Base progress:
Just checking on progress on your patch today, mast bases have extended a mile or so westwards in the last week, and now end near MP (Mile Post!) 20, west of Adlington.
Preparations extend another mile west to about MP21 just before the L&L canal bridge.
The base totals are now about 108 on each side from MP14.5, 20 more than last week.
Progress is maybe best looked at for the Lostock-Euxton section as a whole (12 miles, 19km) which I would put at 38% at 15 structures per km.
At the Salford end, there are c15 bases on each side from the south end of Salford Crescent station towards Salford Central, plus one solitary base alongside Windsor Bridge North Jn.
I could be persuaded that exploratory work has taken place around Agecroft, but nothing definite.
A big work site is taking shape south of Kearsley, no doubt for the single line remodelling.