Our new ticketing site is now live! Using either this or the original site (both powered by TrainSplit) helps support the running of the forum with every ticket purchase! Find out more and ask any questions/give us feedback in this thread!
My eyes have indeed deceived me whilst driving past, the mast on the platform at Blackrod hasn’t yet got its top half it’s the one behind it I caught glimpse of, will keep aclook out this weekend though
I’m beginning to think that if they actually blitz the stations and progress like it is at the moment May/June might not be so far off, I still think around July though as there’s still those issues south of Bolton
As scheduled Poulton Signal Box is no more and was demolished today.
New mast has appeared on the down next to Harper’s Lane Bridge in Chorley looks like a TTC one
We’ve got wires :lol::lol:
Just been down to Lostock Lane Bridge and wires are up from as far back towards Lostock Station, they stop short Just past the work site access point, The wiring train has certainly been busy I’m guessing it’ll be back at weekend, the areas ready look to be between...
Many thanks for that detailed post Dave, very informative as always :D, I’m on late shifts shortly so will keep an eye out from Blackrod towards Preston, I know they have been installing the raised concrete bases in the cutting At Chorley just before the tunnel nightly recently, I’ve also...
We are aware of an issue with emails from the Forum to Microsoft-based email accounts (hotmail/outlook/live.com email addresses). This is being looked into currently, thanks for your patience meanwhile.