800001

Established Member
Joined
24 Oct 2015
Messages
7,307
The 810 will be a write off. Modern day trains are not designed to survive a crash like this. They are designed to protect the passengers inside.

Looking at the pictures, the impact energy has traveled along the subframe of the 810, crushing the vestibule ends and couplings.

I’m not a train designer, but the vestibule area looks like being the crumple/energy absorbing zones. Perhaps Hitachi designed the IEP to sacrifice the passengers in the vestibule to protect the main carriage. Can anyone confirm this?
I've not seen any pictures of the 810 showing crushed vestibules?
Can you provide some on here?
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

superalbs

Verified Rep - Superalbs Travels
Joined
3 Jul 2014
Messages
2,834
Location
Kraków
Was it not the case that Hitachi supposedly did not accept orders for individual orders (for example, for lengthening), which therefore leaves an entirely new unit or nothing as the only two options?
 

sprinterguy

Veteran Member
Joined
4 Mar 2010
Messages
11,567
Location
Macclesfield
Looking at the pictures, the impact energy has traveled along the subframe of the 810, crushing the vestibule ends and couplings.

I’m not a train designer, but the vestibule area looks like being the crumple/energy absorbing zones. Perhaps Hitachi designed the IEP to sacrifice the passengers in the vestibule to protect the main carriage. Can anyone confirm this?
None of the photos I've seen/searched for seem to show any crushing of the vestibules of the 810 unit. Even where the front corner of the derailed third coach has impacted the trailing end of the second coach ahead of it, it still appears to be fully square in the images available.
 
Last edited:

Peter Mugridge

Veteran Member
Joined
8 Apr 2010
Messages
17,801
Location
Epsom
The key is probably any hidden damage to the structure of each carriage; with integral construction it is quite possible for the visible bits to look perfectly all right, but what might have happened to the underneath structural bits that are directly in line with the impact, such as the mountings for the anti-climb devices?

If these are twisted in any way, replacement is likely to be the cheaper option than repair.
 

Nogoohwell

Member
Joined
14 Aug 2020
Messages
104
Location
London
None of the photos I've seen/searched for seem to show any crushing of the vestibules of the 810 unit. Even where the front corner of the derailed third coach has impacted the trailing end of the second coach ahead of it, it still appears to be fully square in the images available.
there is a video on the BBC website. It shows the connections between the rear three coaches in the 810, all compacted and judging by the sun reflection, the body is warped.
Sorry can’t link it from here, but try searching for it on the bbc, publication date 20th June
 

sprinterguy

Veteran Member
Joined
4 Mar 2010
Messages
11,567
Location
Macclesfield
there is a video on the BBC website. It shows the connections between the rear three coaches in the 810, all compacted and judging by the sun reflection, the body is warped.
Sorry can’t link it from here, but try searching for it on the bbc, publication date 20th June
The corridor connections between carriages 3, 4 and 5 have certainly been compressed so that the vehicle ends appear to be touching. The vestibules look to be intact though.
 
Last edited:

RUK

Member
Joined
5 Aug 2009
Messages
421
Location
East of England
Presumably 810 015 is insured - would the payout from it be enough to cover enough of the cost to Rock Rail/EMR to finance the cost of a replacement unit? I suppose a new contract with Hitachi would have to be drawn up for a new unit, though.
 

Peter Sarf

Established Member
Joined
12 Oct 2010
Messages
9,594
Location
Croydon
Presumably 810 015 is insured - would the payout from it be enough to cover enough of the cost to Rock Rail/EMR to finance the cost of a replacement unit? I suppose a new contract with Hitachi would have to be drawn up for a new unit, though.
I wonder if trains are insured?

If you have a large enough fleet it is probably cheaper to cover the risk yourself. Obviously TOCs could well have liability insurance. A road equivalent would be a fleet operator just having third party only insurance. Your not going to lose a significant proportion of the fleet in one go and if you have insurance against that then the insurance company is taking a big risk and might charge a larger premium for that if it is a realistic risk.

I also wonder if an order for just one class 810 would be expensive, much more expensive than 1/33 of the original order cost.
 

dosxuk

Established Member
Joined
2 Jan 2011
Messages
2,434
I wonder if trains are insured ?. If you have a large enough fleet it is probably cheaper to cover the risk yourself. Obviously TOCs could well have liability insurance. A road equivalent would be a fleet operator just having third party only insurance. Your not going to lose a significant proportion of the fleet in one go and if you have insurance against that then the insurance company is taking a big risk and might charge a larger premium for that if it is a realistic risk.
When BA had their oopsie between a building in South Africa and a 747 wing, it came out that they self-insured the aircraft they owned outright but had full insurance for those that were leased.

