Sounds like something that was planned to happen before electrification but slipped.
Ref my previous post #7424 about the same subject.
The "information event" seems to have been arranged with indecent haste..less than a week from the announcement date and very little local, public notification.
I did attend and the NR staff were amenable. The bottom line is the crossing has been closed since the start of the electrification works and the "temporary" closure notice has been extended at least twice and now runs for another 6 months from July. They did miss renewing it for a week according to the dates on the local notices.
In the meantime the planning application has been parked in limbo. Part of the NR original planning application documentation stated "Closure of this level (pedestrian) crossing and the installation of a (foot) bridge was considered to be the most appropriate form of action as it completely eliminates risk on a stretch of railway. After detailed discussions and consideration to all the key factors, Network rail proposes to construct a ramped footbridge at Holts Lane level crossing". Fast forward 12 months and the options are now,
i) Closure of the level crossing with an agreed diversionary route. **
ii) Install a ramped and stepped footbridge.
iii) Install a stepped footbridge.
Any feedback has to be into NR by next week apparently and from the responses NR will then make a decision on the way forward.
** Part of the NR original planning application documentation stated "The option of a diversion was considered and discussed with the Rights Of Way Officer; the route was walked with the RoW officer who determined that the diversionary route would be too long and unsuitable.
The cynic in me thinks it will be a re-think and option i) thus saving a huge chunk of money on a project already suffering from a huge cost overrun.