Bolton-final mast has gone in on platform 5,also have pics of the angle brackets spotted by Joseph Locke.Will forward later

And here they are, added to Reg's album here:

https://www.flickr.com/photos/127646831@N03/albums/72157671732263863

and to the Combined Volume here:

https://www.flickr.com/photos/127646831@N03/albums/72157661069863633

Thank you Reg.

PS, I recommend readers look a Reg's album and compare his very first contribution (6072k) with his latest (A490m), they were taken from almost exactly the same spot....
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

LDECRexile

Established Member
Joined
30 Jan 2014
Messages
2,149
Location
Southport, UK
I have just read a public report of a meeting between the Ormskirk, Preston and Southport Travellers' Association (OPSTA) and Northern which took place last week.

It included the following paragraph which is pertinent to "our" line:

"Northern’s immediate objective and all efforts are to deliver a stable service and complete implementation of the May ’18 timetable by the end of July. Based on current service delivery performance this will be a stretch but they at least gave a progress update on resolving driver availability – all training to complete this month and new rest day working arrangements have been agreed with the unions."
 

snowball

Established Member
Joined
4 Mar 2013
Messages
8,144
Location
Leeds
Press release

https://www.networkrail.co.uk/feeds/holts-lane-footpath-crossing-information-event/

Residents in Poulton-le-Fylde, Lancashire, are invited to a public event to hear more about plans to close Holts Lane footpath crossing.

Representatives from Network Rail will present the proposed plan to allow the closure of the crossing for safety reasons. This is part of the Great North Rail Project (GNRP) Preston to Blackpool upgrade.

Residents will be able to review the latest information about the project and there will be an opportunity to ask questions.

The event will take place on Monday 9 July 2018, 4pm – 7pm at Poulton Civic Centre, Breck Road, FY6 7PU

Sounds like something that was planned to happen before electrification but slipped.
 

Bertie the bus

Established Member
Joined
15 Aug 2014
Messages
3,216
The closure of a foot crossing is part of the Great North Rail Project? This project gets me more excited the more I hear about it.
 

snowball

Established Member
Joined
4 Mar 2013
Messages
8,144
Location
Leeds
The closure of a foot crossing is part of the Great North Rail Project? This project gets me more excited the more I hear about it.
Network Rail seems to have an edict that everything it does in the north has to be described as part of that. "As part of the Great North Rail Project, Driver Bloggs took a personal needs break."

Meanwhile, the current issue of Rail (856, p. 11) has a piece on Manchester-Preston that seems mostly based on the press release quoted in post #7761, but with a little new info. Electric train testing is due to take place overnight on Oct 1, 8, 15 and 22. Minor work will continue until Feb 15.

The latter is a very precise statement, considering how bad they've been at predicting completion of the major work.
 
Last edited:

LDECRexile

Established Member
Joined
30 Jan 2014
Messages
2,149
Location
Southport, UK
I've had three conversations with Orangepersons over the past few days, from which I've gleaned that:

1. Foundations on "our" line are indeed all done.
2. There will be a one week blockade late August (bank holiday weekend) to complete the wiring, there were over 80 wiring runs to go a day or two ago.
3. There will be six weekend blockades of the Blackpool North line in the Winter, after the Illuminations have ended, to implement a permanent solution to the drainage problem at Poulton, currently being handled by pumping.
4. All outstanding parts for the lifts at Kirkham and Wesham are on order from the manufacturers.
5. The number of people working on Salford-Euxton has recently increased, hence the big surge in action we've seen.

6. There are approximately 250 platforms needing lengthening in the north by May 2019, but this number may reduce.
7. It is likely that some blockading will be needed to implement the power feed east of Manchester Victoria.

8. The Transpennine enhancement team is being formed as we speak.
9. The Hope Valley enhancement team will be formed in the coming months

Some of this overlaps with what we've heard from other sources.
 

Norb

Member
Joined
26 May 2014
Messages
68
The Portal is North of the TTC that was installed previously
There still appears to my uneducated eye a gap between the mast south of the station and the TTC
There is a gravity base between the south of the Down/Northbound/Preston-bound platform and the public underpass for a TTC to fill that gap
 

LDECRexile

Established Member
Joined
30 Jan 2014
Messages
2,149
Location
Southport, UK
I had my first outing for weeks today. I travelled by train between Salford Central and Buckshaw Parkway in both directions, and the Wigan line.

