Paul and I travelled from Bolton to Preston and back today. Our prime task was mast and base logging.
The Progressometer shows no change in the number of masts (none was expected) and a small rise in the number of bases in the Buckshaw Parkway area.
This fails to show "green shoots", ie:
1. BB bases now tagged with their number (MG/nn/nn). Lots have these. Joseph Locke remarked on them a while back but I missed their significance - each one says "Yep, we're happy with this."
2. Pegs (lengths of 1" square rough cut wood, typically dipped in yellow or orange paint with mast number-to-be pinned on, see recent images from Buckshaw) have been driven into both new and old "scrapes" (alias "preliminary earthworks".) Once again, the new contractors are visibly taking ownership.
3. New bases in cardboard formers have appeared since last week. Evidence of action on the ground.
Other things:
a. Still can't see the contractor's workbase.
b. Hard to tell what progress is being made on the drainage job between Lostock Junction and Ladybridge, there's a lot of materials and kit around.
c. Appears to be signal troughing progress between Bolton and Dean Clough bridge
d. Lostock and Horwich Parkway car parks full
e. Four coach Arriva trains well but not fully loaded in both directions mid afternoon.
f. Tickets checked and good announcements throughout.
g. Regret that the buffet on Bolton Station has closed.
The Progressometer shows no change in the number of masts (none was expected) and a small rise in the number of bases in the Buckshaw Parkway area.
This fails to show "green shoots", ie:
1. BB bases now tagged with their number (MG/nn/nn). Lots have these. Joseph Locke remarked on them a while back but I missed their significance - each one says "Yep, we're happy with this."
2. Pegs (lengths of 1" square rough cut wood, typically dipped in yellow or orange paint with mast number-to-be pinned on, see recent images from Buckshaw) have been driven into both new and old "scrapes" (alias "preliminary earthworks".) Once again, the new contractors are visibly taking ownership.
3. New bases in cardboard formers have appeared since last week. Evidence of action on the ground.
Other things:
a. Still can't see the contractor's workbase.
b. Hard to tell what progress is being made on the drainage job between Lostock Junction and Ladybridge, there's a lot of materials and kit around.
c. Appears to be signal troughing progress between Bolton and Dean Clough bridge
d. Lostock and Horwich Parkway car parks full
e. Four coach Arriva trains well but not fully loaded in both directions mid afternoon.
f. Tickets checked and good announcements throughout.
g. Regret that the buffet on Bolton Station has closed.