Marshlink Line 9 Week Closure

Status
Not open for further replies.

Ibex

Member
Joined
23 Jan 2010
Messages
800
It has been announced that a 9 week closure of the Marshlink line from Ashford International to Hastings will take place from 9th January despite local protest.

The closure is to allow Network Rail to carry out work on the Ore tunnel, replace bridges at Three Oaks and Doleham, and also maintenence of the embankments at Ashford International and Ham Street. There will also be track improvements between Rye and Hastings to allow for a line speed increase in the future.

Replacement buses and taxis will operate over the 9 week period.

Full article here.
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

Nym

Established Member
Joined
2 Mar 2007
Messages
9,781
Location
Somewhere, not in London
That mean that TPE can borrow Marshlink's turbostars to deal with their chronic overcrowding while it's being done? Then a'la scotrail just keep them?
 

OxtedL

Established Member
Associate Staff
Quizmaster
Joined
23 Mar 2011
Messages
2,631
Announced a long time ago now. http://www.railforums.co.uk/showthread.php?t=53254

Would be nice to think that they'd take this opportunity to do something useful at all (to the rest of the line, other than to the tunnel), because 9 weeks is a long time...

I imagine the stock will just sit in Selhurst. Would be nice to lengthen some of the worse Uckfield workings, but given it's only a short term thing even that might not be a good idea.
 

Ibex

Member
Joined
23 Jan 2010
Messages
800
Oh embarrasing, I do apologise - that's what I get for not searching the forum beforehand.
 

OxtedL

Established Member
Associate Staff
Quizmaster
Joined
23 Mar 2011
Messages
2,631
Well, no, not necessarily, it is new news in that it has now been confirmed, and that thread is quite old, so a new one is probably fine. [Comma.]

I'm impressed by the Southern train in the BBC News article.

Thinking through your point a bit more Nym, the 171s are pretty much incompatible in their present form, so there's no chance of them going anywhere. But of course you knew that. :D
 

Nym

Established Member
Joined
2 Mar 2007
Messages
9,781
Location
Somewhere, not in London
Nothing to stop them being used on independant diagrams, didn't mean to interwork them with anything else, although it would depend on drivers signing 171s... And yes I do know compatabilities ;)
 

ushawk

Established Member
Joined
5 Nov 2010
Messages
1,965
Location
Eastbourne
The 171s will be running the normal diagrams between Brighton and Hastings as there arent any 377s to run them instead. No idea what will happen on the weekends, as usually when there is weekend work on the marshlink, the 171s are usually replaced by 377s.

I also dont know why the locals are protesting, its improving the line for a better service. If the service wasnt improved, they would complain again, no pleasing some people.
 

Nym

Established Member
Joined
2 Mar 2007
Messages
9,781
Location
Somewhere, not in London
Wonder if they could lay 3rd rail while they're at it...

Throw the substations in later, just lay the rail while in a total possession..
 

ushawk

Established Member
Joined
5 Nov 2010
Messages
1,965
Location
Eastbourne
Would be nice but it isnt happening, even if it was to be electrified now - would Southern have the units to run a service ?
 

ushawk

Established Member
Joined
5 Nov 2010
Messages
1,965
Location
Eastbourne
Maybe move possible spare 455's down - would be fine running shuttles on the route - although this is a different topic altogether :oops:
 

swt_passenger

Veteran Member
Joined
7 Apr 2010
Messages
34,229
Well, no, not necessarily, it is new news in that it has now been confirmed, and that thread is quite old, so a new one is probably fine...

I disagree with the idea that it has just been 'confirmed'.

Engineering work closures of this nature are not announced on a basis of 'pending public consultation' - so it was never in doubt from the time it was first announced.
 

ushawk

Established Member
Joined
5 Nov 2010
Messages
1,965
Location
Eastbourne
Think the closure was announced in late October with the timetable of replacement services being announced last month.