Text and photographic coverage has been so good I didn't do my traditional minutiae spotting, but tried to look at the overall effect. I was disquieted by the lack of passengers, have people lost faith or don't they think trains are running or were they sweltering and sheltering? That apart, I was greatly encouraged, the whole look and feel is of a soon-to-be-electrified railway rather than a railway with lots of this and that going on here and there. I have no illusions about the scale of the hill still to climb or the challenges ahead, but ……

The masts yet to be erected are in several clumps, typically with bespoke bases. The clumps I noticed were: Wigan Line, country end; Yarrow Viaduct, east of Dean Clough, south of Squeeze Belly, several stations and just west of Newport St bridge. There were other individuals missing here and there. The amount of earth wire up was very heartening, with a continuous or near continuous run from the worksite south of Kearsley to just north of Clifton and lots of shorter stretches all over the place.

I took a few photos, the most striking not being railway pictures, but the continuing mushrooming building in Salford - if nothing else, lots of future customers.

I've added them to the Combined Volume here:

https://www.flickr.com/photos/127646831@N03/albums/72157661069863633

Heartening.
 

driver_m

Established Member
Joined
8 Nov 2011
Messages
2,248
There should be a monumental advertising push when it's all finally done on that stretch to get the passengers back. And some good incentives too to get people out of their cars.

Ps excellent work on collating this thread and to all the contributors of the info n pics. I love how everyone makes a positive contribution to this thread. Looking forward to the step change this line will provide when it's done and hopefully you'll be doing more of these threads on other lines.
 

driver_m

Established Member
Joined
8 Nov 2011
Messages
2,248
Here here and I am certain the sparks effect will be proven yet again

Oh definitely. But I think this line even more so than the ones already done, will make a huge difference. It has to make a number of other schemes more viable for wires. Dare I say Windermere again, etc etc. Anyway that's for another thread. Won't be long now before you're all out at stupid o'clock videoing one of our lot trying to blow the breakers testing it haha!
 

td97

Established Member
Joined
26 Jul 2017
Messages
1,556
There should be a monumental advertising push when it's all finally done on that stretch to get the passengers back. And some good incentives too to get people out of their cars.
DafT have already announced a marketing campaign to do exactly that

The package will see:
  • marketing campaigns for the tourist areas affected by the disruption, such as Blackpool and the Lake District, will be funded as part of the package
 

mikemcniven

Member
Joined
13 Aug 2016
Messages
381
Location
Manchester
Network Rail GNRP have said all foundations are now in on the Preston - Bolton - Manchester electrification route

https://twitter.com/TheGNRP/status/1015144680231665665

All 1,659 foundations have now been installed on the #Manchester-#Bolton-#Preston railway✅

Team Orange are working hard to install the remaining steelwork which will support the new overhead electric wires〰️|〰️|〰️

http://networkrail.co.uk/bolton
@northernassist #GNRP

DhaEsxgX4AAqGpE.jpg:large
 

LDECRexile

Established Member
Joined
30 Jan 2014
Messages
2,149
Location
Southport, UK
Wrinkley has kindly sent some shots showing progress at Lostock.

He added: "It’s feast and famine at Lostock , and now we are approaching famine.

The good news – the up line earth wire coming from the Wigan line, which stopped at the junction, has now been extended to half way between Beaumont Road and the Ladybridge.
The last mast to be erected, near Beaumont Road has now gained its tensioning reels.
Murphys are filling in the HV cable trench.


The bad news – the last portal near the station still has its crossbar lying on the floor, its been there at least ten days and one TTC still has its cantilever on the floor, its been there at least 13 days. There is a certain randomness about the way this project is being progressed.

A few more danglies to go up before wiring can start.

If you look at the before and after shots (A510t and r) you will see that the up line mast has been cut back, it had nine cross pieces before, now it has seven, don’t know why.

I will see what happens this weekend."

I've added the shots to his album here:

https://www.flickr.com/photos/127646831@N03/albums/72157654034635234

and to the Combined Volume here:

https://www.flickr.com/photos/127646831@N03/albums/72157661069863633

Thank you Wrinkley.
 

reg

Member
Joined
15 Mar 2015
Messages
70
Location
Bolton
Bolton-the first of two bespoke portals is now in place just north of Newport Street bridge.Will forward pic later.
 

chrissawer

Member
Joined
6 Nov 2013
Messages
107
Location
Yorkshire
An interesting reason for delays in Salford this morning:

An object is caught on the overhead electric wires between Salford Central and Salford Crescent. As a result, trains at Manchester Victoria will be delayed by up to 20 minutes, cancelled or revised. We anticipate disruption will continue until 08:30.

