These piles could be signalling related but I think electrification is more likely.
It's difficult to judge the scale, but the diameter looks rather smaller than the mast piles going in elsewhere.
These piles could be signalling related but I think electrification is more likely.
It's difficult to judge the scale, but the diameter looks rather smaller than the mast piles going in elsewhere.
SimSig (Marylebone) has recently had its 2015 era revised to give what is planned to be the final layout of the Bicester South Junction to Oxford Parkway route. I would be interested to know how the name Gavray Junction came about: I guess something of local significance but I don't know the area.
I've managed to upload some photos here in the East West Rail thread.
http://www.railforums.co.uk/showpost.php?p=2263488&postcount=180
These piles could be signalling related but I think electrification is more likely. With London Road level crossing being closed to road traffic now until 14 September I have not been down to that part of town for a week and so I've not had a chance to investigate further or see if there any other piles elsewhere.
What a shame the original stone station buildings were demolished, seemingly after 1992.
Stephen Barker, an engineer who works for Chiltern Railways, will be talking about the project at a joint meeting organised by Railfuture and the Oxon & Bucks Rail Action Committee in Bicester on September 9.
http://www.obrag.org.uk/609/meeting-with-talk-by-chiltern-about-oxford-bicester-line/
Bicester London Road Level Crossing is now closed for a further month, until 5 am on 11 October according to local notices. Does anyone know what additional work is happening and why extended closure is necessary. At the moment people are fairly sympathetic - being August and school holidays the traffic is not too bad - although I can imagine people becoming rather less patient come September!
The www.bicestertooxfordcollaboration.com website hasn't been updated - it still lists the road closure as finishing on 14 September.
The road signs at the crossing have the 11 Oct date
Yes, if test running starts a week before the line opening date of Oct 26, that's cutting things a bit fine!
Yes, if test running starts a week before the line opening date of Oct 26, that's cutting things a bit fine!
The road signs at the crossing have the 11 Oct date
THE opening of the final section of new railway between central Oxford, Bicester and London could be delayed until next summer.
Work to complete the line between Oxford Parkway at Water Eaton, and Oxford station in the city centre, cannot take place until Network Rail secures final permissions from Oxford City Council.
The local authority must approve measures to reduce noise and vibration for nearby homes, with the last section of track being considered east of Burgess Fields in North Oxford.
It had been hoped by train operator Chiltern Railways that work could be complete by next spring.
But Network Rail consents manager Paul Panini said it was now not expected to be finished until next May or June, even if permission was secured by the end of this year.
He said: “This is the last section in our package of works.
“It always takes a little bit longer than you think to get these things agreed and we are where we are.
“We think we would get to completion of the tracks by April, with signalling works carried out in May or June.”
Unless anyone knows otherwise, could this be the first train to use the Bicester chord?
http://www.realtimetrains.co.uk/train/H16522/2015/09/14/advanced
Unless anyone knows otherwise, could this be the first train to use the Bicester chord?
http://www.realtimetrains.co.uk/train/H16522/2015/09/14/advanced
I'd be suprised if the stone train was the first timetabled train to run over the Chord. The path is the base path for 6M06, with the return working being 6V01. However I'm willing to be corrected nearer the time.
When the line between Aynho Junction and Bicester North was doubled, there were special ECS movements arranged to fully test the new infrastructure. IIRC they ran in the engineering possession, so wouldn't count as scheduled trains. The locos for these ECS's (specially hired 50s) sat outside our office outside hours.
It's down to run tomorrow as 6M06![]()
60103 "Flying Scotsman" due over the Bicester Chord!
According to Steam Dreams 2016 programme, 1st June is the date to watch out for!
The NIMBYs in Oxford will go absolutely nuts if they find out!
the risk of Port Meadow catching fire from sparks.
That's odd, it never happened during the heyday of steam. (As far as we know!)
Any firm indications as to when driver route knowledge training begins?
From this week's Bicester Advertiser
A MAP of Bicester sparked alarm after it suggested the London Road level crossing would close.
The map, available at council buildings, labelled the level crossing as shut from 2019 as residents claimed any closure would build a Berlin Wall between the east and west of the market town.