• Our new ticketing site is now live! Using either this or the original site (both powered by TrainSplit) helps support the running of the forum with every ticket purchase! Find out more and ask any questions/give us feedback in this thread!

Cambourne to Cambridge Busway

Status
Not open for further replies.

nerd

Member
Joined
4 May 2011
Messages
524
http://www.gccitydeal.co.uk/citydeal/info/2/transport/1/transport_projects_and_consultations/2

The preferred option is set out in the 'Quick Guide' paper. What is proposed is a dedicated bus-only road running south of the current A428.

Publicity states that it won't use guide-wheels and tracks; just a standard road for buses only (as per Gosport, or Runcorn).

But I can't find from the papers why the decision was made not to go for a second tracked guideway - as the options paper apparently evaluated the proposals applying guideway costs.

Does anyone know?

maybe:

- guided track costs too high; with no concomitant benefit?
- bad experience of poor constructon standards on the existing guideway?
- easier legally to build a road than a guideway - no need for a TWA order?

but someone must know the reason.
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

WatcherZero

Established Member
Joined
25 Feb 2010
Messages
10,272
Probably because they are value engineering the **** out of it. Their 'preferred' option has a BCR of 0.2 which is abysmal, but the other options are even worse;

Option 2: 0.489
Option 4: 0.043
Option 5: 0.054

Note that in the executive report for councillors they neglect to mention Option 1 the do minimum option (no new infrastructure just improve existing bus shelters) which has a BCR of 1.22 which is far superior.
 
Status
Not open for further replies.

Top