• Our new ticketing site is now live! Using either this or the original site (both powered by TrainSplit) helps support the running of the forum with every ticket purchase! Find out more and ask any questions/give us feedback in this thread!

Blackpool - Manchester Electrification

Status
Not open for further replies.
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

CAF397

Member
Joined
15 Sep 2010
Messages
1,095
Location
Lancashire
Trains running through the new tunnel by the end of November then?
Fits in nicely with the 13 December timetable change.
NR and the contractors deserve considerable praise for overcoming the problems and limiting the delay in completion.

Just to stick a spanner in the works, to reconnect the tracks either end of the tunnel, and restore the signalling would take another full blockade of 4-5 days.

Thing is, if the tunnel is ready by the end of November, Network Rail and the TOCs maybe reluctant to do it in the run up to christmas, when weekends are almost as busy as weekdays.

Probably a lot of contractors earning money during the Christmas shutdown, and between Christmas and new year!
 

furnessvale

Established Member
Joined
14 Jul 2015
Messages
4,899
Just to stick a spanner in the works, to reconnect the tracks either end of the tunnel, and restore the signalling would take another full blockade of 4-5 days.

Thing is, if the tunnel is ready by the end of November, Network Rail and the TOCs maybe reluctant to do it in the run up to christmas, when weekends are almost as busy as weekdays.

Probably a lot of contractors earning money during the Christmas shutdown, and between Christmas and new year!

Maybe they will do things in two stages, ie reconnect the up line through the new tunnel and in a separate possession, transfer the down?
 

snowball

Established Member
Joined
4 Mar 2013
Messages
8,144
Location
Leeds
As luck would have it I'm watching a programme on BBC4 about battlefield tunnelling in WWI.

--- old post above --- --- new post below ---

Just to stick a spanner in the works, to reconnect the tracks either end of the tunnel, and restore the signalling would take another full blockade of 4-5 days.

Maybe they will do things in two stages, ie reconnect the up line through the new tunnel and in a separate possession, transfer the down?

They could surely tie in the up line during night-time possessions with minimum interference to operations. Then, if it wasn't for signalling issues, they could clip and scotch the temporary crossovers out of use and run up trains through the enlarged bore and down ones through the mousehole until the turn of the year.

Except that I think Joseph has said that recongfiguring the signalling is the main issue
 
Last edited:

Joseph_Locke

Established Member
Joined
14 Apr 2012
Messages
1,878
Location
Within earshot of trains passing the one and half
They could surely tie in the up line during night-time possessions with minimum interference to operations. Then, if it wasn't for signalling issues, they could clip and scotch the temporary crossovers out of use and run up trains through the enlarged bore and down ones through the mousehole until the turn of the year.

Except that I think Joseph has said that recongfiguring the signalling is the main issue

I believe the current plan is to revert to two-track operation through the new tunnel first (soon) and then recover the S&C later. This two-step plan is presumably being driven by resources such as trains and cranes.
 

swt_passenger

Veteran Member
Joined
7 Apr 2010
Messages
34,243
Will be, isn't this tunnel wider than Crossrail the previous widest tunnel?

I think Network Rail's PR was simply saying it was the largest tunnelling machine (shield) currently in use in UK.

As it is a double track tunnel it's sort of obvious that it will be bigger than the Crossrail TBMs used for a single track tunnel, I don't see any point in them making comparisons with Crossrail, the latter is a completely different sort of project.
 

Howardh

Established Member
Joined
17 May 2011
Messages
9,770
When Preston/Chorley/Bolton/Manchester ends up with fast electric spanking brand new refurbished second-hand stock; what will happen to the Bolton/Blackburn and Wigan lines?

Clearly they won't be electrified - but are there any plans to redouble the former line and run newer diesel stock on both?

Considering three lines run through Bolton and if those other two continue to run the oldest stock NR can find, then the odds are if you turn up at Trinity Street the next train will be as dirty and grimy diesels as they are now :( I suppose in a couple of years they won't be the nodding-donkeys so that's something.

Not much benefit there unless pax are prepared to wait in our luxury executive class waiting room on 1/2/3 for an electric to glide in!
 

thealexweb

Member
Joined
5 Jan 2014
Messages
1,106
When Preston/Chorley/Bolton/Manchester ends up with fast electric spanking brand new refurbished second-hand stock; what will happen to the Bolton/Blackburn and Wigan lines?

Clearly they won't be electrified - but are there any plans to redouble the former line and run newer diesel stock on both?

