My eyes have indeed deceived me whilst driving past, the mast on the platform at Blackrod hasn’t yet got its top half it’s the one behind it I caught glimpse of, will keep aclook out this weekend though
I’m beginning to think that if they actually blitz the stations and progress like it is at the moment May/June might not be so far off, I still think around July though as there’s still those issues south of Bolton
As scheduled Poulton Signal Box is no more and was demolished today.
New mast has appeared on the down next to Harper’s Lane Bridge in Chorley looks like a TTC one
We’ve got wires :lol::lol:
Just been down to Lostock Lane Bridge and wires are up from as far back towards Lostock Station, they stop short Just past the work site access point, The wiring train has certainly been busy I’m guessing it’ll be back at weekend, the areas ready look to be between...
Many thanks for that detailed post Dave, very informative as always :D, I’m on late shifts shortly so will keep an eye out from Blackrod towards Preston, I know they have been installing the raised concrete bases in the cutting At Chorley just before the tunnel nightly recently, I’ve also...
Just seen on twitter that they are installing foundations at Red Moss in Horwich this weekend, it looked as though all the masts were up along that stretch:rolleyes:
Cheers Dave
Plenty of work trackside at Chorley, new mast at Blackrod and a new large base about to be constructed as per photos, it’s odd where these bad ground contortions seem to be but nonetheless they seem to be getting amongst it