Canopy / Access for All works at Luton

Status
Not open for further replies.

Edvid

Established Member
Joined
7 Feb 2008
Messages
2,501
Over the next couple of years Network Rail are set to replace the leaking canopies on the platform 1/2 island and then build a new footbridge with lifts.

It's not a wholesale rebuild (which quite honestly the station needs), but it's a welcome development nonetheless. In the past 40+ years the station building is the only thing that hasn't changed in that part of town.

Friday 22 Sep 2023


Construction work begins on major improvements at Luton station​

Region & Route: Eastern | Eastern: East Midlands
Network Rail has started work at Luton station as part of an extensive programme of improvements and upgrades designed to improve passenger experience.

The work will see the station canopies on platform 1 and 2 replaced, and a new, accessible bridge and three lifts installed.

Over the next seven weeks, scaffolding will be put up on platform 1 and 2 for the decades-old canopies to be replaced. Storm damage had caused them to leak.

Work is expected to be completed in spring 2024, and platforms are planned to remain open throughout.

Meanwhile, progress on delivering accessibility improvements is continuing with work on the station’s Access for All scheme expected to start on site in spring 2024.

The scheme will see a new, accessible bridge installed with three lifts to make sure that all passengers can use the station freely and easily.

Accessibility work is scheduled to be completed in spring 2025.

Gary Walsh, route director for Network Rail in the East Midlands, said: “I know how strongly the community who use Luton station feel about these improvements and am pleased they will be able to see progress on site very soon.

“Inevitably the bridge and lift work will cause disruption to those who use the station. We’ve worked hard to design our scheme to keep disruption to the minimum possible and I thank passengers for their patience and understanding while we erect the scaffolding. Safety measures will be in place to protect passengers using the platforms.

“Work to the canopies and the subsequent work to make the station more accessible is essential to make Luton station better for all those who use it.”

Govia Thameslink Railway Customer Services Director Jenny Saunders said: "Our passengers at Luton rightly deserve better station facilities and we're delighted this work is now going to start."

 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

Mag_seven

Forum Staff
Staff Member
Global Moderator
Joined
1 Sep 2014
Messages
11,987
Location
here to eternity
Over the next couple of years Network Rail are set to replace the leaking canopies on the platform 1/2 island and then build a new footbridge with lifts.

It's not a wholesale rebuild (which quite honestly the station needs), but it's a welcome development nonetheless. In the past 40+ years the station building is the only thing that hasn't changed in that part of town.




Thread reopened to allow an update from @Edvid
 

Edvid

Established Member
Joined
7 Feb 2008
Messages
2,501
Canopy works are done, but works to build the new accessible footbridge are still yet to start. Detailed design work by Network Rail revealed platform extensions built in 2010 would be too weak to support it, so strengthening works will be required (and that means an increased budget); spring 2025 is the latest target start date.

Article below includes background on Luton's interminable wait for the delivery of step-free access to all platforms.


Why has our station waited 18 years for lifts?​

Ben Schofield
BBC News, Bedfordshire
Fae Southwell
BBC News, Bedfordshire

Published 18 December 2024, 06:27 GMT

For almost two decades, passengers at a town's main railway station have repeatedly been promised lifts - but they have never arrived.

Travellers at Luton, named among England's 10 worst stations in 2009, still face flights of stairs to reach most platforms. Gold medal-winning Paralympian and wheelchair user Baroness Tanni Grey-Thompson said the 18-year wait was "ridiculous" and "completely unacceptable". Network Rail acknowledged "how frustrating the delays are" and apologised. It plans to start preparatory work in the spring but did not know how long the project would take or how much it would cost. So what has the wait meant for passengers with disabilities?

Last year, 3.6 million passengers used Luton - the 144th busiest station in the UK. Karen James, 53, is unlikely to be among them in the future. In May, she moved away from the Bedfordshire town where she had lived all her life, partly due to the continued lack of lifts. A wheelchair user since 2018, she has osteoarthritis in her back, and fibromyalgia which causes chronic fatigue, brain fog and dizziness. She previously used the station to visit her son and 20-month-old grandson in Welwyn in neighbouring Hertfordshire. But four of its five platforms are only accessible by stairs, which she finds agonising and take her "forever" to climb. "My husband would have to bump down the wheelchair," she added. Going back up was worse than descending. "It took me a good 20 minutes or so to get up the steps and I was just exhausted," she said. "When you've got disabilities, you should be able to have access to everything you need, like transport."

Luton's passengers were first promised better access in 2006 when Labour ministers launched an Access for All fund, promising £370m over 10 years. Luton was among the first 42 stations in line for some of that investment, which the Department for Transport (DfT) said would "generally" include "the provision of lifts or ramps". Three years later, then transport secretary Lord Adonis promised a portion of a £50m improvement fund. In 2014, the Conservative government announced Luton would share another £100m from Access for All, when railways minister Baroness Kramer said the money would "make a real difference to the lives of disabled passengers". Projects would be "completed by 2019", but work at Luton and several other stations was postponed.