Anyone know what happened? I saw a group of orangemen about half way between Central and Crescent but they were stood back waiting for our train to pass. There is only an earth wire between the stations, off to the side of the track, so I'm surprised a problem with it has caused delays for diesel trains.
 

59CosG95

Established Member
Joined
18 Aug 2013
Messages
6,853
Location
Beeston (Notts)
Apologies for this week's update's tardiness, my graduation ceremony was yesterday and I've been working night shifts on top of that!


GSoP Post 12.0
Manchester Victoria - Preston; State of Play, week beginning 9th July 2018.

All bases in! 100 (at a guess/at most) masts still missing.
All mileages from Manchester Victoria. Bridge mileages are approximated where noted.

1. Man Vic Station (West End) - Man Vic West Jct - Deal Street Jct; 0m 0ch to 0m 32ch
Fully wired 2013-15.

2. Deal Street Jct - Salford Central (East End); 0m 32ch to 0m 59ch
Fully masted. Limit of electrification is currently at 0m 46ch; SPS is up along the unwired stretch.

3. Salford Central; 0m 59ch
Fully masted, most SPS (Small Part Steelwork e.g. dangly bits) up. No wires.

4. Salford Central (West End) - Windsor Bridge South Jct; 0m 59ch to 1m 46ch
All bases in place, mostly with masts, no catenary or earth wires. Two runs of Earth wire are up.

5. Windsor Bridge South Jct - Windsor Bridge North Jct (inc. Salford Crescent); 1m 46ch to 1m 70ch
No catenary/contact wires. The bespoke "right triangle" fixings on one of the footbridges have turned out to be fixings for dangly bits. Each side has two stovepipes; one for a registration arm, one for an earth wire.
All masts, almost all SPS and both Earth Wires now up through the station. Registration arm assemblies starting to appear too.
S Jct looks ready for wiring, but mast gaps still present at N Jct. Lots of SPS up immediately north of Salford Cres.

6. Windsor Bridge North Jct - Clifton (South End); 1m 70ch to 4m 57ch
Many bases in place, some with masts, no wires.
At Pendleton (the Old Station site), just north of Broughton Rd Bridge (2m 26ch), the Pendleton retaining wall has been cut back in several places to make room for bases (which are all now in).

Between Frederick Rd & Broughton Rd (2m 26ch) bridges, most masts are up, except on the "problem bases" around Broughton Rd. The 3 bases, between Broughton Rd Bridge & Cockrobin Bridge (approx. 2m 51ch) have now all gained masts.
The "problem base" north of Cockrobin Bridge has now finally gained a TTC (Twin Track Cantilever) on the northbound (see photo A384g); the gap is now closed.

Dangly bits up near Agecroft, and the missing bases in the walled stretch north of Agecroft Rd have now appeared & gained TTCs - woohoo! The problem was due to excessively sandy ground conditions in the area.
Steelwork either side of Park House Rd Bridge looks well advanced.
Lot of masts with SPS up on the southern approach to Clifton.

7. Clifton Station; 4m 57ch
2 boomed TTCs (with SPS), no wires. Drainage manhole modules awaiting installation; temporary covers are over their future homes.

8. Clifton (North End) - Kearsley (South End); 4m 57ch to 7m 57ch
Ready for wires throughout?
Brackets are fitted to the underside of the M60 overbridge. Bridge MVE1 27B (immediately NW of this) is fully erected, but unopened, and work the walkway is not yet finished.
The line through the former Dixon Fold station site (around the new footbridge, approx. 6m 00ch) looks ready for wires; the wire-readiness extends south to the M60 bridge.
Earth wires now up between Clifton & Kearsley; definitely through Clifton Country Park but the full extent is not confirmed.
Looking south from Kearsley, all masts that are up appear to be fully kitted out with SPS.

9. Kearsley Station; 7m 57ch
All bases in place, no masts, no wires.

10. Kearsley (North End) - Farnworth (South End); 7m 57ch to 8m 31ch
All masts (almost all with booms), no wires. Dangly bits starting to appear at the Kearsley end. Farnworth tunnel (8m 25ch) has all its registration arms in place. Earth wire might well have gone in through the tunnel too.

11. Farnworth Station; 8m 31ch
All bases in place, 1 or 2 masts, no wires. Looks pretty much ready for wiring south of the Farnworth Station Footbridge.

12. Farnworth (North End) - Moses Gate (South End); 8m 31ch to 9m 06ch
A pair of bases & squat masts are up between Farnworth Station footbridge and Rawson St Bridge (approx. 8m 44ch). Two bases have now gone in in the southbound cess, awaiting masts; one each side of the "squat portal" uprights.
Fully boomed and fully bedanglied TTCs up between Rawson St & the Balustraded Bridge (approx. 8m 56ch); this stretch now looks wire-ready.
The Gravity "Base of the century" just south of the Squeeze Belly Entry footbridge (approx. 8m 67ch) is now curing away nicely, with shuttering removed.

