Blackpool - Manchester Electrification

Status
Not open for further replies.

Muenchener

Member
Joined
31 May 2018
Messages
142
Work party in evidence North of BSV last night, around PN34, between 00:45 and 05:30. Last minute check of the job before energizing up to Eux Jct. tonight/tomorrow morning... It's coming together at last.
Anyone know if the 390 test train is booked for certain next week?
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

SansHache

Member
Joined
31 Mar 2015
Messages
182
Location
Manchester
Work party in evidence North of BSV last night, around PN34, between 00:45 and 05:30. Last minute check of the job before energizing up to Eux Jct. tonight/tomorrow morning... It's coming together at last.
Anyone know if the 390 test train is booked for certain next week?

Test trains have been postponed to the end of the month as the testing strategy has evolved with the staged energisation of the route.
 

snowball

Established Member
Joined
4 Mar 2013
Messages
8,144
Location
Leeds
Work party in evidence North of BSV last night, around PN34, between 00:45 and 05:30. Last minute check of the job before energizing up to Eux Jct. tonight/tomorrow morning... It's coming together at last.
Anyone know if the 390 test train is booked for certain next week?
Test trains have been postponed to the end of the month as the testing strategy has evolved with the staged energisation of the route.
In other words, presumably, there's not much point in keeping the booking for the Perndolino if Crescent to Buckshaw won't be energised in time.
 

SansHache

Member
Joined
31 Mar 2015
Messages
182
Location
Manchester
In other words, presumably, there's not much point in keeping the booking for the Perndolino if Crescent to Buckshaw won't be energised in time.
Yes, there is no benefit in running test trains over short sections of the route, particularly the Pendolino tests. The dynamic testing will take place once the complete route is electrified and the section proving tests have been completed.
 

absolutelymilk

Established Member
Joined
18 Jul 2015
Messages
1,587
Any idea when the Great Extension Lead will be connected and the first electric passenger train can run?
 

Muenchener

Member
Joined
31 May 2018
Messages
142
Yes, there is no benefit in running test trains over short sections of the route, particularly the Pendolino tests. The dynamic testing will take place once the complete route is electrified and the section proving tests have been completed.
As you say; little point in running fuller tests until end of Oct as frustrating as that is. Nov 2nd target date is now getting ever closer. This project has to be delivered for the Dec timetable change both for the credibility of both Network Rail and Northern Rail...
 

td97

Established Member
Joined
26 Jul 2017
Messages
1,556
Northern Rail
Arriva Rail North, or just Northern
Northern Rail ceased to exist as a TOC in 2016.
Even the BBC get it wrong and it grates me every time I see it
Also, the next timetable change for Northern will be May 2019 and not this December.
Any idea when the Great Extension Lead will be connected and the first electric passenger train can run?
Manchester - Preston electrification infrastructure is supposed to be complete by early December, with full electric service in May 2019. Whether it's 0% to 100% electrics overnight (a la Blackpool) or a gradual build up is anyone's guess.
 

Muenchener

Member
Joined
31 May 2018
Messages
142
Arriva Rail North, or just Northern
Northern Rail ceased to exist as a TOC in 2016.
Even the BBC get it wrong and it grates me every time I see it
Also, the next timetable change for Northern will be May 2019 and not this December.

Manchester - Preston electrification infrastructure is supposed to be complete by early December, with full electric service in May 2019. Whether it's 0% to 100% electrics overnight (a la Blackpool) or a gradual build up is anyone's guess.

Regardless of how the current incumbent TOC is identified there will be a timetable change in Dec; accepting that in the case of Northern those changes are, in the main, cosmetic with timings amended by a minute or two in most cases. My point being; they have had many months to deliver the timetable, with little in the way of variance, and yet have struggled to deliver the performance expected.
 

59CosG95

Established Member
Joined
18 Aug 2013
Messages
6,853
Location
Beeston (Notts)
Well, it's GSoP time again!
GSoP Post 22.1 - confirmed wires thro' Salford Central
Manchester Victoria - Preston; State of Play, week beginning 1st October 2018.
All masts in! Approx. 95/98 wire runs complete. Due to be treated as LIVE (Euxton Jct - Buckshaw Parkway; Ordsall Lane Jct - Salford Crescent; Deal St Jct - Windsor Bridge S Jct - Stanchion MG02 37) as of 1st October.
As wiring is not completed between Windsor Bridge South Jct & Buckshaw Parkway, testing has been postponed.

All mileages from Manchester Victoria. Bridge mileages are approximated where noted.

