• Our new ticketing site is now live! Using either this or the original site (both powered by TrainSplit) helps support the running of the forum with every ticket purchase! Find out more and ask any questions/give us feedback in this thread!

Search results

  1. H

    BR Department Abbreviations Help Please

    Much of the main buried routes on the Western were hand dug. Not all of the resignalling had been completed as electrification commenced. The main cable strike was in the Pangbourne area which was a buried telecom type cable which still supported signalling circuits.
  2. H

    BR Department Abbreviations Help Please

    Utter tosh. Only 3 cables were struck during the installation and only 1 of those caused delays.
  3. H

    Railway telegraph poles - how many are left...and in use?

    I remember the winter of 1982 when mile upon mile of overhead pole route came down due to the weight of snow on the wires. I'm pretty sure it was around the Yeovil area. Copper everywhere and snapped poles strewn around. We used every bit of interruption cable we had laid on the ground to...
  4. H

    Railway telegraph poles - how many are left...and in use?

    I think it should be remembered that the wires on the poles were a lot bigger than the small stuff used for telephone circuits to domestic properties. They weren't measured by diameter but by poundage. So you'd take a block of copper, stretch it for a mile and that's the final size. The normal...
  5. H

    Railway telegraph poles - how many are left...and in use?

    I was watching the Blue Lamp film recently and in the scene where Dirk Bogarde has crossed the line escaping capture you can see him climbing the embankment past a pole where the cables come down and cross under the bridge. We used to have a piece of kit called a Mox iron which was used to...
  6. H

    Signalling(?) cable theft (again) between Grantham and Newark Northgate

    Looking at the picture the cable on the left is an old telecom type cable which contains a bit more metal than just copper.
  7. H

    Saddest sight - The decline of Stockton station

    The windows and frames were in the habit of falling out, hence the plywood panels. I think the yellow marks maybe where they've been inspected and indicate which ones need repair and which ones don't.
  8. H

    Adjusting the clocks

    I had a chat with one of my ex colleagues who used to adjust the clocks at Temple Meads in the 80s. There were 3 systems at the station apparently and when I asked where they got the accurate time from to do the adjustments he said "we used our watches, nothing more than that" I remember buying...
  9. H

    Multiple lines closed 27 Jan in South West and central South due to flooding

    Those are 1 ton bags of aggregate, be it ballast or otherwise. It's the standard way of getting stone to a site and putting it where needed. I'm sure one of the Pway experts on here will add further details.
  10. H

    Yellow painted footways at Truro

    I suspect that they are used as covers for the troughs leading to the locs. The drivers walkway on the east end of Bristol Temple Meads leading up to the train care depot at Barton Hill are used in that way. Trough lids are notorious in icy weather.
  11. H

    Examples of Platforms built out over old tracks

    Not sure if this counts but wasn't Filton Abbeywood Station built on the old NCB Sidings ?
  12. H

    Oxford Corridor Phase 2 & Platform 5 updates

    Trial holes are only part of a whole process which is undertaken prior to excavations going ahead. I would spend hours going through historical plans, rail enthusiasts photos, aerial photos etc etc. You are correct in that you'll never find everything but you have to make every effort. With...
  13. H

    Oxford Corridor Phase 2 & Platform 5 updates

    Before I finished work with NWR in 2021 I was the buried services manager for Infrastructure Projects on the Western. It was my job to assist the contractors in locating and identifying buried services. The first thing I would always tell the contractor was that if you dug a trench from one...
  14. H

    Future of the GWR electrification

    The Henbury line wasn't re signalled as part of the BASRE project so that work will eat into any funding. Would it be a separate project ?
  15. H

    Future of the GWR electrification

    The whole of the station is being rewired but a lot of work remains to be done once the scaffolding associated with the roof works comes down. In addition all the redundant signalling, telecoms, CIS, PA cabling and equipment left and never recovered throughout the station is/has been/to be removed.
  16. H

    Anyone Know what the building is in Wolverton station car park

    I don't know Wolverton but I suggest it's either a Relay Room or a Telecom Node (FTN)
  17. H

    Oxford Corridor Phase 2 & Platform 5 updates

    All of the legacy cable drawings for the MLN were available. Now it doesn't matter if the exact location of the cables is shown on those drawings or not, what is important is the fact that something is there. So trial holes were dug at each location where a pile was to be installed, if something...
  18. H

    Oxford Corridor Phase 2 & Platform 5 updates

    Well seeing as I'm the expert I can assure you only one cable was hit.
  19. H

    Oxford Corridor Phase 2 & Platform 5 updates

    They didn't hit multiple cables and in fact after the one incident at Pangbourne they brought in an expert who in fact stopped further strikes completely, not only for GWEP but all major projects on the Western.

Top