Christmas Closure, Paddington to Ealing

Status
Not open for further replies.

flappy8

Member
Joined
20 Feb 2016
Messages
48
Can someone tell us what work is being undertaken in this closure period on this section? There was something on the news which implied a new flyover was being commissioned, but wasn't clear about where that was exactly. I've had a search about but haven't been able find anything.
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

PHILIPE

Veteran Member
Joined
14 Nov 2011
Messages
13,472
Location
Caerphilly
Can someone tell us what work is being undertaken in this closure period on this section? There was something on the news which implied a new flyover was being commissioned, but wasn't clear about where that was exactly. I've had a search about but haven't been able find anything.

Mentioned here, Post #5 in connection with Crossrail

http://www.railforums.co.uk/showthread.php?t=133790
 

LNW-GW Joint

Veteran Member
Joined
22 Feb 2011
Messages
21,923
Location
Mold, Clwyd
Can someone tell us what work is being undertaken in this closure period on this section? There was something on the news which implied a new flyover was being commissioned, but wasn't clear about where that was exactly. I've had a search about but haven't been able find anything.

It's a diveunder rather then a flyover, between Acton Main Line and Ealing Broadway.
It's to get freight trains to/from the Acton yard without blocking the Relief Lines.
Being commissioned at the moment.
http://www.networkrailmediacentre.c...erpass-at-acton-reaches-structural-completion

There are also many other bits and pieces associated with Crossrail, plus extending and upgrading the 1990s electrification into Paddington station.
 

Nippy

Member
Joined
13 Aug 2013
Messages
740
More specifically, it is to get freight out of Acton without blocking the Up Relief. The flyover being commissioned is at Airport Jn.
 

XDM

Member
Joined
9 Apr 2016
Messages
483
It's a diveunder rather then a flyover, between Acton Main Line and Ealing Broadway.
It's to get freight trains to/from the Acton yard without blocking the Relief Lines.
Being commissioned at the moment.
http://www.networkrailmediacentre.c...erpass-at-acton-reaches-structural-completion

This freight diveunder could be of great long term term use for passenger trains. It allows trains from Clapham junction via the West London line, & Stratford via the North London line to get to Heathrow without needing an inch of new track & without any conflicting moves on the great western or crossrail lines.
 

takno

Verified Rep - Traksy
Joined
9 Jul 2016
Messages
6,593
This freight diveunder could be of great long term term use for passenger trains. It allows trains from Clapham junction via the West London line, & Stratford via the North London line to get to Heathrow without needing an inch of new track & without any conflicting moves on the great western or crossrail lines.

Just for clarity, it's a passenger diveunder, going underneath the freight lines. Not sure how much value that will add in practice, going slow line through 5 stations which will be packed with crossrail traffic would be a fairly painful process, and most nll destinations at least would be better served by a change onto crossrail.
 

Phil.

Established Member
Joined
10 Oct 2015
Messages
1,323
Location
Penzance
Bit of help here please, I've not noticed what's happened there. Didn't trains used to be able to come down the bank from Acton Welles Junction and go into the yard without touching the up relief line? Were the freight lines taken out at sometime in the past?
 

Ianno87

Veteran Member
Joined
3 May 2015
Messages
15,214
Bit of help here please, I've not noticed what's happened there. Didn't trains used to be able to come down the bank from Acton Welles Junction and go into the yard without touching the up relief line? Were the freight lines taken out at sometime in the past?

No, that move will still be possible and is (effectively) unchanged.

The dive-under is to allow trains to depart Acton Yard towards the Reading direction without conflicting with Up Relief Line services towards Paddington / Crossrail, which are sent via the dive-under.

Up Relief passenger services will, I believe, still have an option of taking the 'flat' route when there is no conflicting freight service, as this will be very slightly faster than dropping via the dive-under.

The physical arrangement of the flyover also happens to mean that freights into the yard from the Reading direction will also 'fly over' the Up Relief dive under, but in operational terms this is no different to today.
 

Ianno87

Veteran Member
Joined
3 May 2015
Messages
15,214
This freight diveunder could be of great long term term use for passenger trains. It allows trains from Clapham junction via the West London line, & Stratford via the North London line to get to Heathrow without needing an inch of new track & without any conflicting moves on the great western or crossrail lines.

Good luck. The 'plain line' capacity of the Relief Lines from Ealing to Hayes will be very, very highly utilised nice Crossrail is up and running.
 

MarlowDonkey

Established Member
Joined
4 Apr 2013
Messages
1,870
Up Relief passenger services will, I believe, still have an option of taking the 'flat' route when there is no conflicting freight service, as this will be very slightly faster than dropping via the dive-under.

The existing diesel local services could use the dive-under even if the electrification is incomplete. Are they doing so ?
 

Phil.

Established Member
Joined
10 Oct 2015
Messages
1,323
Location
Penzance
No, that move will still be possible and is (effectively) unchanged.

The dive-under is to allow trains to depart Acton Yard towards the Reading direction without conflicting with Up Relief Line services towards Paddington / Crossrail, which are sent via the dive-under.

Up Relief passenger services will, I believe, still have an option of taking the 'flat' route when there is no conflicting freight service, as this will be very slightly faster than dropping via the dive-under.

The physical arrangement of the flyover also happens to mean that freights into the yard from the Reading direction will also 'fly over' the Up Relief dive under, but in operational terms this is no different to today.

Ah, thanks for that. I was confused - it don't take much - after reading the N.R. release which I interpreted as trains entering and leaving at the Paddington end.
 

LNW-GW Joint

Veteran Member
Joined
22 Feb 2011
Messages
21,923
Location
Mold, Clwyd
The existing diesel local services could use the dive-under even if the electrification is incomplete. Are they doing so ?

The Relief lines do not reopen until 3 January, when the new layout becomes fully signalled.
I expect the local wiring will be complete by then.
 