Platforms 'not strong enough'​

Another announcement in 2019 said the project would be re-started, with work "completed by the end of March 2024". For much of this period, there was an ambition to completely rebuild the station, partly financed through access funding, but it did not get off the ground. Most recently, station owner Network Rail said "detailed design work" had revealed platform extensions - installed in 2010 - were not strong enough to bear the weight of the planned lifts. Strengthening work is due to begin next spring.

Marie McCormick, 64, has dystonia, which causes muscle spasms in her upper limbs and neck, and she said the situation was "discriminatory". "Policymakers have a duty of care to provide equality in public spaces," she said. She would like to use trains more for days out and hospital appointments, but said using the steps would give her "palpitations". Poor access made her and others with disabilities vulnerable to "isolation.... it just exacerbates the social exclusion".

Baroness Grey-Thompson, who crawled off a train in London in the summer when assistance did not arrive after 20 minutes, said there was a "massive sense of frustration" in the failure to bring ageing stations up to date. She said Luton's 18-year wait seemed "a ridiculous amount of time". "When people see the station is going to get Access for All funding, there is an assumption that there's going to be pretty major change," she said. "If the funding's there and the will is there, these sort of things should just happen. There needs to be some really serious questions asked about why is it so complicated to do it."

In a statement, the independent London TravelWatch watchdog said implementation had been "painfully slow" and "extremely frustrating" for wheelchair users, as well as for passengers with buggies or heavy luggage. "It is one of [our] key priorities to ensure this programme of work is better implemented across the network, to ensure all stations are more accessible," it said. "We understand the work at Luton will begin next spring, and look forward to this work being completed without further delays."

Luton South and South Bedfordshire Labour MP Rachel Hopkins said she had heard "various reasons" for the delays. "It was pushed from one budget period to the next budget period, then it was Covid, then it was all the designs, then it was 'we're trying to start, but we found some problems'," she said. She said Network Rail "isn't project-managing it properly enough". "For them to keep delaying - I don't think it's acceptable."

Station operator Govia Thameslink said it wanted lifts installed "as soon as possible" and was supporting Network Rail. Station staff, it added, would help passengers and arrange alternative transport to Luton Airport Parkway for those unable to manage stairs. Since Access for All launched, step-free accessible routes have been built at more than 250 stations. Gavin Crook, principal programme sponsor for Network Rail's East Midlands route, said: "We are committed to providing access improvements at Luton station and are sorry this is taking longer that we would like." A DfT spokesperson said: "Everyone should be able to travel with ease and confidence, which is why this government is committed to improving the accessibility of our railways. While previous plans for improvements at Luton station were delayed at the time due to design challenges, Network Rail is now responsible for the works, which are progressing."
 

edwin_m

Veteran Member
Joined
21 Apr 2013
Messages
28,659
Location
Nottingham
Unlike some deferred or otherwise incomplete AfA stations on the list, Luton does at least have a fully accessible station a short distance away linked by an accessible bus route.

I do agree though that it's a pretty grim station from the user's point of view.
 

Edvid

Established Member
Joined
7 Feb 2008
Messages
2,501
Thank you Cowley

Following last year's platform-strengthening, works to deliver the accessible footbridge are now underway. :smile:

As part of the Government’s Access for All programme, the station is being upgraded with a new fully accessible footbridge and three lifts.

Currently, only platform 5 has step-free access. The improvements will provide an unobstructed, accessible route from the main entrance and drop off points to all platforms.

This will make the station safer and more convenient for passengers – especially those with reduced mobility, or travelling with items like prams or luggage.

The main construction work is taking place from February to December. The bridge span will be installed in June, followed by the lifts towards the end of 2026. The overall project is planned for completion in spring 2027.

There's also a poster at the station which describes arrangements for when the taxi rank / drop-off area is relocated / closed.

IMG_20260207_120349568_HDRe.jpg
 

reduke

Member
Joined
31 Aug 2017
Messages
96
That photo is not particularly inspiring...

It suggests that passengers from the north of the station may need to cross the existing footbridge, go down the lift to outside platform 5, re-enter the station, go up the other lift on platform 5, and then down again to their required platform...

Does anyone have any more information?
 

ChilliSauce

On Moderation
Joined
28 Oct 2025
Messages
328
That photo is not particularly inspiring...

It suggests that passengers from the north of the station may need to cross the existing footbridge, go down the lift to outside platform 5, re-enter the station, go up the other lift on platform 5, and then down again to their required platform...

Does anyone have any more information?
That is how I interpreted it . And from the Ticket Office the same protracted route to the step free access to platforms .

Overall this looks a bit like a sticky plaster solution to the overall situation at Luton with respect to the Ticket Hall, staircase to platform 1&2 ...

This new bridge will in effect be totally useless to anyone who uses the station car park. So could end up as an AfA white elephant ..
 