QueensCurve

Established Member
Joined
22 Dec 2014
Messages
2,195
One of the current oddities at Euxton is the way Up Slow trains on the WCML heading for Bolton find themselves on the Down Bolton for a spell before reaching the Up Bolton.
That can't do much for the capacity of the junction.

It is a hangover from when British Rail remodelled Euxton Junction as a single lead junction.:(

This was remodelled again to a double lead a few years ago.

The really odd thing is that the Bolton lines join the fast lines and not the slow. Capacity would perhaps be enhanced if the fast and slow lines were transposed, but this would then presumably require a flyover between Euxton and Preston.
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

LDECRexile

Established Member
Joined
30 Jan 2014
Messages
2,149
Location
Southport, UK

QueensCurve

Established Member
Joined
22 Dec 2014
Messages
2,195
between Preston and Blackpool North / Blackpool South on Sunday 21 February
Start date21/02/2016 End date21/02/2016 Route affected Download map of route afected First TransPennine Express between Manchester Airport and Blackpool North
Northern Rail between York / Leeds / Manchester Oxford Road and Blackpool North and also between Colne and Blackpool South


Train operators affected First TransPennine Express; Northern Rail; Description Engineering work is taking place between Preston and Blackpool North / Blackpool South with all lines closed.
Buses replace trains between Preston and Blackpool North and also between Preston and Blackpool South.

Planning your Journey
For full details of these changes and the impact on your journey, please use the National Rail Enquiries Journey Planner
Does anyone know what work is programmed?
 

LNW-GW Joint

Veteran Member
Joined
22 Feb 2011
Messages
21,902
Location
Mold, Clwyd
First run round the Euxton-Salford route for 7 weeks.
The only thing new on the electrification front that I noticed was a run of marker pegs and some light excavations for mast bases, between Euxton Jn and Chorley tunnel.
I didn't make it to Blackpool, so I don't know what the weekend's blockade achieved.
Anybody else know what was going on?
 

LDECRexile

Established Member
Joined
30 Jan 2014
Messages
2,149
Location
Southport, UK
First run round the Euxton-Salford route for 7 weeks.
The only thing new on the electrification front that I noticed was a run of marker pegs and some light excavations for mast bases, between Euxton Jn and Chorley tunnel.
I didn't make it to Blackpool, so I don't know what the weekend's blockade achieved.
Anybody else know what was going on?

Sticks and scrapes = action on the ground! Yippee!
 

Viscount702

Member
Joined
7 Sep 2011
Messages
336
According to post 2442 above they are supposed to be doing trial holes and bases between Adlington and Lostock at the moment.

Do we take it from LNW-GW Joint's post above that nothing is happening here at present
 

Joseph_Locke

Established Member
Joined
14 Apr 2012
Messages
1,878
Location
Within earshot of trains passing the one and half
According to post 2442 above they are supposed to be doing trial holes and bases between Adlington and Lostock at the moment.

Do we take it from LNW-GW Joint's post above that nothing is happening here at present

All the BB-installed bases between Lostock and (at least) Horwich now have a tag giving the new MG structure number - a portent of main steel?
 

Howardh

Established Member
Joined
17 May 2011
Messages
9,770
So we have to wait another bloody year to get the electrification Pre/Bon/Manchester - Dec 2017 is the earliest date now.

Why don't they abandon the whole thing and give us the best second-hand stock that's being released from other lines that have been electrified, or replaced by new stock?

Some Northern Powerhouse. We're the Forgotten Lands.
 

ALX400

Member
Joined
7 Dec 2009
Messages
326
Location
Bolton
All the BB-installed bases between Lostock and (at least) Horwich now have a tag giving the new MG structure number - a portent of main steel?

Isnt the end of March the timescale for starting to see Masts Joe ?, sure i've read that somewhere, hope it is like :lol:
 

snowball

Established Member
Joined
4 Mar 2013
Messages
8,144
Location
Leeds
Isnt the end of March the timescale for starting to see Masts Joe ?, sure i've read that somewhere, hope it is like :lol:

The document posted in #2442 and #2453, covering Lostock to Euxton, has the first masts up in May between Blackroad and Lostock. I haven't seen a corresponding document for Deal Street or Ordsall Lane to Lostock.
 

GRALISTAIR

Established Member
Joined
11 Apr 2012
Messages
10,477
Location
Preston Lancs
Isnt the end of March the timescale for starting to see Masts Joe ?, sure i've read that somewhere, hope it is like :lol:

The document posted in #2442 and #2453, covering Lostock to Euxton, has the first masts up in May between Blackroad and Lostock. I haven't seen a corresponding document for Deal Street or Ordsall Lane to Lostock.

