It really does seem optimistic. Perhaps there is a degree of wanting to test the 387s on a more intense schedule to T5, and taking the opportunity of lower passenger numbers so it doesn't mess things up so much?
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

kevin_roche

Member
Joined
26 Feb 2019
Messages
997
It really does seem optimistic. Perhaps there is a degree of wanting to test the 387s on a more intense schedule to T5, and taking the opportunity of lower passenger numbers so it doesn't mess things up so much?
How will Crossrail eventually run 6 trains per hour to Heathrow as well as the HEX if they can't cope with 4 now?

I thought that ETCS was supposed to allow 40% extra according to the European Agency For Railways. https://en.wikipedia.org/wiki/European_Union_Agency_for_Railways
 
Last edited:

matt_world2004

Established Member
Joined
5 Nov 2014
Messages
4,581
How will Crossrail eventually run 6 trains per hour to Heathrow as well as the HEX if they can't cope with 4 now?

I thought that ETCS was supposed to allow 40% extra according to https://en.wikipedia.org/wiki/European_Union_Agency_for_Railways
It's not the tunnel capacity at Heathrow that's the problem . But the long dwell time at Heathrow airport for the Heathrow express trains. For six trains per hour it is going to require a new timetable shortening the dwell time.
 

JN114

Established Member
Joined
28 Jun 2005
Messages
3,522
It's not the tunnel capacity at Heathrow that's the problem . But the long dwell time at Heathrow airport for the Heathrow express trains. For six trains per hour it is going to require a new timetable shortening the dwell time.

It will require HEx to go back to their old, pre- Dec 2019 timetable, which only uses 1 platform at T5.

That is planned to happen once Crossrail start running into the Sewer.
 

kevin_roche

Member
Joined
26 Feb 2019
Messages
997
It's not the tunnel capacity at Heathrow that's the problem . But the long dwell time at Heathrow airport for the Heathrow express trains. For six trains per hour it is going to require a new timetable shortening the dwell time.
Ahh! Of course, the platform arrangements at Paddington are an issue. Once the Crossrail trains are no longer taking up the high-level platforms, HEX can have them back and the longer dwell will happen at Paddington.
 

Horizon22

Established Member
Associate Staff
Jobs & Careers
Joined
8 Sep 2019
Messages
10,944
Location
London
How will Crossrail eventually run 6 trains per hour to Heathrow as well as the HEX if they can't cope with 4 now?

I thought that ETCS was supposed to allow 40% extra according to the European Agency For Railways. https://en.wikipedia.org/wiki/European_Union_Agency_for_Railways

Still some interweaving with GWRs 387s to Hayes & Harlington not fitted with operational ETCS.

And the dwells are highly imbalanced at the moment. HeX are supposed to only use P7 at Paddington because TfL are still primarily using 11-12 which necessitates a 7 min turnaround whilst its about 20' over at T5 due to the uptick in intensity of GWR services. Will be some breathing room when Crossrail goes underground.
 

rebmcr

Established Member
Joined
15 Nov 2011
Messages
4,005
Location
St Neots
Will be some breathing room when Crossrail goes underground.
Does anyone know whether it would be operationally feasible to terminate services at Paddington Low Level from the west, in advance of the core opening? Using Carto Metro for reference, it looks like there would have to be bidirectional working between there and Subway Junction?
 

JN114

Established Member
Joined
28 Jun 2005
Messages
3,522
Does anyone know whether it would be operationally feasible to terminate services at Paddington Low Level from the west, in advance of the core opening? Using Carto Metro for reference, it looks like there would have to be bidirectional working between there and Subway Junction?

It would be technically possible, once the central section opens for passenger traffic, but It definitely wouldn’t be operationally practical. It would virtually preclude any kind of service running on the central section other than these eastbound Crossrail terminators - and if you’re running onto the central section, you might as well go to Abbey Wood or somewhere designed for terminating eastbound services.
 

Horizon22

Established Member
Associate Staff
Jobs & Careers
Joined
8 Sep 2019
Messages
10,944
Location
London
Does anyone know whether it would be operationally feasible to terminate services at Paddington Low Level from the west, in advance of the core opening? Using Carto Metro for reference, it looks like there would have to be bidirectional working between there and Subway Junction?

You could, but you'd probably have to start the return working from Paddington too as well. That would mean berthing in a Paddington platform for maybe around 90 mins which becomes rather impractical. Will be interesting what sort of service contingencies MTR / TfL have got in mind for late running into the central section especially for an Abbey Wood service where there isn't much skip-stop potential.
 

