Cardiff/Swansea electrics,as the Professor sees it

Status
Not open for further replies.
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

Greenback

Emeritus Moderator
Joined
9 Aug 2009
Messages
15,268
Location
Llanelli
I would love to see electrificayion of every rail line in Wales, but sadly it is just not practical. As oil prices increase electric power may become more economically attractive, assuming that electricity does not also massively increase in price, but at the moment, the wires have to stop at Cardiff. I didn't expect them tog et that far!
 
Joined
12 Dec 2009
Messages
634
Location
Carmarthen
where it says "shaving 20min off the journey" (I assume Paddington - Cardiff), where would it gain time? The line speed would still be the same or am I wrong? Will trains will be permitted higher speeds than at present? Or does an electric propelled train accelerate that much quicker than diesel, that 20min can be saved?
 

tbtc

Veteran Member
Joined
16 Dec 2008
Messages
18,061
Location
Reston City Centre
where it says "shaving 20min off the journey" (I assume Paddington - Cardiff), where would it gain time? The line speed would still be the same or am I wrong? Will trains will be permitted higher speeds than at present? Or does an electric propelled train accelerate that much quicker than diesel, that 20min can be saved?

Acceleration is generally a lot better on electric, but the service to Cardiff doesn't stop *that* often for the savings to be *that* significant (e.g. the total time spent at Reading/ Swindon/ Bristol Parkway/ Newport isn't going to be twenty minutes, so where you can *save* twenty minutes from is beyond me).

Sadly we seem to need a headline "saving" like this to justify new investment - not enough to say it'll shave a few minutes off each journey, we'll have to save one ultra-fast service each day just to grab attention... :(
 

The Planner

Veteran Member
Joined
15 Apr 2008
Messages
19,737
Got it in one, there will be a single non-stop journey that is stripped to its bare bones to grab the headline, much like the 0730 New St - Euston.
 

WatcherZero

Established Member
Joined
25 Feb 2010
Messages
10,272
Acceleration is generally a lot better on electric, but the service to Cardiff doesn't stop *that* often for the savings to be *that* significant (e.g. the total time spent at Reading/ Swindon/ Bristol Parkway/ Newport isn't going to be twenty minutes, so where you can *save* twenty minutes from is beyond me).

Sadly we seem to need a headline "saving" like this to justify new investment - not enough to say it'll shave a few minutes off each journey, we'll have to save one ultra-fast service each day just to grab attention... :(

Didnt the governments IEP time savings boast 30 minute saving to Bristol but only 20 minute saving to Cardiff indicating it would lose some time on that section?
 

dalmahoyhill

Member
Joined
7 Jan 2011
Messages
93
Location
Scotland
the 20 min saving probably includes the refurb package between severn tunnel and cardiff within that time saving. I understand the works including signalling will improve line speeds and capacity.

yes electric trains accelerate much faster, than can climb gradients better as well.
ediinburgh glasgow is going to drop by 9 mins from 49 to 40mins over 50 miles so 20 min saving between london and cardiff seems possible,
 

bluenoxid

Established Member
Joined
9 Feb 2008
Messages
2,667
What???

It is a welsh assembly decision. The line is in Wales, therefore the electrification should be Welsh.

The HST upgrade should keep the train running long enough for them to scrimp and save.
 

The Planner

Veteran Member
Joined
15 Apr 2008
Messages
19,737
the 20 min saving probably includes the refurb package between severn tunnel and cardiff within that time saving. I understand the works including signalling will improve line speeds and capacity.

Cardiff and Newport re-signalling is capacity driven, there aren't any massive linespeed increases. Severn Tunnel to Maindee is already done and has been for a little while.
 

WatcherZero

Established Member
Joined
25 Feb 2010
Messages
10,272
the 20 min saving probably includes the refurb package between severn tunnel and cardiff within that time saving. I understand the works including signalling will improve line speeds and capacity.

yes electric trains accelerate much faster, than can climb gradients better as well.
ediinburgh glasgow is going to drop by 9 mins from 49 to 40mins over 50 miles so 20 min saving between london and cardiff seems possible,

No, it stated a time saving of 30 minutes London-Bristol but a time saving of only 20 minutes London-Cardiff indicating it was actually losing time beyond Bristol. This is similar to HS2 losing some time on the Scotland stretch because they dont tilt, but in this case im unsure of why it would be losing time.
 

Solaris

Member
Joined
17 Jun 2010
Messages
145
Quick stats.... if the Cardiff London train journey could achieve the same average speed currently possible on the WCML (av 100 mph) then the trip would take less than 90 mins?

Rail infrastructre in Wales is not devolved (even if NR re-organise) and is a matter for the DfT in London.

The GWML upgrade (electrification and signalling) will allow running of up to 140mph on some sections between Bristol and Reading.
 