Adlington -Lostock should be happening now according to the docs. :D
 

LNW-GW Joint

Veteran Member
Joined
22 Feb 2011
Messages
21,902
Location
Mold, Clwyd
Adlington-Lostock should be happening now according to the docs. :D

No masts before May according to the dates quoted.
Foundations Lostock-Blackrod have been about 75% finished for 9 months, maybe 50% Blackrod-Adlington.
Plenty of trial holes all along the route.
 

GRALISTAIR

Established Member
Joined
11 Apr 2012
Messages
10,477
Location
Preston Lancs
No masts before May according to the dates quoted.
Foundations Lostock-Blackrod have been about 75% finished for 9 months, maybe 50% Blackrod-Adlington.
Plenty of trial holes all along the route.

My misread - trial holes Feb 2016 -foundations start Feb -April 2016 and steel starting May 2016.
 

LDECRexile

Established Member
Joined
30 Jan 2014
Messages
2,149
Location
Southport, UK
I've been knocked for six by family stuff for a few weeks, I now aspire to get back into gear.

I attach page 18 of the current Modern Railways which sets out most expected dates for NW Electrification.
 

Attachments

  • ModernRailwaysMarch2016p18.jpg
    ModernRailwaysMarch2016p18.jpg
    147.9 KB · Views: 107

LDECRexile

Established Member
Joined
30 Jan 2014
Messages
2,149
Location
Southport, UK
I was delighted to come back from London yesterday to find an unsolicited approach from Chris Davis, offering to share the album of photos of the Ordsall Chord works he has started.

Not only has this added good material which will grow, but it has also shown me an omission I'd made when I started the new Blackpool-Manchester flickr album in the New Year, ie I forgot to re-create the links to Ian Fitter's Ridgway album and the Real Mad Haggis's Ladybridge album which were long standing opening features of the earlier album.

I've therefore added the first image in the same style as before, if you click on it you are offered links to Chris's, Ian's and Haggis's albums.

To see for yourself please go there from here:

https://www.flickr.com/photos/127646831@N03/albums/72157661069863633

Welcome aboard Chris, thank you for your initiative.
 

absolutelymilk

Established Member
Joined
18 Jul 2015
Messages
1,587
I've been knocked for six by family stuff for a few weeks, I now aspire to get back into gear.

I attach page 18 of the current Modern Railways which sets out most expected dates for NW Electrification.

When it says Huyton to Roby four-tracking, where exactly will be four-tracked? Just from Huyton station to Roby station?
 

notlob.divad

Established Member
Joined
19 Jan 2016
Messages
1,609
Thanks, it says "as close to Roby station as possible" for the junction, are there physical constraints on making it four-track closer to Wavertree or is it a financial constraint?

This isn't strictly Manchester - Blackpool Electrification, and there is another thread on it. But at the risk of a moderator's rath, if you look on Google maps satellite view you can see where the 4 tracking will end at Roby Junction. It is just missing the turnout. I think it was technically feasible to run it closer to Broad Green but it would have to finish by the station. 4 tracking couldn't run through Broad Green or beyond without major civil works at the start of the M62.

If you want to carry on the discussion I suggest we switch to one of the other threads
 

LNW-GW Joint

Veteran Member
Joined
22 Feb 2011
Messages
21,902
Location
Mold, Clwyd
No obvious progress at lineside between Victoria and Euxton today, on the Down side anyway.
I went through to Blackpool, and likewise nothing to see by way of route upgrades, either for electrification or resignalling.
Though the current weekend possessions must be for something.
There's an awful lot to do to get electric trains running to Blackpool in a little more than 2 years.

The best part of the trip was the incredibly clear view of the snow-covered Lakeland fells from near Poulton, at a range of more than 30 miles.
 
Last edited:

Hophead

Established Member
Joined
5 Apr 2013
Messages
1,398
I've been knocked for six by family stuff for a few weeks, I now aspire to get back into gear.

I attach page 18 of the current Modern Railways which sets out most expected dates for NW Electrification.

I have to say that I find it regrettable that Network Rail are not attempting to prioritise either the Bolton or the Stalybridge scheme, with a view to getting a few more DMUs displaced in a shorter timeframe, rather than working on both simultaneously (or so it seems from the published dates).

I'm sure there will be a good reason, but it's not immediately clear what that reason might be.
 

Class 170101

On Moderation
Joined
1 Mar 2014
Messages
8,661
Depends upon where possessions are already booked.

Operators don't like NR changing possessions at late notice just to suit NR. Indeed they usually, in my experience, throw them out.
 

Hophead

Established Member
Joined
5 Apr 2013
Messages
1,398
My comment arises from the fact that the whole project's running late and has had to be substantially replanned in any case. In view of that, I was wondering if there would have been merit in trying to get one part complete sooner than December 2017. Obviously that's not going to happen now, so it's rather academic.
 