1. Man Vic Station (West End) - Man Vic West Jct - Deal Street Jct; 0m 0ch to 0m 32ch
Fully wired 2013-15. Platforms 1 & 2 at Man Vic have now been bedanglied. Already live.

2. Deal Street Jct - Salford Central (East End); 0m 32ch to 0m 59ch
Fully wired and LIVE as of 1/10/18.

3. Salford Central; 0m 59ch
Fully wired and LIVE as of 1/10/18. masted, most SPS (Small Part Steelwork e.g. dangly bits) up. The missing mast at the western end is now up, and is now in use as an SSA (self-supporting anchor), though insulators are yet to be spliced in.
The wires also overlap into the CEMEX (Hope Street) sidings. On the Down side (westbound) platform, protruding roof beams have been cut back, and earth wire (or Return Screening Conductor wire) ducting has been installed at shin height.

4. Salford Central (West End) - Windsor Bridge South Jct; 0m 59ch to 1m 46ch
Fully wired and LIVE as of 1/10/18.

5. Windsor Bridge South Jct - Windsor Bridge North Jct (inc. Salford Crescent); 1m 46ch to 1m 70ch
Windsor Bridge South Jct now wired (catenary/contact) from the Deal St direction on both the Salford Lines. Earth wires (+ AT wires) are also in situ here.
All lines through Salford Crescent are wired.
Repairs to the wooden fence on the eastern side have/are taken/taking place.
The crossovers at Agecroft South Jct, Windsor Bridge South Jct, and Windsor Bridge North Jct are also fully wired.
The "Windsor Link" (i.e. Windsor Bridge South Jct to Ordsall Lane Jct) is now LIVE.

6. Windsor Bridge North Jct - Bolton (South End); 1m 70ch to 10m 50ch
Both lines are FULLY wired from Windsor Bridge North Jct to Lever St Jct; wires continue through Bolton P3 & P4 towards Lostock & the WCML at Euxton Jct.
At Clifton, Drainage manhole modules are awaiting installation; temporary covers are over their future homes.
Bridge MVE1 27B (immediately NW of the M60 overbridge) is fully erected, but unopened, and work the walkway is not yet finished.
The Platform 5 Line is fully wired (C&C) from the points at Weston St to Orlando St Bridge.
South of Lever Street footbridge, the Up Line now has ATF wires installed.

7. Bolton Station; 10m 50ch
All masts in the station area are now in place. Earth wires now in. Canopies look complete, and platforms now fully open (i.e. no temp. fencing in sight).
Platform 1: ALL bolts & brackets now drilled into the glazed brick retaining wall opposite the platform, with cantilever arms swung into position.
Platform 2: Line is fully wired (C&C) from the points at Weston St to the SSA (Self-Supporting Anchor - aka "the wicketkeeper"). Insulators have yet to be installed on the wicketkeeper, and most fixings are still temporary. Buffers look finished.
Platform 3 (Up Bolton): Wired from Orlando St Bridge, through the station, and onwards to Lostock & the WCML. The majority of fixings used are permanent (some are still temporary). Blackburn Line overrun now installed.
Platform 4 (Down Bolton): Wired from Weston Street through P4 and onwards to Lostock & the WCML.
Platform 5: Wire-ready, with cantilever arms swung into position. Shin-high ducting is now installed.

8. Bolton (North End) - Lostock (South End); 10m 50ch to 13m 52ch
Both the Up (P3) & Down (P4) Bolton Lines have been wired from Deal St/Ordsall Lane Jcts, through Bolton station, past Lostock ATF Sectioning Station, over Lostock Jct and through Lostock Station to the existing wires at Golf Course Footbridge, thence continuing to the WCML.
The run of masts between Newport St & the NW end of P5 now have their earth wire affixed.
The crossover NW of Newport Street has not been wired yet.
Between the 2nd & 3rd bridges NW of Newport St (the unknown bridge & Dawes St), the mast in photo A732m has led a chequered life, being assembled, dismantled and then re-assembled! It has now been reinstated parallel to the two bridges it was installed between, and already bears the wires on the Down Bolton (temporary fixings, AFAIK).
Cable ducting troughs laid in the Down Side Cess between Bolton Station, past Newport Street, under Soho Street, Black Horse St & New St, and through Bullfield Tunnel.
The overrun along the line to Blackburn (as far as Bradshawgate Tunnel) has now been wired from P3; they have yet to reach there from P1.
Earth wire up on the Down side west of Moor St Tunnel.

