Berwick (Sussex) level crossing blocked 30/5/23

Status
Not open for further replies.

Desirolly

Member
Joined
14 May 2020
Messages
50
Location
Hertford Loop

Attachments

  • IMG_5543.png
    IMG_5543.png
    477 KB · Views: 79
Last edited:
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

TrainGeekUK

Member
Joined
15 Jun 2019
Messages
124
The situation at Berwick today with regard to the farming vehicle blocking the line at a level crossing.
Not a good start to the half term break!

Who would ultimately be responsible for the delay?

Clearly it’s not a Network Rail fault but would there be an investigation as to how such a vehicle could break down in such an awkward place!

1685444212317.png
 
Last edited:

zwk500

Veteran Member
Joined
20 Jan 2020
Messages
18,641
Location
Northampton
The situation at Berwick today with regard to the farming vehicle blocking the line at a level crossing.
Not a good start to the half term break!

Who would ultimately be responsible for the delay?

Clearly it’s not a Network Rail fault but would there be an investigation as to how such a vehicle could break down in such an awkward place!
I think it's still an NR delay, although it might be the case that NR can claim some of the costs back. If the driver has stopped and phoned the box to get permission to cross then it's just one of those things, I think. A breakdown can happen anywhere, although there will probably be a NR person looking into if anything to do with the LX was involved in the incident (which might take all of 5 mins).

Which way was the tractor crossing? - from the position of the axles it looks like it was heading southbound (picture is from the up platform looking back towards Eastbourne). IIRC there's a bit of a dip on the south side of the line, but the northern approach is fairly level. Although it isn't so steep that it would cause the hitch to strike the road, I'd have though. (I used to drive that way to School in Sixth Form).

BTW - Could you clarify in the thread title this is the Berwick in Sussex, not Berwick-Upon-Tweed?
 

Javelin_55

Member
Joined
9 Apr 2020
Messages
156
Location
South East
Who would ultimately be responsible for the delay?

This would be a NR delay. The most likely delay code at face value would be XN (Network Rail External).

There would certainly be an investigation as to how this happened. The XN code would also cover the possible scenario of the vehicle striking the barriers and causing the detachment.
 

Bald Rick

Veteran Member
Joined
28 Sep 2010
Messages
35,958
Yes, XN

In delay attribution terms, anything that isn’t a TOC / FOC cause must be an NR cause.

(exceptions apply for delays occurring on non NR railways).
 

fgwrich

Established Member
Joined
15 Apr 2009
Messages
10,653
Location
Hampshire
Looks to be a bit of a S**t situation given what those tankers are usually used for! At least there's non need to spread any rumours with this one!

(Sorry, couldn't help myself with that pun :lol: )
 