JonathanH

Veteran Member
Joined
29 May 2011
Messages
23,261
TfL Rail services have been set up as separate London Paddington to Heathrow Central and Heathrow Central to Heathrow Airport Terminal 5 services from today, presumably because there was a chance that they might have terminated at Heathrow Central and run empty to Terminal 4, had the Heathrow Express gone back up to 4tph.

The headcodes of the separate services are 9Txx from Paddington to Heathrow Central and 2Txx onwards (2Pxx / 9Pxx in the other direction) but the same 345 runs through.
 

itfcfan

Member
Joined
7 May 2011
Messages
346
Paddington - Hayes & Harlington services are showing as 7 cars on Tiger today (have been 9 cars for the past few weeks/months):

It looks like 9 car 345s are being used on the Paddington - Reading services (and presumably the Heathrow services too, although the car indicator is blank on Tiger for these today).
 

JonathanH

Veteran Member
Joined
29 May 2011
Messages
23,261
Paddington - Hayes & Harlington services are showing as 7 cars on Tiger today (have been 9 cars for the past few weeks/months):

It looks like 9 car 345s are being used on the Paddington - Reading services (and presumably the Heathrow services too, although the car indicator is blank on Tiger for these today).
Yes, all of the Reading services were 9-cars today (as were 5G70/5G71 (the Maidenhead spare) and 5G74-5G79 (the morning test run described a few weeks ago)) although not the 5G50-5G53 runs which was 345013. There is also a series of test runs to Heathrow today.

A bit surprised that they can't muster 14 serviceable 9-car units from a fleet of 18 but perhaps they want to keep the 7-car units operational.

I reckon they have 12 units in passenger service and 3 on empty trips - eg 15 in use. 345055 and 345068 were both taken out of service yesterday after failures.
 

Snow1964

Established Member
Joined
7 Oct 2019
Messages
11,019
Location
West Wiltshire
It would be technically possible, once the central section opens for passenger traffic, but It definitely wouldn’t be operationally practical. It would virtually preclude any kind of service running on the central section other than these eastbound Crossrail terminators - and if you’re running onto the central section, you might as well go to Abbey Wood or somewhere designed for terminating eastbound services.

It may be possible before central section opens as the main testing could probably be done without using the Bond Street-Paddington section (more than enough room to do testing on remainder of unopened section)

However to reach Paddington (crossrail) in service from the west, need the testing completed on the signalling transition from the west. Realistically would only be of any use if central section wasn’t ready and there was say an Abbey wood - Liverpool Street shuttle other end. Otherwise might as well just open it throughout to Abbey Wood in one go.
 

TT-ONR-NRN

Veteran Member
Joined
30 Dec 2016
Messages
12,731
Location
Worcester
With 9-car units now operating to Hayes, two 7-car units (345006 and 345007) have been dragged to Ilford over the last two days to bolster the east side fleet.

18 7-car units at Ilford now 345003/05/06/07/08/09/10/11/12/14/15/16/17/22/38/39/42/56, and
12 7-car units at Old Oak Depot 345013/20/29/40/44/47/49/51/52/57/63/64

This facilitates the change in east-side operations such that the remaining 315s are diagrammed to work peak only from next week.

As noted above, the 9-car fleet at Old Oak Depot available for passenger services appears to be limited for the time being to 345021/23/28/30/60/65/68/70 for five diagrams. Reading services require 9 7-car units and the spare to run 5G70/5G71/5G72/5G73 - ie a hot spare at Maidenhead in the morning peak and Ladbroke Grove in the evening peak - ie 12 units for 10 diagrams.

345023 reported in service today on Heathrow services for the first time, taking the number which have carried passengers to 52 of the 70 units - just 345001/02/18/19/24/25/26/31/32/33/36/41/45/46/48/50/67/69 to go by my reckoning.
I think that would simply have been a mistake - 345052 was on the east side during May - it moved from Ilford to Old Oak Depot in the middle of June and has been operating west side services as a 7-car unit ever since.

There have only been six units converted from 7-car to 9-car and four of those were converted back - 345055 and 345059 were converted back to 9-cars during May and have been used in service as such since then. 345047 and 345057 appear to have been in the conversion process when the withdrawal of 9-car operation to Reading happened in June and reappeared as 7-cars (along with 345063 and 345064 which had to be converted back from 9-car units).


There are two groups of these - 24 units have now carried passengers as 9-car units (including 345023/63/64):
345021/27/28/37/53/54/58/60 were in the group of units which appear not to have operated in passenger service after the withdrawal of 9-car operation to Reading in June.
345004/30/34/35/43/55/59/61/62/65/66/68/70 were in the group of units which operated Hayes and Heathrow services from late July to mid-September and Heathrow services since then.

