Class 158 train on Southport line

Status
Not open for further replies.

Llama

Established Member
Joined
29 Apr 2014
Messages
1,959
70 tonnes is way wide of the mark, the underframes probably did need strengthening but not so much that it would more than double the weight of the DTS cars. A 319 unit weighs in at ~140t (~30/50/30/30t per vehicle). Unless Brush thought it would be a good wheeze to equip the 769s with redundant prime movers from HST power cars I think we can discount that.
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

sprinterguy

Veteran Member
Joined
4 Mar 2010
Messages
11,573
Location
Macclesfield
The extra 70 tonnes comes from reinforcing the end coaches to carry the weight of the engines and all the other associated extra equipment. The end coaches were never designed to carry that much weight, and on the tests the coaches proved that they couldn't carry it without the underframe flexing.
You're suggesting that the weight of the driving cars has been increased from 30 to 65 tonnes apiece? I don't think so.

The article I linked states that 7.5 tonnes is the total weight increase after all modifications have been made, there's nothing in addition to that:
The modifications add approximately 7.5 tonnes to the DT vehicle. In discussion about the impact of this extra mass, Simon revealed that finite element analysis of the bodyshell had been carried out, that the axles are strong enough, and that the suspension and brake cylinder pressures had been adjusted to compensate for the additional mass.
 

Grannyjoans

Member
Joined
29 Mar 2017
Messages
403
That's not as bad as I thought then. After further reading into this I heard that when running on diesel the power going to the traction motors will be about half that when running on electric. These are going to be pretty slow when running on diesel.

Will 769 flex be ready for March ? I'm sure it is already a year and a half late, as it was originally meant to enter service in the May 2018 timetable change.
 