R

RailUK Forums

Merle Haggard

Established Member
Joined
20 Oct 2019
Messages
3,991
Location
Northampton
Did you mean G to Y?
Sorry, yes you are correct.

//

To amplify; although the signals reduced by two steps it was one step at a time, so the last green went G > YY and, after a pause as the train in front set back, YY > Y. as it was approached (if there was long visibility),- and all the other signals visible in the distance also stepped down. which understandably alarmed the driver of the following train. Stretches of the line South of Hanslope allow early sighting of signal aspects.

As an aside, the original 4 aspect signals on the line when cleared from R to G - after, for instance, a junction being cleared by another train in the opposite direction - went briefly but visibly R > Y > YY > G, I don't think this happens now. Presumably mechanical control involved
 

dk1

Veteran Member
Joined
2 Oct 2009
Messages
19,929
Location
East Anglia
Obviously not related to this incident but due to unforeseen unit swaps today, some services are not calling at South Parkway.
 

8J

Member
Joined
31 Aug 2009
Messages
679
Obviously not related to this incident but due to unforeseen unit swaps today, some services are not calling at South Parkway.
Indeed. I believe an 807 suffered some significant damage after striking a couple of deer near Apsley which caused delays and 390s being stepped up to work on 807 diagrams.
 

Horizon22

Established Member
Associate Staff
Jobs & Careers
Joined
8 Sep 2019
Messages
11,044
Location
London
It is possible for a train to set back after an overrun. There are some conditions that must be met but if they are then it’s usually done.

Some TOCs have "forward only" policies.
 

sharpener

Member
Joined
4 Oct 2018
Messages
410
Some TOCs have "forward only" policies.

Is there any justification for the differences and are they going to be rationalised after re-nationalisation? How is this going to be done in practice?
 
Last edited:

Horizon22

Established Member
Associate Staff
Jobs & Careers
Joined
8 Sep 2019
Messages
11,044
Location
London
Is there any justification for the differences and are they going to be rationalised after re-nationalisation? How is this going to be done in practice?

Safety risk and tolerance I guess.

And how is what exactly going to be "done in practice"? A forward-only policy or the rationalisation? Because I am not certain the latter will happen (alongside a great many other things).
 
Joined
28 Oct 2017
Messages
254
Yeah, merseyrail does now
That would be seriously inconvenient if they repeated one of the two overshoots I have experienced, which was Capenhurst (trainee driver with a sudden rain shower on the long 70 mph straight), because the next journey of that train back from Chester isn't booked to stop at Capenhurst. That time on a 507/508 they called signaller and backed it up from the rear cab.

The other was Bromborough in fog (again a dead straight, and the stations don't line up with signals), and just let on/off through the guards door as the rear of the train was platformed.
 
Status