13. Moses Gate Station; 9m 06ch
Fully masted, no wires.

14. Moses Gate (North End) - Bolton (South End); 9m 06ch to 10m 50ch
Weston St to Moses Gate looks almost ready for wiring.
Many bases, many masts, no wires. SPS and Tensorex drums appearing on some masts/cantilevers around Burnden Jct (10m 09ch).
All uprights appear to be up on both sides of Lever St footbridge; a multi-track portal is up immediately to the south of the bridge. To the north (on the east side), a TTC with reduced-height registration arms is up.
Stretching south from Bolton, long stretches of earth wire are now up. Another portal has been erected in 2 replacement bases.
Orlando St Bridge appears to be fully "stovepiped".

15. Bolton Station; 10m 50ch
Through the station, all lines are fully masted with the exception of P1 and P3 (1 mast missing between Weston St & Newport St bridges, on each line), according to the observations of Reg.
The 1st TTC up over P1/2 has now been bedanglied; in total, P1/2 is covered by 4 TTCs and 3 STCs. P2 still requires its "termination mast".

Platforms 98% open to public; the 2% not open is a fenced-off section of canopy support to the right of signal "MP9239". P2 buffers look finished. Canopies look complete.

Earth wires now going in; the first one runs parallel to P3, from the southern end almost up to the road bridge at the northern end. A second one (parallel to P5) is up, and it extends south through Burnden as far as the eye can see.
Two sets of chalked "hieroglyphs" are etched into the bridge deck of Trinity St over P3/4; possible locations for stovepipes? Additionally, bolts & brackets are now drilled into the glazed brick retaining wall opposite P1.

16. Bolton (North End) - Lostock (South End); 10m 50ch to 13m 52ch
Newport St bridge has now had studs/brackets of some kind drilled in. The run of masts between Newport St & the NW end of P5 now have their earth wire affixed. Just east of Newport St Bridge, a TTC (unbedanglied) has now gone up on the southbound side.
A pair of wall brackets have been drilled into the retaining wall on the Down side at Bolton West Jct with corresponding brackets on the Up side. The westernmost pair of these have now gained a portal boom and uprights.

Between Newport Street Bridge & Moor Lane (the Bullfield Tunnels area), the tunnels are bedanglied throughout, with Aerial Earth Wire (AEW) brackets up over both tracks' respective tunnels/bridges.
Immediately NW of Newport St, one of the concrete bases that was poured over the weekend of May 5th has now had a mast affixed; the other mast for the other base is now similarly masted.

Gt. Moor St. bridge now has a stovepipe in on the Down side. The most recently cured base, fresh from unwrapping, has now had a mast & two dangly assemblies put up (see pic. A300k; between Great Moor St. & Dawes St. bridges). Of the "3 amigos" (the three closest masts to Great Moor St. Bridge), 2 now have Tensorex Drums fitted and the other has its dangly bits cabled-tied down(see pic. A320k).
Cable ducting troughs laid between Black Horse St & New St on the Down side, in the cess; all 6 masts are now up in this gap.
The overrun along the line to Blackburn (as far as Bradshawgate Tunnel) looks nearly ready for SPS & wires.

All masts are now up between Moor Lane & Mayor Street bridges, with the addition of a portal just NW of Moor Ln.

East of Dean Clough Bridge (12m 26ch), 2 "failed" driven pile bases on the southbound side now have formwork for concrete gravity pad replacements in position, awaiting the concrete pour.
Between Dean Clough Bridge and 'the' Ladybridge (next one further west), all masts appear to be up, with cantilever assembles affixed (and folded out of place).
Thence, between 'the' Ladybridge and Beaumont Rd, all masts of all varieties are now up. Earth wires are already being strung.
All bases and masts are in place between Beaumont Rd & Lostock station.

Masts have started to appear immediately south of Lostock; at the extreme southern end of the station, a twin track portal with SPS has been erected, with the 4-track portal over Lostock Jct (13m 39ch) immediately south of that now being boomed too. 3 "failed" protruding, uncapped pile bases are on the Wigan Line; one assumes that gravity pad replacements will eventually be in the offing.
More masts around the switchgear box are sprouting dangly bits, switchgear kit etc.
A UTX has been installed in the "vee" in Lostock Jct, for buried service access.
Work currently going on with stacks of cable ducting on the Wigan Line - possibly from the substation?
Another TTC (with boom) has gone up on the Wigan Line.
East of Lostock, a possession was taken over the weekend of 23rd/24th of June - registration arms/dangly bits appeared to be on a road-railer trailer, so perhaps some masts gained their dangly bits. One of the booms was affixed for one of the portals over the junction.

