I've found this 12-minute video of the works around Farnworth, taken from a series of passing trains between May and July this year.
https://www.youtube.com/watch?v=FDHksaikETQ
It ends just before Fillie started boring. A further video is promised later in the year.
I frequently do web searches for phrases like "Farnworth Tunnel" but it wasn't one of those that found it. I found it by accident as a side effect of searching for information on the balustraded bridge.
I now believe that the photo captions are wrong to identify the name Squeeze Belly Entry with the balustraded bridge.
In order along the line going towards Bolton we have
Farnworth tunnels
Cemetery Road bridge
Farnworth station
A footbridge from which many photos have been taken
The narrow road bridge connecting Rawson Street to Lower Rawson Street
The balustraded bridge
An extremely narrow humpback footbridge with solid stone parapets
Bolton Road bridge
Moses Gate station
The name Squeeze Belly Entry surely applies to the incredibly narrow footbridge. Here is a video of it:
https://www.youtube.com/watch?v=pqWZMikOTxA
And when I watched that video on YouTube, the next video that came up automatically afterwards was the one linked at the top of this post.
--- old post above --- --- new post below ---
They are the same fears expressed in #1455, #1461, #1465 and #1474, with the additional information of the picture taken on the 15th.
NR are reported to have said:
1. By the 11th (when the Minister visited) Fillie had made 10m progress.
2. She was then 1m ahead of schedule.
It's hard to believe statement 2.
Is this another example of NR's seeming habit of refusing to admit that a project is behind schedule until it's actually missed its previously announced completion date?
https://www.youtube.com/watch?v=FDHksaikETQ
It ends just before Fillie started boring. A further video is promised later in the year.
I frequently do web searches for phrases like "Farnworth Tunnel" but it wasn't one of those that found it. I found it by accident as a side effect of searching for information on the balustraded bridge.
I now believe that the photo captions are wrong to identify the name Squeeze Belly Entry with the balustraded bridge.
In order along the line going towards Bolton we have
Farnworth tunnels
Cemetery Road bridge
Farnworth station
A footbridge from which many photos have been taken
The narrow road bridge connecting Rawson Street to Lower Rawson Street
The balustraded bridge
An extremely narrow humpback footbridge with solid stone parapets
Bolton Road bridge
Moses Gate station
The name Squeeze Belly Entry surely applies to the incredibly narrow footbridge. Here is a video of it:
https://www.youtube.com/watch?v=pqWZMikOTxA
And when I watched that video on YouTube, the next video that came up automatically afterwards was the one linked at the top of this post.
--- old post above --- --- new post below ---
I've had correspondence with a proven wellwisher for the project expressing increasing concern that Fillie is way behind.
Please bear in mind that normal traffic is due to resume in early October, as shown on public posters and timetables.
The prime cause for his concern can be seen in the temporary mini-album here:
https://www.flickr.com/photos/127646831@N03/albums/72157657384006325
4730c - The Network Rail image - shows Fillie geared up but still on dry land, so to speak. Her extreme rear appears to be the conveyor belt above the road vehicle with a white metal framework above it.
4818p - taken on 6th Aug shows her in the earth, with a large grey framework visible ahead of the Orangemen who stand at her rear.
4866g - taken 15th Aug shows her rear end still visible, though the large grey framework has disappeared. The Orangemen stand in the same general rear area as in 4818p.
Network Rail sent a tweet to the correspondent on 31st July saying they expected to start boring that night.
The expected rate is 6 metres per day, which over 15 days would be 90 metres. This would make her invisible from the Kearsley footbridge.
The original published target start date for boring was 22nd July, published target end date 8th Sept.
Orangemen he's talked to give conflicting stories or know nowt.
Can anyone allay or confirm these fears?
They are the same fears expressed in #1455, #1461, #1465 and #1474, with the additional information of the picture taken on the 15th.
NR are reported to have said:
1. By the 11th (when the Minister visited) Fillie had made 10m progress.
2. She was then 1m ahead of schedule.
It's hard to believe statement 2.
Is this another example of NR's seeming habit of refusing to admit that a project is behind schedule until it's actually missed its previously announced completion date?
Last edited: