2005 Gerrards Cross tunnel collapse

Status
Not open for further replies.

Signal Head

Member
Joined
26 May 2013
Messages
460
I've just come across this page (New Civil Engineer) with information concerning the final HSE report on the collapse of the 'Tesco Tunnel' in 2005 which some may remember. It was big news at the time, and it was most fortunate that there wasn't a train inside the structure when the collapse occurred. The article describes a catalogue of miscommunication, lack of communication and (to me) general incompetence and I thought it might be of interest to some on here.

It seems the report was never released, and in fact attempts to obtain it were repeatedly refused, which in itself is rather dubious. It is available now apparently thanks to one person's persistence via FOI requests.
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

Railsigns

Established Member
Joined
15 Feb 2010
Messages
2,754
Gareth Dennis has put a video on YouTube looking at the report in detail.

Why did the HSE not publish their original report? Well, thanks to an intrepid fan of the show, we've finally got hold of it! We'll be lawyering up as we flick through the pages of the draft report and stare in horror and the engineering negligence that nearly led to a multi-fatality rail disaster.
 

150219

Member
Joined
24 Nov 2009
Messages
471
I've just come across this page (New Civil Engineer) with information concerning the final HSE report on the collapse of the 'Tesco Tunnel' in 2005 which some may remember. It was big news at the time, and it was most fortunate that there wasn't a train inside the structure when the collapse occurred. The article describes a catalogue of miscommunication, lack of communication and (to me) general incompetence and I thought it might be of interest to some on here.

It seems the report was never released, and in fact attempts to obtain it were repeatedly refused, which in itself is rather dubious. It is available now apparently thanks to one person's persistence via FOI requests.
It was a close run thing. There was a London-bound train standing in the up platform at Gerrards Cross and a down train between Denham Golf Club and Gerrards Cross at the time it collapsed.
 

edwin_m

Veteran Member
Joined
21 Apr 2013
Messages
28,629
Location
Nottingham
This article on HS2 green tunnels emphasises how the covering over is co-ordinated to avoid a similar collapse.


Backfilling to each side and above the tunnel is carried out to a tightly controlled sequence, including a ‘permit to backfill’ process. This avoids possible unequal loading which could deform or damage the structure. Backfill material is placed and compacted in 250mm layers using selected arisings from the tunnel excavation or from nearby.
 

satisnek

Member
Joined
5 Sep 2014
Messages
1,097
Location
Kidderminster/Mercia Marina
Remember it well. In the aftermath Chiltern Railways offered a 50% fares discount so I had at least two cheap London trips even though they did involve a lengthy detour via Aylesbury. At the time it was said that a train had just passed through before the collapse, implying that the train precipitated it.
 

edwin_m

Veteran Member
Joined
21 Apr 2013
Messages
28,629
Location
Nottingham
At the time it was said that a train had just passed through before the collapse, implying that the train precipitated it.
Possible that the vibrations from a train finally brought it down, but it would have had to be highly unstable for that to trigger it. So it doesn't remove the responsibility from the teams that created the instability by messing up with the earth covering.
 

satisnek

Member
Joined
5 Sep 2014
Messages
1,097
Location
Kidderminster/Mercia Marina
Possible that the vibrations from a train finally brought it down, but it would have had to be highly unstable for that to trigger it. So it doesn't remove the responsibility from the teams that created the instability by messing up with the earth covering.
Most definitely. Trains don't normally leave collapsed overline structures in their wake.
 

Pigeon

Member
Joined
8 Apr 2015
Messages
1,123

Thanks for that.

I always assumed it had been Tesco who had come up with the idea in the first place because who else would it be. I didn't realise until I read that report that it was Railtrack, of all people, who came up with it, and then touted it round until they found some sucker who would bite.

I guess this wasn't generally known at the time either, because the wikipedia article on the tunnel quotes the leader of South Bucks council as saying, after the collapse, "We want to know why such a hugely complex engineering process has been deemed necessary to build a relatively small new Tesco store". It would surely have strengthened the protesters' position considerably if they had known that the answer was "it wasn't".
 

Thebaz

Member
Joined
24 Nov 2016
Messages
495
Location
Purley
My word... As a chartered geospatial engineer with responsibilities for monitoring structures, I can't believe what I just read. To be consistently reporting large (and growing) deflections that were simply ignored by the project management is just.... it's just... No words. It's criminal, that's what it is. A total miracle no-one was killed or injured.
 