17. Lostock Station; 13m 52ch
Switchgear box delivered 6th April '18.
All TTCs now in behind the Down platform; one of them is not like the others (additional bracing member).

18. Lostock (North End) - Horwich Pkwy (South End); 13m 52ch to 15m 50ch
Two more UTXs have been installed in the "vee" between the two lines, to the north of the station.
Immediately north of the station, the closest TTCs to the platforms have now sprouted part of their switchgear kit.
For a mile between the stations, all wires up from the "Golf Course" Footbridge (approx. 14m 04ch) to half a mile south of Horwich Pkwy (approx. 15m 10ch). Earth wires have gone up on the Down side immediately north of the station; these presumably extend to the existing wired section.
All masts appear to be in place with SPS for the remaining sections between the two, including the A6027/De Havilland Way overbridge, which now has dangly bits mounted on the walls.

19. Horwich Parkway Station; 15m 50ch
Two new TTCs up on the south end of the platforms; one portal and one TTC to go up. Bedanglied TTCs now up through the station, with more to erect.

20. Horwich Pkwy (North End) - Blackrod (South End); 15m 50ch to 17m 14ch
All masts appear to be up NW of Horwich Pkwy to the M61 bridge. Earth/AT wires linking 9 masts together between the 2 stations, heading north (on the Up side) from immediately north of the M61 bridge (approx. 16m 29ch).

More Earth/AT wires are now up immediately NW of the footbridge at the NW end of Horwich Parkway Car Park, on the Down side (N'bound); the footbridge in question has also been sandwiched by some very complex-looking steelwork (presumably for the reduced clearances).
SPS appearing on portals near Blackrod, and SPS assemblies have been folded out of the way on the station's southern approach.
Work has concluded on the footbridge that will replace Red Moss foot crossing; complex portal/masts are up there too.

21. Blackrod Station; 17m 14ch
No wires. Empty mast base at the southern end. Bonding complete on P1. A second TTC has now been erected, and the extant one has now been boomed. Both have almost all SPS bits affixed (registration arms, and autotransformer growths; see photo A520m). Masts look complete to Lostock. P2 re-tarmacing ongoing.

22. Blackrod (North End) - Adlington (South End); 17m 14ch to 19m 15ch
Lots of masts up just north of Blackrod, with SPS all fitted. Some base replacement work occurred over 17th/18th Feb to replace failed bases. Successful bases have masts up with SPS on.

23. Adlington Station; 19m 15ch
2 single masts up (one on each side) and 2 TTCs (on one of the sides); all are bedanglied and earth bonded. The road bridge at the southern end has also been stalactited. No wires.

24. Adlington (North End) - Chorley (South End); 19m 15ch to 22m 20ch
2 short stretches of wire on the s'bound track.

All bespoke mast fixings are now up on Yarrow Viaduct (21m 26ch at the southern end); work had stopped after the alleged discovery of a large void within the structure, but this appears to be resolved. All evidence of a worksite has now gone, which suggests a portal (south end) and a TTC (north end) are next!

25. Chorley Station; 22m 20ch
No wires. First mast now up over the Down/Northbound/Preston-bound platform; this is at the northern end of the station, and features dangly bits.A portal has now gone in, north of the previously installed TTC; a gap may still be extant between the station and said TTC.

26. Chorley (North End) - Buckshaw Pkwy (South End); 22m 20ch to 24m 39ch
Many bases, some masts, 1 or 2 wires. Roof brackets affixed in Chorley Tunnel (23m 20ch to 23m 25ch), and at least 6 dangly bits/SPS are up in the Flying Arches cutting. All bases on top of the retaining wall at the northern end now have portal booms affixed.

27. Buckshaw Parkway Station; 24m 39ch
Some bases in place, 2 TTCs up on the Down side, 1 TTC up on the Up side. The footbridge has now sprouted stovepipes. No wires.

28. Buckshaw Pkwy (North End) - Euxton Jct; 24m 39ch to 25m 31ch
Almost fully masted; about half the wires up until halfway to Euxton, then fully wired the rest of the way.

Do let me know if I've missed anything!
 

deltic08

On Moderation
Joined
26 Aug 2013
Messages
2,901
Location
North
Apologies for this week's update's tardiness, my graduation ceremony was yesterday and I've been working night shifts on top of that!


