Falcon1200
Established Member
i think a lot of the emergency planning leaves a lot to be desired to be honest. I think better planning would help.
e.g. If there is disruption north of Preston blocking one track you probably do London-glasgow (fast) and Manchester-Edinburgh as your two trains an hour. and if there is space you keep barrow-Manchester in play as well - otherwise that can terminate at Lancaster.
i assume when lines are blocked the freight is cancelled or rerouted.
Two issues, where are you diverting the freight, and there aren't enough crossovers to do single line working to a significant extent.
As I may have said once or twice before (or actually, innumerable times when I was Controller for the WCML in Scotland) bi-directional signalling between say Preston and Law Jc, where the route is mostly double track with no feasible diversion, would be invaluable. However under the current signalling, staff have to attend on site for Single Line Working (SLW), by the time this is introduced trains on the blocked line will already have been standing for up two hours, and once SLW is in operation trains on the unaffected line are disrupted too; Not to mention the next workings of the stock and crew of all those trains.
As to freights, these have a right to run too, and cannot simply be abandoned.