Recent content by contractor1

  1. contractor1

    Filton Bank 4-tracking visualisation

    Quick update....last set of S&C going in tonight (new 7007) at FAW all down to alstom testing everything then!
  2. contractor1

    Filton Bank 4-tracking visualisation

    A contract to relay 4 miles of track with multiple s&c
  3. contractor1

    Filton Bank 4-tracking visualisation

    this is what happens & how things are planned when network rail gives a construction company!
  4. contractor1

    Filton Bank 4-tracking visualisation

    2 weekend 55 hr blocks in july, first 13th - 16th, second 20th - 23rd blockade is on October 26th til November 19th
  5. contractor1

    Filton Bank 4-tracking visualisation

    Weekend 8 kirow crane landing S&C
  6. contractor1

    Filton Bank 4-tracking visualisation

    From weekend 7 blockade! Another blockade this weekend too!
  7. contractor1

    Filton Bank 4-tracking visualisation

    blockade is from 26th october to 19th november
  8. contractor1

    Filton Bank 4-tracking visualisation

    no new station at ashley hill! no new stations being built on the filton 4 track project apart from a new platform at filton filton
  9. contractor1

    Filton Bank 4-tracking visualisation

    the footings next to the down filton are in the way of the new track thats going back in! a new single span footbridge is goning to replace the old one
  10. contractor1

    Filton Bank 4-tracking visualisation

    no ballast being dropped on the formation for a while yet, just digging for the new track bed. drainage works filton end near lockleaze bridge in a couple of weeks though ;)
  11. contractor1

    Filton Bank 4-tracking visualisation

    sorry week 22 26th august
  12. contractor1

    Filton Bank 4-tracking visualisation

    digging for the track bed starts 22 august!
  13. contractor1

    Unexpected Visitors To Signal Boxes

    i have visited many signal boxes on pre site visits for when line blockages have been booked, mainly to introduce myself, check paperwork and just a general chat. very rarely have i been given the.....OUT!