GSoP Post 12.0
Manchester Victoria - Preston; State of Play, week beginning 9th July 2018.

All bases in! 100 (at a guess/at most) masts still missing.
All mileages from Manchester Victoria. Bridge mileages are approximated where noted.

1. Man Vic Station (West End) - Man Vic West Jct - Deal Street Jct; 0m 0ch to 0m 32ch
Fully wired 2013-15.

2. Deal Street Jct - Salford Central (East End); 0m 32ch to 0m 59ch
Fully masted. Limit of electrification is currently at 0m 46ch; SPS is up along the unwired stretch.

3. Salford Central; 0m 59ch
Fully masted, most SPS (Small Part Steelwork e.g. dangly bits) up. No wires.

4. Salford Central (West End) - Windsor Bridge South Jct; 0m 59ch to 1m 46ch
All bases in place, mostly with masts, no catenary or earth wires. Two runs of Earth wire are up.

5. Windsor Bridge South Jct - Windsor Bridge North Jct (inc. Salford Crescent); 1m 46ch to 1m 70ch
No catenary/contact wires. The bespoke "right triangle" fixings on one of the footbridges have turned out to be fixings for dangly bits. Each side has two stovepipes; one for a registration arm, one for an earth wire.
All masts, almost all SPS and both Earth Wires now up through the station. Registration arm assemblies starting to appear too.
S Jct looks ready for wiring, but mast gaps still present at N Jct. Lots of SPS up immediately north of Salford Cres.

6. Windsor Bridge North Jct - Clifton (South End); 1m 70ch to 4m 57ch
Many bases in place, some with masts, no wires.
At Pendleton (the Old Station site), just north of Broughton Rd Bridge (2m 26ch), the Pendleton retaining wall has been cut back in several places to make room for bases (which are all now in).

Between Frederick Rd & Broughton Rd (2m 26ch) bridges, most masts are up, except on the "problem bases" around Broughton Rd. The 3 bases, between Broughton Rd Bridge & Cockrobin Bridge (approx. 2m 51ch) have now all gained masts.
The "problem base" north of Cockrobin Bridge has now finally gained a TTC (Twin Track Cantilever) on the northbound (see photo A384g); the gap is now closed.

Dangly bits up near Agecroft, and the missing bases in the walled stretch north of Agecroft Rd have now appeared & gained TTCs - woohoo! The problem was due to excessively sandy ground conditions in the area.
Steelwork either side of Park House Rd Bridge looks well advanced.
Lot of masts with SPS up on the southern approach to Clifton.

7. Clifton Station; 4m 57ch
2 boomed TTCs (with SPS), no wires. Drainage manhole modules awaiting installation; temporary covers are over their future homes.

8. Clifton (North End) - Kearsley (South End); 4m 57ch to 7m 57ch
Ready for wires throughout?
Brackets are fitted to the underside of the M60 overbridge. Bridge MVE1 27B (immediately NW of this) is fully erected, but unopened, and work the walkway is not yet finished.
The line through the former Dixon Fold station site (around the new footbridge, approx. 6m 00ch) looks ready for wires; the wire-readiness extends south to the M60 bridge.
Earth wires now up between Clifton & Kearsley; definitely through Clifton Country Park but the full extent is not confirmed.
Looking south from Kearsley, all masts that are up appear to be fully kitted out with SPS.

9. Kearsley Station; 7m 57ch
All bases in place, no masts, no wires.

10. Kearsley (North End) - Farnworth (South End); 7m 57ch to 8m 31ch
All masts (almost all with booms), no wires. Dangly bits starting to appear at the Kearsley end. Farnworth tunnel (8m 25ch) has all its registration arms in place. Earth wire might well have gone in through the tunnel too.

11. Farnworth Station; 8m 31ch
All bases in place, 1 or 2 masts, no wires. Looks pretty much ready for wiring south of the Farnworth Station Footbridge.

12. Farnworth (North End) - Moses Gate (South End); 8m 31ch to 9m 06ch
A pair of bases & squat masts are up between Farnworth Station footbridge and Rawson St Bridge (approx. 8m 44ch). Two bases have now gone in in the southbound cess, awaiting masts; one each side of the "squat portal" uprights.
Fully boomed and fully bedanglied TTCs up between Rawson St & the Balustraded Bridge (approx. 8m 56ch); this stretch now looks wire-ready.
The Gravity "Base of the century" just south of the Squeeze Belly Entry footbridge (approx. 8m 67ch) is now curing away nicely, with shuttering removed.

