By the time you added additional turn back facilities and electrified the route would it really be a short term solution?
It would certainly be a lot quicker than building platforms 15/16!
By the time you added additional turn back facilities and electrified the route would it really be a short term solution?
It would certainly be a lot quicker than building platforms 15/16!

Someone else tried that a year ago. It got nowhere; https://petition.parliament.uk/archived/petitions/232155
Very aware of that, no harm in trying though.
My logic was if I could share it to the forum early on and have a big push for it, it may happen. Unfortunately, there is bigger news out there at the moment, and I can't exactly hand out flyers to non-existent commuters. My hope is if this all clears up by perhaps August time, I can have a go then.
Railfuture has a whole suite of options for freight developed, including the above, to relieve pressure on the corridor.Has anyone suggested reinstating the line between Timperley in the East and Cadishead?
That way you could send some services via Stockport!
If you wanted to you could also connect it to Newton-le-willows if the line through Culcheth and construct a new short chord.
From Google maps both lines are intact!
Define "developed"Railfuture has a whole suite of options for freight developed, including the above, to relieve pressure on the corridor.
Railfuture has a whole suite of options for freight developed, including the above, to relieve pressure on the corridor.
It would be slower for a start so I doubt anyone would use it to/from Manchester, nice chunk of single line too.Thanks, but what do folk think about reinstating this line and sending some passenger services via Stockport ?
And having to cross the WCML on the flat at Edgeley 'southbound'.It would be slower for a start so I doubt anyone would use it to/from Manchester, nice chunk of single line too.
And having to cross the WCML on the flat at Edgeley 'southbound'.
While the trackbed from Glazebrook to Skelton Junction is still extant, the line is derelict and what remains of the track hasn't been used for many years. The line is of minimal potential value for passenger services, and is of limited potential use for goods services. Normally, the main CLC line westwards via Glazebrook is full with passenger services, and has no connectivity other than to Liverpool, so a line would need to be reconstructed from Glazebrook via Culcheth (the old GC branch to Wigan) to join the Chat Moss route east of Newton-le-Willows.Has anyone suggested reinstating the line between Timperley in the East and Cadishead? That way you could send some services via Stockport! If you wanted to you could also connect it to Newton-le-willows if the line through Culcheth and construct a new short chord. From Google maps both lines are intact!
I believe from other posts that this is only a temporary measure because of the current relative lack of passenger trains on this easier route.However, I was surprised to note from RTT that several daily Liverpool to Drax biomass trains run via Chat Moss, Manchester Oxford Road, Guide Bridge and Standedge! This adds to traffic via the Castlefield corridor and cuts right across the Piccadilly station throat. Why can't these trains travel via Victoria, or is the climb from Victoria to Miles Platting too onerous? I had thought they were routed via Northwich, Skelton Junction and Denton.
You are correct that Miles Platting is a bit steep, though tests have been taking place to see how heavier loads cope from starting from a stand etc..It is difficult to route trains from the Trafford Park FLT other than via the Castlefield corridor, which is the main source of the goods trains via this route. However, I was surprised to note from RTT that several daily Liverpool to Drax biomass trains run via Chat Moss, Manchester Oxford Road, Guide Bridge and Standedge! This adds to traffic via the Castlefield corridor and cuts right across the Piccadilly station throat. Why can't these trains travel via Victoria, or is the climb from Victoria to Miles Platting too onerous? I had thought they were routed via Northwich, Skelton Junction and Denton.
Obviously NOT fully designed and costed. Even NR seem incapable of doing that without spending £millions. However, enough thought has gone into the matter to say that any given route is technically feasible.Define "developed"
With regards to the Freightliner Terminal at Trafford Park is there any possibility of using the old exit onto the Trafford Park rail system and heading out that way with a crossing of the ship canal near Eccles? Or has metrolink taken all the spare land in its expansion to the Trafford Centre?
James
Those lines are all at-grade crossings with the road network.
With the very few services involved would it make much of a difference?
James
The biggest issue there is the CLC route, fully diesel and the only way into Manchester. Wires cannot come soon enough, nor can a transfer station at Cornbrook to distribute passengers across Manchester more evenly (with integrated/non-punitive Met onwards ticketing).
I can barely see a line in the North West more suitable to wires, and high acceleration EMUs, than that. That said, near enough all of the benefits (barring the environmental one) would be gained by operating all Northern services on the route using Class 195s for the superb acceleration they have. A use for the 2-car sets perhaps? Gangways don't really matter on commuter services.
My inclination for a service pattern would be 4tph - 2 of them all stations to Warrington then Birchwood, Urmston, Deansgate... and 2 of them Liverpool SP, Widnes, Warrington West, Warrington C then all stations[1] to Manchester Picc (and beyond). I don't know if you could fit the EMT in between those though?
[1] Glazebrook, hmm. I think I'd still give it 2tph because that's then Merseyrail style simplicity which makes the timetable easy to use. It's sort of the line's Capenhurst - in the middle of nowhere when every other station is urban or suburban.