Between Moor Lane & Lostock, Earth wires have already been strung.
Autotransformer wires now largely up between Moor Lane & Mayor St. Bridges, and between Lostock & Ladybridge (on both lines); they have now gone under Dean Clough Bridge & the Ladybridge on both sides.
A UTX has been installed in the "vee" in Lostock Jct; this now takes the ATF wires for both routes at Lostock Jct.
Most (if not all) wires are now up over Lostock Jct itself.
All masts now up on the Wigan overlap; earth wires now up too, in varying lengths on both sides. C&C wires also up on the overlap on both lines until the Limit of Wiring. Some dangly arms and all the termination insulators have not yet been installed.

9. Lostock Station; 13m 52ch
Switchgear box delivered 6th April '18. Over the August Bank Holiday Weekend, the two Autotransformers (AT1 & AT2) were delivered.
Both Preston Lines wired through the station to connect with the existing wires north of "Golf Course" footbridge.
Platform extension/resurfacing work complete on the Down platform (fully) and the Up platform (NW of the station bridge); work on the Up platform still ongoing east of the bridge.
ATF wires are in through the UTXs around the station; works are now presumed finished as the 4 drums of wire are now AWOL. (NB: ATF wires are confirmed only for the Preston lines; not sure if they were ever planned to go to Wigan. The UTX there may be future-proofing.)

10. Lostock (North End) - Euxton Jct; 13m 52ch to 25m 31ch
Two more UTXs have been installed in the "vee" between the Preston & Wigan lines, to the north of Lostock station; one takes the ATF wires for the Wigan Line, the other does the same for the Preston Line.
Immediately north of Lostock, the closest TTCs to the platforms have now sprouted part of their switchgear kit.
All C&C wires up on both lines from south of Bolton, through Lostock, Horwich, Blackrod & Adlington, over Yarrow Viaduct, through Chorley Station, Chorley Tunnel, the Flying Arches & Buckshaw Parkway to the WCML.
Temp. fixings still evident at Buckshaw Pkwy & Adlington stns. AT & earth wires not always present, but the C&C appears continuous.
On Yarrow Viaduct, the northern portal has now been installed. The Down side Earth wire is also up, but the Down side AT wire is still absent. (It is assumed this is replicated on the Up side.)
AT wires still need installation/remedial work at Station Rd Bridge (Blackrod; B5238; 17m 9ch).
At Railway Rd Bridge (Adlington; 19m 0148yds), AT wires (and some earth wires) still need to be installed.
Within Adlington Station, orangemen were digging ducting trenches for the Earthing bonds for the TTCs on the Up platform.
Orangemen at work on the footpath at the foot of the northern steps of Heath Charnock FB.
Through Chorley Station, all wires (including ATF wires) are installed.
The Buckshaw Parkway crossover is also wired.
Within Buckshaw Pkwy, the registration arms on the footbridge are now in position.

Do let me know if I've missed anything!
 
Last edited:

LDECRexile

Established Member
Joined
30 Jan 2014
Messages
2,149
Location
Southport, UK
I went from Southport via Bolton to The Salfords and back by train today.

The best news is that Paul was able to come for the first time for ages (I suspect first time this year.) He was in good form and a sight for sore eyes.

The worst news is that I couldn't see any evidence of activity at Bolton or Salford Crescent, to this layman they looked unchanged from last week.

The second best news has been shared by Chris, above. Although Paul refused to climb on my shoulders to test the wires at Salford Central by hand, they looked as if they could well have been juiced - no temporary fittings, signs everywhere.

Photos to follow.
 

Geeves

Established Member
Joined
6 Jan 2009
Messages
2,615
Location
Rochdale
Still alot of temporary fittings and pulleys around the place at Salford Crescent. Had a good old gander waiting for the train back to Vic. I would say another weekends work at least to finish all the bits and bobs especially down near the A6 bridge
 

LDECRexile

Established Member
Joined
30 Jan 2014
Messages
2,149
Location
Southport, UK

GRALISTAIR

Established Member
Joined
11 Apr 2012
Messages
10,457
Location
Preston Lancs
386t and 386r - I cant at the moment think of a witty reply. Wonderful photography - not sure if the BBC would give you a show as a comedian though!!
 

