Any idea on what was planned for over the Xmas period?
Bridge at Teeside.
Track renewal at York
Bridge at Reading (Delayed I believe due water in foundations)
Bridge at Doncaster (Delayed by high winds)

Any more?
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

73001

Member
Joined
2 Jun 2010
Messages
447
Location
Liverpool
Bridge replacement at Sandhills (Merseyrail Northern Line) between 25th and 28th Dec and I think some work on the freight line to Seaforth Docks.
 

Rich_D3167

Member
Joined
14 Jun 2010
Messages
196
Location
Hull
Brocklesby Junction has been renewed over the period. Closed at 21:00 on Christmas Eve and reopened at 02:00 this morning.
 

68000

Member
Joined
27 Jan 2008
Messages
832
Closure of Paisley SC and transfer to West of Scotland SC
New line on the Paisley corridor
 

WatcherZero

Established Member
Joined
25 Feb 2010
Messages
10,272
Staff in pickers working on the OHLE at Wigan NW as I returned home 10pm on Boxing Day.
 

syorksdeano

Member
Joined
7 Jan 2011
Messages
779
Bridge replacement just outside Sheffield (Woodseats Road bridge) but delayed by high winds
 

The Planner

Veteran Member
Joined
15 Apr 2008
Messages
19,662
About bloody time, there has been a TSR on the down fast for what seems like years...
 

ChiefPlanner

Established Member
Joined
6 Sep 2011
Messages
8,316
Location
Herts
About bloody time, there has been a TSR on the down fast for what seems like years...

I understand the DF was put in with "the wrong kind of waterproofing" - hence a major dig out and re-laying of membranes etc. Been on a long time that TSR !
 

Waddon

Member
Joined
15 Sep 2009
Messages
469
Not really trackwork, but the old post office bridge across all the platforms at East Croydon was removed over Christmas
 

Minstral25

Established Member
Joined
10 Sep 2009
Messages
1,964
Location
Surrey
Again possibly not trackwork but Redhill to Purley is closed until 3rd January for I understand "embankment" works - but putting 1 and 1 together they are possibly upgrading the points at Stoats Nest Junction to allow faster crossover. Still needs a flyover!
 

boing_uk

Member
Joined
18 May 2009
Messages
619
Location
Blackburn
Hmm, well I dont know which bit of Brocklesby Jcn they have been working on, but the ride over the pointwork was quite lively in the 170 I was on GMB to MAN last night...
 

Old Timer

Established Member
Joined
24 Aug 2009
Messages
3,702
Location
On a plane somewhere at 35,000
I understand the DF was put in with "the wrong kind of waterproofing" - hence a major dig out and re-laying of membranes etc. Been on a long time that TSR !
Cannot see why this should have led to a TSR.

As Network Rail specified the formation design and supervised this work one wonders who will be paying the bill for the re-work ?
 

swt_passenger

Veteran Member
Joined
7 Apr 2010
Messages
34,257
Again possibly not trackwork but Redhill to Purley is closed until 3rd January for I understand "embankment" works - but putting 1 and 1 together they are possibly upgrading the points at Stoats Nest Junction to allow faster crossover. Still needs a flyover!

It really is embankment works though, as we discussed a few weeks back?

http://www.railforums.co.uk/showthread.php?t=56545
 

Minstral25

Established Member
Joined
10 Sep 2009
Messages
1,964
Location
Surrey
Status
Not open for further replies.

Top