It wouldn't surprise me if it was a condition of the lease for both aircraft and trains that they have insurance, not least to guarantee the leasing company their income for the expected life of the asset.
 

Bikeman78

Established Member
Joined
26 Apr 2018
Messages
6,172
...and in an earlier accident in the same area, two brand new class 321 carriages were built - so again, precedent for partial replacement.
It was four new vehicles. Two vehicles from 321420 switched to 321418 and returned to service. A new 321420 was built. Interestingly, the vehicles took the numbers of the four scrapped ones. Both units rans misformed for the rest of their careers and six vehicles survive in 320418 and 320420.
 
Last edited:

norbitonflyer

Established Member
Joined
24 Mar 2020
Messages
5,675
Location
SW London
The issue with crumple zones is that what looks like superficial damage to just the end panels actually is far more serious and results in the whole vehicle being written off. Once key structural members have been taken past their design loads, that's basically it for the vehicle, even if the passenger parts look mostly ok.
In reacll that there was comment at the time of the 1985 Battersea Park rear end collision that the two mark 1 vehicles that actually took the force of the colliion (an East Sussex DEMU power car and a Gatwick Express GLV) looked rather less damaged than the Mark 2 vehicle immediately behind the GLV. There may have been damage to the underframes though - certainly the DEMU power car was condemned later that year, as were the first two Mark 2s of the Gatwick train - but not, it would seem, the GLV.

. I seem to recall reading that the engine mountings of the Class 73 that was propelling the second train were also damaged, so the shock of the impact passed right through the train
Battersea%20Pk%201985.png.opt850x494o0%2C0s850x494.png
 

jthjth

Member
Joined
10 Apr 2015
Messages
382
Could EMR use a standard 5 car 26 metre 80x, possibly tagged onto an existing production run? That in multiple with a 5 car 810 comes to 245 metres. Should fit the St Pancras platforms?
 

800001

Established Member
Joined
24 Oct 2015
Messages
7,307
Could EMR use a standard 5 car 26 metre 80x, possibly tagged onto an existing production run? That in multiple with a 5 car 810 comes to 245 metres. Should fit the St Pancras platforms?
The only existing production run is the current build of 810 units for EMR.
The last 2 units are in the final production stage .
 

Zomboid

Established Member
Joined
2 Apr 2025
Messages
2,242
Location
Oxford
They'll just run with one fewer 10 car diagram than they'd planned, to start with. If a new 810 is ordered then it'll be at the back of the queue.
 

norbitonflyer

Established Member
Joined
24 Mar 2020
Messages
5,675
Location
SW London
In reacll that there was comment at the time of the 1985 Battersea Park rear end collision that the two mark 1 vehicles that actually took the force of the colliion (an East Sussex DEMU power car and a Gatwick Express GLV) looked rather less damaged than the Mark 2 vehicle immediately behind the GLV. There may have been damage to the underframes though - certainly the DEMU power car was condemned later that year, as were the first two Mark 2s of the Gatwick train - but not, it would seem, the GLV.

. I seem to recall reading that the engine mountings of the Class 73 that was propelling the second train were also damaged, so the shock of the impact passed right through the train
Looking at the report on this, there seem to be some parallels.
Rear end collision, after the first train stopped so a signalling fault could be investigated
Second train running on a succession of yellows, driver missed a red.

Differences
The driver survived, and could report what had happened. He was quite candid that he had simply missed the signal.
He had been passing a number of signals that went from red to yellow as he approached, but missed that the last one had not done so.
On the left hand curve, and on the left hand track, he had read through to the next signal, cleared for the preceding train, but that train itself had been obscured by the girders of a bridge
The first train was moving off under the just-cleared signal, so the closing speed was lower and the brakes were not on, making the impact less severe

The reported fault was with a track circuit. the DEMU had been diverted from fast to slow so the fault (on the up fast) could be investigated. It had been held at the signal to wait for a down train to pass.
 

Merle Haggard

Established Member
Joined
20 Oct 2019
Messages
3,879
Location
Northampton
Some of the coaches involved in the Bushey high speed derailment (23/10/10) were stored for a while in the Riverside sidings at Northampton. They were Mk3s,and although they didn't seem to be noticeable damaged each window reflected a slightly different angle of image along the coat suggesting a small but crucial twist distortion. You had to view from an angle to see this and all the photos of the 810 after the collision seem to be side on.
 