Central Scotland electirification

Status
Not open for further replies.

jopsuk

Veteran Member
Joined
13 May 2008
Messages
12,774
apparently this is still on. What will it actually consist of?
I know the core is the Edinburgh-Falkirk High-Glasgow Queen Street route and have seen Stirling mentioned as a near certainty. Where will the Stirling wires terminate? At present, many of the local services terminate at Dunblane or Alloa- so wires at least as far there?

With three out of four Glasgow-Edinburgh lines electrified, will the Shotts route be wired up too? Cumbernauld too? The infills are surely easier and cheaper than the delicate task of extending into Fife.
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

rail-britain

Established Member
Joined
12 Aug 2007
Messages
4,102
Only the EGE (Edinburgh Glasgow Electrification) has been approved
Otherwise known as GRIP Stage 1 and Stage 2

Stage 2 is to electrify the diversionery routes :
Greenhills - Falkirk Grahamston - Polmont
Greenhills - Garnqueen - Springburn
This would remove DMUs from the Glasgow - Cumbernauld - Falkirk Grahamston service

Equally, the timescale has been pushed back by 3 years
 

route:oxford

Established Member
Joined
1 Nov 2008
Messages
4,949
Only the EGE (Edinburgh Glasgow Electrification) has been approved
Otherwise known as GRIP Stage 1 and Stage 2

Stage 2 is to electrify the diversionery routes :
Greenhills - Falkirk Grahamston - Polmont
Greenhills - Garnqueen - Springburn
This would remove DMUs from the Glasgow - Cumbernauld - Falkirk Grahamston service

Equally, the timescale has been pushed back by 3 years

Hopefully common sense will prevail and at stage 2 the wires will stretch through Larbert ready for the final push to Perth.

The Kippenross tunnel is sometimes mentioned as a "problem", with the suggestion that it'll have to be permanently opened up and thus spoil the lawn at Kippenross house. Looking at multimap today, I noticed that Kippenross tunnel doesn't appear to have ventilation shafts. Is this normal for a fairly long tunnel?
 

rail-britain

Established Member
Joined
12 Aug 2007
Messages
4,102
Hopefully common sense will prevail and at stage 2 the wires will stretch through Larbert ready for the final push to Perth
There are no plans to extend beyond Carmuirs to Larbert

Stage 3 is for electrification of several routes to the south of Glasgow, in effect for all the services currently operated by Class 156 units
 

Railsigns

Established Member
Joined
15 Feb 2010
Messages
2,754
There are no plans to extend beyond Carmuirs to Larbert
The EGIP project includes electrification beyond Larbert to both Dunblane and Alloa and by all accounts it's still going ahead. Where have you heard anything to the contrary?
 

rail-britain

Established Member
Joined
12 Aug 2007
Messages
4,102
The details are on the Transport Scotland website
The EGIP project no longer applies and was replaced last year by the formal five stage project
All five stages have passed planning and finance, stages one and two have been approved for construction

It was always the case that stages one and two would be built together, once the required contractors have completed their involvement in stage one they then move to stage two

There is then the possibility that stage three can be merged with this project, this needs approval by the end of next year
If not, then a new set of contracts will be required
 

Railsigns

Established Member
Joined
15 Feb 2010
Messages
2,754
The Press seems to think the whole project is still going ahead...

Herald, 3rd July:

"Transport Scotland, the Government agency responsible for rail services, confirmed yesterday that it was committed to installing electric power lines on more than 200 miles of rail track in the central belt by 2016."

Scotsman, 4th July:

"Government agency Transport Scotland has confirmed that it was committed to installing electric power lines on more than 200 miles of rail track in the Central Belt by 2016."
 

chic

Member
Joined
23 Jul 2009
Messages
37
The details are on the Transport Scotland website
The EGIP project no longer applies and was replaced last year by the formal five stage project
All five stages have passed planning and finance, stages one and two have been approved for construction

It was always the case that stages one and two would be built together, once the required contractors have completed their involvement in stage one they then move to stage two

There is then the possibility that stage three can be merged with this project, this needs approval by the end of next year
If not, then a new set of contracts will be required

where on the TS website? egip isn't within TS's 'projects' page.
http://www.transportscotland.gov.uk/projects

have a look under 'rail' too.

search for ege or egip there, you won't find what you're talking about. so where?

news articles i saw today were:-

http://news.scotsman.com/transport-news/1bn-rail-upgrade-remains-on.6399328.jp

http://www.heraldscotland.com/news/...d-to-go-ahead-with-rail-electrification-1.103

There's an update on network rail's projects on their website, is that the source you mean?
http://www.networkrail.co.uk/aspx/6648.aspx

look for enhancements programme june 2010 update.
 