The units with the new software now in use appear to be 345021/28/60 from the first group and 345030/43/65/68/70 from the second group together with 345023 which appears to have been the test unit for this upgrade. A fleet of nine units appears to be sufficient for five diagrams.

There aren't many observations posted of the units involved in Tunnel workings - it was 345024/25/31/32/33/36/41/50/67/69 but with the ramping up of testing, it would appear that more units are likely to be needed.

It would seem reasonable that the remainder of the fleet not being used for Tunnel testing or passenger service are simply parked at Old Oak Depot spare. I assume that as more units are upgraded to the next software type, there will be a return to operation for them.

EDIT: 345043 added to the list of 345s back in service today.

Is there any update on the fleet status? :)
 

Mollman

Established Member
Joined
21 Sep 2016
Messages
1,697
Location
Preston

kevin_roche

Member
Joined
26 Feb 2019
Messages
997
The latest monthly report by Mark Wild to the London Assembly Transport Committee is now available on the TfL website.


It contains much that we already know. Two items that I found interesting confirmation are on page 3 under the heading of Operational Readiness.

Following a software update, nine car trains (Full Length Units) have been re-introduced on services between Paddington and Hayes & Harlington. This has allowed an increase in service to Hanwell which is now receiving four trains per hour.
There are TfL Traffic Managers working in the Route Control Centresignalling trains - a first for this project.
 

JonathanH

Veteran Member
Joined
29 May 2011
Messages
23,261
Is there any update on the fleet status? :)
I'm only an interested observer keeping an eye on these units using publicly available sources, but the main update is that the fleet of 9-car units working Reading / Heathrow / Hayes services appears to currently be 18 units, by observation: 345004/21/23/28/30/34/35/43/55/58/59/60/61/62/65/66/68/70

No other changes as far as I can make out.
 

Yindee8191

Member
Joined
16 Mar 2019
Messages
181
I'd agree - do they reduce the 9s to 7s at OOC?
I don’t think they’re removing any coaches at the moment, all the sets they’ve used as 7-cars are out there now. In fact, they’re possibly now lengthening the 7-cars back to 9 cars in preparation for full trial running, which might explain what those two are doing there.
 

trivran

Member
Joined
23 Apr 2012
Messages
191
TfL Rail trains on the former Heathrow Connect I have used in recent days have been 9 cars.
 

itfcfan

Member
Joined
7 May 2011
Messages
346
Yes, all of the Reading services were 9-cars today (as were 5G70/5G71 (the Maidenhead spare) and 5G74-5G79 (the morning test run described a few weeks ago)) although not the 5G50-5G53 runs which was 345013. There is also a series of test runs to Heathrow today.

A bit surprised that they can't muster 14 serviceable 9-car units from a fleet of 18 but perhaps they want to keep the 7-car units operational.

I reckon they have 12 units in passenger service and 3 on empty trips - eg 15 in use. 345055 and 345068 were both taken out of service yesterday after failures.
Tiger shows Paddington - Hayes & Harlington services back as 9 car 345s today:
 

Gulf1159

Member
Joined
14 Jul 2018
Messages
176

JonathanH

Veteran Member
Joined
29 May 2011
Messages
23,261
is 345039 still a seven car unit or has it been lengthened?
It is still a 7-car. 9-car units can't operate on the east side yet and it was working there until it moved.

No observations of any 7-car units being lengthened yet. Indeed, a number of them have been out on empty trips as 7-cars. Both 345052 and 345064 observed as 7-cars on the Railcam at Slough today working 5G74 0823 Old Oak Depot to Reading and 5G50 1013 Old Oak Depot to Reading.
 

20atthemagnet

Member
Joined
1 Feb 2019
Messages
246
Location
England
Slightly off topic perhaps unless it’s relevant to 345s but new Balise beacons have appeared on the west side of Liverpool Street since work started on lengthening the platforms on platform 17 and 18. Anybody know what their purpose is? We already have CSDE beacons on all the platforms. They are identical to the square yellow ones you see littered around stratford for ATO. As usual NR have said nothing... drivers are questioning and nobody seems to know..
 

rebmcr

Established Member
Joined
15 Nov 2011
Messages
4,005
Location
St Neots
Slightly off topic perhaps unless it’s relevant to 345s but new Balise beacons have appeared on the west side of Liverpool Street since work started on lengthening the platforms on platform 17 and 18. Anybody know what their purpose is? We already have CSDE beacons on all the platforms. They are identical to the square yellow ones you see littered around stratford for ATO. As usual NR have said nothing... drivers are questioning and nobody seems to know..
I know there are additional balise along platforms in the core for accurate stopping, but that's CBTC and Liverpool Street isn't...

Perhaps Pway looked at the specs for Liverpool Street Low Level and accidentally applied them up top?
 