Considering three lines run through Bolton and if those other two continue to run the oldest stock NR can find, then the odds are if you turn up at Trinity Street the next train will be as dirty and grimy diesels as they are now :( I suppose in a couple of years they won't be the nodding-donkeys so that's something.

Not much benefit there unless pax are prepared to wait in our luxury executive class waiting room on 1/2/3 for an electric to glide in!

Lostock Junction to Wigan North Western electrification should still be happening. It was previously announced and approved. But you are correct, Phase 4 alone will not allow the introduction of a single extra Northern Rail EMU. The only route that was a possibility was Hazel Grove to Preston but for now at least that continues to Blackpool North.
 

AM9

Veteran Member
Joined
13 May 2014
Messages
16,021
Location
St Albans
When Preston/Chorley/Bolton/Manchester ends up with fast electric spanking brand new refurbished second-hand stock; what will happen to the Bolton/Blackburn and Wigan lines?

The 319s haven't changed hands since 1994 so they are no more second-hand than they were for over 80% of Thameslink's time with them.

Clearly they won't be electrified - but are there any plans to redouble the former line and run newer diesel stock on both?

Considering three lines run through Bolton and if those other two continue to run the oldest stock NR can find, then the odds are if you turn up at Trinity Street the next train will be as dirty and grimy diesels as they are now :( I suppose in a couple of years they won't be the nodding-donkeys so that's something. ...

Lines that are still unelectrified, (probably because of a low BCR) will have to use whatever is available from the RoSCos which is likely to include 142s until at least 2020. With the 319s releasing a significant number of existing DMUs, Northern Rail (or their successor) has a greater range and number of units from which to choose, which initially may include 142s & 150s. At least there will be less of an excuse for short forming.
 

snowball

Established Member
Joined
4 Mar 2013
Messages
8,144
Location
Leeds
are there any plans to redouble the former [Blackburn] line and run newer diesel stock on both?
Work was completed only a month or two ago to extend at both ends the stretch of double track through Darwen. It included rebuilding some bridges. I haven't heard of any further plans for redoubling on that route.

--- old post above --- --- new post below ---

Incredibly there's nothing about the breakthrough on the Northern Programme Twitter feed despite the fact that there are new posts this morning.

Also nothing on the LNW press releases page.
 
Last edited:

Howardh

Established Member
Joined
17 May 2011
Messages
9,770
Thanks for the info - can you confirm that Bolton/Wigan will be electrified as alluded to above? Didn't think that was the case, so my mistake. If so then I would suggest it's another good reason to rebuild/relocate Lostock station so the Wigan line is serviced.
 

snowball

Established Member
Joined
4 Mar 2013
Messages
8,144
Location
Leeds
can you confirm that Bolton/Wigan will be electrified as alluded to above?

It was first announced in Dec 2013 but subject to qualifications. I seem to remember that full authorisation happened earlier this year. On that basis I suppose it could yet be axed in the Hendy review - except that it's shown as going ahead in this map which came with the "un-pausing" announcement on 30 Sep:

https://www.gov.uk/government/news/transpennine-and-midland-mainline-electrification-works-to-resume
 

PDG1949

Member
Joined
21 May 2014
Messages
323
Location
St. Helens, Merseyside
Slightly off thread, but whilst doing some research on disused stations/lines, Dave/LDECRexile and myself found out that the Northern Office and Yard of Murphy's Civil Engineering Contractors occupies the space once taken by the old GCR Golborne North station and sidings
 

Attachments

  • Golborne North GCR aka J Murphy's Northern Office.jpg
    Golborne North GCR aka J Murphy's Northern Office.jpg
    339 KB · Views: 49

CAF397

Member
Joined
15 Sep 2010
Messages
1,095
Location
Lancashire
It's possible that when Lostock Jn - Wigan gets wired, that Wigan Wallgate terminators will transfer to Wogan NW, to allow EMU operation from Wigan to Victoria & Stalybridge. That'll free up DMUs too. Preston-Hazel Grove will possibly go EMU when Chorley is finished, and maybe just leave Blackpool-Preston as a DMU shuttle pending wiring.
 

GRALISTAIR

Established Member
Joined
11 Apr 2012
Messages
10,480
Location
Preston Lancs
It's possible that when Lostock Jn - Wigan gets wired, that Wigan Wallgate terminators will transfer to Wogan NW, to allow EMU operation from Wigan to Victoria & Stalybridge. That'll free up DMUs too. Preston-Hazel Grove will possibly go EMU when Chorley is finished, and maybe just leave Blackpool-Preston as a DMU shuttle pending wiring.

