Bishton flyover

Status
Not open for further replies.
Joined
12 Dec 2009
Messages
634
Location
Carmarthen
Could someone explain what is this for? There are 4 lines before it and 4 lines after it so if freight on the relief line needs to be passed by passenger workings it can be anyway. Could just sets of points have been used to divert workings onto the appropriate lines depending on whether it is heading for Severn Tunnel or Caldicot direction?
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

O L Leigh

Established Member
Joined
20 Jan 2006
Messages
5,609
Location
In the cab with the paper
Quite simply, it reduces the number of conflicting moves between trains on the Up Main and Up Relief. Trains can get from the yards at Newport and Llanwern towards Severn Tunnel Junction without having to cross over the main lines.