to run to Waterloo from Wimbledon Park then to Hampton Court before starting at Surbiton, same after the diagram finishes at Waterloo (runs to HMC then to Wimbledon Park)
 

swtrains

Member
Joined
30 May 2024
Messages
193
Location
London
Thanks, slightly off topic, but do you know why the set has to run to Waterloo from Wimbledon Park then to Hampton Court before starting at Surbiton, same after the diagram finishes at Waterloo (runs to HMC then to Wimbledon Park)
It was put into place after the 707s left, as the trains replacing it were 5-car and not 10, and kept being switched out regularly. Thames Ditton onwards gets very busy in the morning peak, so I imagine they had to put in a second diagram to cope with that. I think it starts at Surbiton because otherwise it would clash with the ex 707 diagram. Not sure why it runs back to Hampton Court after it's finished though.
 