LNW-GW Joint

Veteran Member
Joined
22 Feb 2011
Messages
21,897
Location
Mold, Clwyd
Incomplete wiring on the Down visible today -
- no AT wire over most of Blackrod-Adlington
- one wire run through Lostock incomplete with temp fixings
- one wire run through Bolton P5 missing
- temporary fixings around Clifton and Salford Crescent P1

No wires east of Victoria, in fact there are at least 2 missing masts to install before wires can go up.
P1/2 bays at Victoria unwired
 

reg

Member
Joined
15 Mar 2015
Messages
70
Location
Bolton
Incomplete wiring on the Down visible today -
- no AT wire over most of Blackrod-Adlington
- one wire run through Lostock incomplete with temp fixings
- one wire run through Bolton P5 missing
- temporary fixings around Clifton and Salford Crescent P1

No wires east of Victoria, in fact there are at least 2 missing masts to install before wires can go up.
P1/2 bays at Victoria unwired
Bolton platform 5-a single wire now runs between Newport St/Orlando St bridges, mainly on temporary fittings.Photo later.
 

LNW-GW Joint

Veteran Member
Joined
22 Feb 2011
Messages
21,897
Location
Mold, Clwyd
Bolton platform 5-a single wire now runs between Newport St/Orlando St bridges, mainly on temporary fittings.Photo later.

Yes, I wasn't very clear.
I'm assuming it is the contact wire that is missing, but there are a couple of tensioners either side of Bolton P5 without wires, so something is missing.
 

Jamesrob637

Established Member
Joined
12 Aug 2016
Messages
6,056
Just about to do an entire run of the Bolton line from Preston to Manchester! Hope it'll look like a completely electrified line to my semi-professional eyes!
 

CAF397

Member
Joined
15 Sep 2010
Messages
1,095
Location
Lancashire
The section to Buckshaw Parkway can’t be live as there are still insulators on both the Catenary and Contact wires of the Up Bolton and Down Bolton immediately after the tracks diverge at Euxton Jn. Note these are actually the proper wires and not any feed in section wires.

Noticed them yesterday but needed another look today.
 

geoffk

On Moderation
Joined
4 Aug 2010
Messages
3,922
Location
Exeter
Arriva Rail North, or just Northern
Northern Rail ceased to exist as a TOC in 2016.
Even the BBC get it wrong and it grates me every time I see it
Also, the next timetable change for Northern will be May 2019 and not this December.

Manchester - Preston electrification infrastructure is supposed to be complete by early December, with full electric service in May 2019. Whether it's 0% to 100% electrics overnight (a la Blackpool) or a gradual build up is anyone's guess.
One would hope that, once the electrical installation has been tested, electric units can be infiltrated onto the line as there is a shortage of diesel units while emus are sitting in sidings. I travelled from Piccadilly to Horwich Parkway and back to Victoria today and electrification looked complete to my untrained eye but it's been suggested by those of you with better knowledge that some of the fittings are temporary.
 

snowball

Established Member
Joined
4 Mar 2013
Messages
8,144
Location
Leeds
One would hope that, once the electrical installation has been tested, electric units can be infiltrated onto the line as there is a shortage of diesel units while emus are sitting in sidings.
Except that it appears from #8521 that electric services can't be relied on until the extension lead is finished.
 

Elecman

Established Member
Joined
31 Dec 2013
Messages
3,567
Location
Lancashire
The section to Buckshaw Parkway can’t be live as there are still insulators on both the Catenary and Contact wires of the Up Bolton and Down Bolton immediately after the tracks diverge at Euxton Jn. Note these are actually the proper wires and not any feed in section wires.

Noticed them yesterday but needed another look today.

I would hope so as it is either a Neutral Section or a Sectioning insulator
 

Ianno87

Veteran Member
Joined
3 May 2015
Messages
15,214
Except that it appears from #8521 that electric services can't be relied on until the extension lead is finished.

Would it be technically possible to energise the wires without the extension lead, albeit with no power resilience?

Presumably the system would have to be designed to cope should the feed from Stalybridge be lost?
 

GRALISTAIR

Established Member
Joined
11 Apr 2012
Messages
10,457
Location
Preston Lancs
The section to Buckshaw Parkway can’t be live as there are still insulators on both the Catenary and Contact wires of the Up Bolton and Down Bolton immediately after the tracks diverge at Euxton Jn. Note these are actually the proper wires and not any feed in section wires.

Noticed them yesterday but needed another look today.
I would hope so as it is either a Neutral Section or a Sectioning insulator


Yes it should go WCML, live section, Neutral section (I will find the exact posts that tell you this) and then another live section into and just beyond Buckshee
 

reg

Member
Joined
15 Mar 2015
Messages
70
Location
Bolton
Bolton-platform 5 now has contact and catenary ,starting at a Tensorex drum in Bullfield (just past Morrisons footbridge) through to Orlando St. bridge.Temporary fixings again used in some places.
 