13. Moses Gate Station; 9m 06ch
Fully masted, no wires.

14. Moses Gate (North End) - Bolton (South End); 9m 06ch to 10m 50ch
Weston St to Moses Gate looks almost ready for wiring.
Many bases, many masts, no wires. SPS and Tensorex drums appearing on some masts/cantilevers around Burnden Jct (10m 09ch).
All uprights appear to be up on both sides of Lever St footbridge; a multi-track portal is up immediately to the south of the bridge. To the north (on the east side), a TTC with reduced-height registration arms is up.
Stretching south from Bolton, long stretches of earth wire are now up. Another portal has been erected in 2 replacement bases.
Orlando St Bridge appears to be fully "stovepiped".

15. Bolton Station; 10m 50ch
Through the station, all lines are fully masted with the exception of P1 and P3 (1 mast missing between Weston St & Newport St bridges, on each line), according to the observations of Reg.
The 1st TTC up over P1/2 has now been bedanglied; in total, P1/2 is covered by 4 TTCs and 3 STCs. P2 still requires its "termination mast".

Platforms 98% open to public; the 2% not open is a fenced-off section of canopy support to the right of signal "MP9239". P2 buffers look finished. Canopies look complete.

Earth wires now going in; the first one runs parallel to P3, from the southern end almost up to the road bridge at the northern end. A second one (parallel to P5) is up, and it extends south through Burnden as far as the eye can see.
Two sets of chalked "hieroglyphs" are etched into the bridge deck of Trinity St over P3/4; possible locations for stovepipes? Additionally, bolts & brackets are now drilled into the glazed brick retaining wall opposite P1.

16. Bolton (North End) - Lostock (South End); 10m 50ch to 13m 52ch
Newport St bridge has now had studs/brackets of some kind drilled in. The run of masts between Newport St & the NW end of P5 now have their earth wire affixed. Just east of Newport St Bridge, a TTC (unbedanglied) has now gone up on the southbound side.
A pair of wall brackets have been drilled into the retaining wall on the Down side at Bolton West Jct with corresponding brackets on the Up side. The westernmost pair of these have now gained a portal boom and uprights.

Between Newport Street Bridge & Moor Lane (the Bullfield Tunnels area), the tunnels are bedanglied throughout, with Aerial Earth Wire (AEW) brackets up over both tracks' respective tunnels/bridges.
Immediately NW of Newport St, one of the concrete bases that was poured over the weekend of May 5th has now had a mast affixed; the other mast for the other base is now similarly masted.

Gt. Moor St. bridge now has a stovepipe in on the Down side. The most recently cured base, fresh from unwrapping, has now had a mast & two dangly assemblies put up (see pic. A300k; between Great Moor St. & Dawes St. bridges). Of the "3 amigos" (the three closest masts to Great Moor St. Bridge), 2 now have Tensorex Drums fitted and the other has its dangly bits cabled-tied down(see pic. A320k).
Cable ducting troughs laid between Black Horse St & New St on the Down side, in the cess; all 6 masts are now up in this gap.
The overrun along the line to Blackburn (as far as Bradshawgate Tunnel) looks nearly ready for SPS & wires.

All masts are now up between Moor Lane & Mayor Street bridges, with the addition of a portal just NW of Moor Ln.

East of Dean Clough Bridge (12m 26ch), 2 "failed" driven pile bases on the southbound side now have formwork for concrete gravity pad replacements in position, awaiting the concrete pour.
Between Dean Clough Bridge and 'the' Ladybridge (next one further west), all masts appear to be up, with cantilever assembles affixed (and folded out of place).
Thence, between 'the' Ladybridge and Beaumont Rd, all masts of all varieties are now up. Earth wires are already being strung.
All bases and masts are in place between Beaumont Rd & Lostock station.

Masts have started to appear immediately south of Lostock; at the extreme southern end of the station, a twin track portal with SPS has been erected, with the 4-track portal over Lostock Jct (13m 39ch) immediately south of that now being boomed too. 3 "failed" protruding, uncapped pile bases are on the Wigan Line; one assumes that gravity pad replacements will eventually be in the offing.
More masts around the switchgear box are sprouting dangly bits, switchgear kit etc.
A UTX has been installed in the "vee" in Lostock Jct, for buried service access.
Work currently going on with stacks of cable ducting on the Wigan Line - possibly from the substation?
Another TTC (with boom) has gone up on the Wigan Line.
East of Lostock, a possession was taken over the weekend of 23rd/24th of June - registration arms/dangly bits appeared to be on a road-railer trailer, so perhaps some masts gained their dangly bits. One of the booms was affixed for one of the portals over the junction.

