It’s not that big a job. It was a separate job, running to a later schedule (originally) and couldn’t be brought into the blockade. Just bringing forward the platform extension work into the block was quite a challenge. Had the blockade been delayed to accommodate the LX commissioning it would have to have gone back at least a year, and then the risk of TSRs at Horsham (and elsewhere where track and Civils work was done) would have been greater. Also it would have extended the blockade over the 9 days into another working week. Better to have 9 + 2, with 6 of the days weekends, than 11 with 4 of them weekends.
Definitely the right decision.
Thanks for some more background and a would have thought a TSR, unless it was 5mph, at Horsham wouldn't have had a material impact on the service given everything stops there.
Anyhow looking at the public version of EAS 2022 v4 these are the disruptives through Horsham although I acknowledge half of the year has already been superseded by CPPP so maybe different but disruptives tend to hold
wk43 - 27hr track mtce
wk51 - 27hr wheel timbers
wk11 - 52hr l/xing renewal pt1
wk12 - 52hr l/xing renewal pt2
wk21 - 52hr track renewal
wk22 - 52hr track renewal
wkk3 - 27hr track mtce
So the only reduction is the M-F blockade possession over this year. I get L/Xing renewals are a 1 in 30 year job and at least they've incorporated the new connection presumably as part of the data change for Littlehaven but we really do need to get to a place where blockades deliver levels of work that enable a reduction in disruptives for at least the following five years.