I know things were disrupted with Balfour-Beatty etc, but Preston - Blackpool is only supposed to be about 3 months behind Preston -Manchester anyway, so IMHO the above point is somewhat moot.
 

CAF397

Member
Joined
15 Sep 2010
Messages
1,095
Location
Lancashire
I know things were disrupted with Balfour-Beatty etc, but Preston - Blackpool is only supposed to be about 3 months behind Preston -Manchester anyway, so IMHO the above point is somewhat moot.

There's major work remodelling Blackpool North and Kirkham that needs to be undertaken, various rumours state a 3-month blockade to perform. Apart from the bridge reconstructions done in 2012/2013 there has been no other work done as of yet between Blackpool and Preston.

As far as I know the blockade hasn't even been agreed, I think they wanted the period between the illuminations and the start of the Spring, but the council has objected because that would hit their Christmas period.
 

snowball

Established Member
Joined
4 Mar 2013
Messages
8,144
Location
Leeds
I thought that it was agreed that the blockade would start in Jan or Feb?
Jan 2017, I thought.


Brilliant videos and stills. Many thanks to those involved.

I wonder how Fillie's final position compared with the circular hole in the concrete portal? Some of the pictures make it seem as if she was a few inches to the right.

The views along Cemetery Road bridge suggest that much the same is happening to the parapets there as at Skew Bridge.
 
Last edited:

LDECRexile

Established Member
Joined
30 Jan 2014
Messages
2,149
Location
Southport, UK
Thank you to snowball and ironstone for your kind remarks and encouragement.

I thought the same about Cemetery Road and Skew Bridge parapets.

Re her alignment, it may be that Fillie's nose is sticking out by now. I definitely can't get along today, but am hopeful that I can tomorrow.

Wrinkley has put together four brilliant compilations of films from Sunday. Inevitably there's overlap with material already published, as we were within feet of each other throughout, but hey, how often does Fillie break through?!

I've added them to Wrinkley's album here:

https://www.flickr.com/photos/127646831@N03/albums/72157654034635234

and to the Combined Volume here:

https://www.flickr.com/photos/127646831@N03/albums/72157648767927083

I've put them in their correct chronological sequence, so you may find it easier to find them by looking in Wrinkley's album, where they appear first.

Thank you Wrinkley
 

SodTheDrummer

Member
Joined
14 May 2015
Messages
201
Location
Bolton
Jan 2017, I thought.


Brilliant videos and stills. Many thanks to those involved.

I wonder how Fillie's final position compared with the circular hole in the concrete portal? Some of the pictures make it seem as if she was a few inches to the right.

The views along Cemetery Road bridge suggest that much the same is happening to the parapets there as at Skew Bridge.

Agreed! Superb pics and videos. Utter silence from NR on the Twitter feed still I see... I'm going to pop over on the way home tonight and have a look for myself.
 

Codville

Member
Joined
25 Jan 2013
Messages
60
Must be Jan 2017 then, I've not seen Blackpool Gazette moaning about the planned blockade lately.
 

snowball

Established Member
Joined
4 Mar 2013
Messages
8,144
Location
Leeds
Utter silence from NR on the Twitter feed still I see.

Now has pics of the Mayor of Bolton opening Ladybridge Lane bridge but still nothing about Fillie!

Despite being a regular reader of the Twitter feed I'm not a registered Twitterer. Is there someone here who is? Can you tweet them to complain?
 
Last edited:

Chrism20

Established Member
Joined
27 Feb 2013
Messages
1,398
Must be Jan 2017 then, I've not seen Blackpool Gazette moaning about the planned blockade lately.

Early 2017 was what I was told when I asked at BPN a few months ago about the work.

Does anyone know if there are going to be Sunday closures on the line again this winter like there were at the start of the year? I'll be going to see my folks after Christmas and the buses were awful this year.
 
Last edited:

snowball

Established Member
Joined
4 Mar 2013
Messages
8,144
Location
Leeds
I don't know but I imagine the weekend closures were mostly for the bridgeworks, now mostly done.
 

QueensCurve

Established Member
Joined
22 Dec 2014
Messages
2,196
It's possible that when Lostock Jn - Wigan gets wired, that Wigan Wallgate terminators will transfer to Wogan NW, to allow EMU operation from Wigan to Victoria & Stalybridge. That'll free up DMUs too. Preston-Hazel Grove will possibly go EMU when Chorley is finished, and maybe just leave Blackpool-Preston as a DMU shuttle pending wiring.

I can't help but think that an opportunity was lost to concentrate all services on one station by moving the Wallgate platforms to the other side of the road and havving a common station entrance in between the two lines as at Perth/Stone etc.
 
Status