17. Lostock Station; 13m 52ch
Switchgear box delivered 6th April '18.
All TTCs now in behind the Down platform; one of them is not like the others (additional bracing member).

18. Lostock (North End) - Horwich Pkwy (South End); 13m 52ch to 15m 50ch
Two more UTXs have been installed in the "vee" between the two lines, to the north of the station.
Immediately north of the station, the closest TTCs to the platforms have now sprouted part of their switchgear kit.
For a mile between the stations, all wires up from the "Golf Course" Footbridge (approx. 14m 04ch) to half a mile south of Horwich Pkwy (approx. 15m 10ch). Earth wires have gone up on the Down side immediately north of the station; these presumably extend to the existing wired section.
All masts appear to be in place with SPS for the remaining sections between the two, including the A6027/De Havilland Way overbridge, which now has dangly bits mounted on the walls.

19. Horwich Parkway Station; 15m 50ch
Two new TTCs up on the south end of the platforms; one portal and one TTC to go up. Bedanglied TTCs now up through the station, with more to erect.

20. Horwich Pkwy (North End) - Blackrod (South End); 15m 50ch to 17m 14ch
All masts appear to be up NW of Horwich Pkwy to the M61 bridge. Earth/AT wires linking 9 masts together between the 2 stations, heading north (on the Up side) from immediately north of the M61 bridge (approx. 16m 29ch).

More Earth/AT wires are now up immediately NW of the footbridge at the NW end of Horwich Parkway Car Park, on the Down side (N'bound); the footbridge in question has also been sandwiched by some very complex-looking steelwork (presumably for the reduced clearances).
SPS appearing on portals near Blackrod, and SPS assemblies have been folded out of the way on the station's southern approach.
Work has concluded on the footbridge that will replace Red Moss foot crossing; complex portal/masts are up there too.

21. Blackrod Station; 17m 14ch
No wires. Empty mast base at the southern end. Bonding complete on P1. A second TTC has now been erected, and the extant one has now been boomed. Both have almost all SPS bits affixed (registration arms, and autotransformer growths; see photo A520m). Masts look complete to Lostock. P2 re-tarmacing ongoing.

22. Blackrod (North End) - Adlington (South End); 17m 14ch to 19m 15ch
Lots of masts up just north of Blackrod, with SPS all fitted. Some base replacement work occurred over 17th/18th Feb to replace failed bases. Successful bases have masts up with SPS on.

23. Adlington Station; 19m 15ch
2 single masts up (one on each side) and 2 TTCs (on one of the sides); all are bedanglied and earth bonded. The road bridge at the southern end has also been stalactited. No wires.

24. Adlington (North End) - Chorley (South End); 19m 15ch to 22m 20ch
2 short stretches of wire on the s'bound track.

All bespoke mast fixings are now up on Yarrow Viaduct (21m 26ch at the southern end); work had stopped after the alleged discovery of a large void within the structure, but this appears to be resolved. All evidence of a worksite has now gone, which suggests a portal (south end) and a TTC (north end) are next!

25. Chorley Station; 22m 20ch
No wires. First mast now up over the Down/Northbound/Preston-bound platform; this is at the northern end of the station, and features dangly bits.A portal has now gone in, north of the previously installed TTC; a gap may still be extant between the station and said TTC.

26. Chorley (North End) - Buckshaw Pkwy (South End); 22m 20ch to 24m 39ch
Many bases, some masts, 1 or 2 wires. Roof brackets affixed in Chorley Tunnel (23m 20ch to 23m 25ch), and at least 6 dangly bits/SPS are up in the Flying Arches cutting. All bases on top of the retaining wall at the northern end now have portal booms affixed.

27. Buckshaw Parkway Station; 24m 39ch
Some bases in place, 2 TTCs up on the Down side, 1 TTC up on the Up side. The footbridge has now sprouted stovepipes. No wires.

28. Buckshaw Pkwy (North End) - Euxton Jct; 24m 39ch to 25m 31ch
Almost fully masted; about half the wires up until halfway to Euxton, then fully wired the rest of the way.

Do let me know if I've missed anything!
What is a UTX at Lostock please?
 

LDECRexile

Established Member
Joined
30 Jan 2014
Messages
2,149
Location
Southport, UK
Good News

I did a car and shanks tour from Squeeze Belly to Broughton Road today, lots of the line has one and in some cases two earth wires up. Will do a train tour tomorrow or Thursday to confirm the detail.

Photos later or tomorrow.
 