Should also be posted that Southern are doing a special offer with tickets on the Marshlink route during the closure, detailed in this link - http://www.southernrailway.com/sout...works-southern-announces-special-fares-offer/

EDIT - looking at the past articles on the BBC News website, it was actually first posted in September, not October.
 

OxtedL

Established Member
Associate Staff
Quizmaster
Joined
23 Mar 2011
Messages
2,631
I disagree with the idea that it has just been 'confirmed'.

Engineering work closures of this nature are not announced on a basis of 'pending public consultation' - so it was never in doubt from the time it was first announced.

Well, it's nice to think it was, though... :)
 

tempests1

Member
Joined
3 Aug 2010
Messages
239
Location
Haslemere
I disagree with the idea that it has just been 'confirmed'.

Engineering work closures of this nature are not announced on a basis of 'pending public consultation' - so it was never in doubt from the time it was first announced.

The work is going ahead AMCO (Amalagamated Construction) are undertaking the work as the contractor to Network Rail in addition the company will be also be attending to Bo Peep Tunnel at the same time. Dyer & Butler will be completing work on various bridges and culverts on the Rye Single Line. People will always moan but I believe Ore Tunnel is in a complete state and the work is essiential otherwise the tunnel could be totally out of compliance and would be shut down in the near future as a safety of the line issue. The local MP was very vocal on the issue but considering they are not a railway engineer or have a good understanding of the industry their views can very quickly be discounted:D
 

IanXC

Emeritus Moderator
Joined
18 Dec 2009
Messages
6,609
That mean that TPE can borrow Marshlink's turbostars to deal with their chronic overcrowding while it's being done? Then a'la scotrail just keep them?

Wheres that like button got to!

Should also be posted that Southern are doing a special offer with tickets on the Marshlink route during the closure, detailed in this link - http://www.southernrailway.com/sout...works-southern-announces-special-fares-offer/

Top marks to Southern - 50% off for an period extending slightly longer than the closure. IMHO this should be the norm in situations like this.
 

atomicdanny

Member
Joined
7 Mar 2010
Messages
542
Location
Kent, UK
Shame though that they couldn't double track the single track parts and add third rail at the same time, but that's wishful thinking though !
 

ushawk

Established Member
Joined
5 Nov 2010
Messages
1,965
Location
Eastbourne
The work is going ahead AMCO (Amalagamated Construction) are undertaking the work as the contractor to Network Rail in addition the company will be also be attending to Bo Peep Tunnel at the same time. Dyer & Butler will be completing work on various bridges and culverts on the Rye Single Line. People will always moan but I believe Ore Tunnel is in a complete state and the work is essiential otherwise the tunnel could be totally out of compliance and would be shut down in the near future as a safety of the line issue. The local MP was very vocal on the issue but considering they are not a railway engineer or have a good understanding of the industry their views can very quickly be discounted:D

Im assuming the bit highlighted in bold will be done overnight/during weekends ?
 

robertclark125

Established Member
Joined
12 Mar 2008
Messages
1,646
Location
Cardenden, Fife
Those moaning about the closure ought to ask this; would they rather have no work done, and then an accident occurs through neglect?
 

tempests1

Member
Joined
3 Aug 2010
Messages
239
Location
Haslemere
Im assuming the bit highlighted in bold will be done overnight/during weekends ?

Bo Peep Tunnel
I could have been clearer :oops: it will be weekends!

Week 44 - 0145 Sun 28th to 0400 Mon 30th January 2012
Week 45 - 0145 Sat 04th to 0400 Mon 06th February 2012
 

TheJRB

Established Member
Joined
14 Feb 2011
Messages
1,208
Location
Ashford, Kent
Shame though that they couldn't double track the single track parts and add third rail at the same time, but that's wishful thinking though !

How nice it would be! :D

I think they're going to look into removing some of the Permanent Speed Restrictions on the line, specifically the one on the viaduct just outside Ashford station, but that might have been or will be on another occasion.

It's a line that could do with some extra care (and electrification!) as it's very popular and can get quite badly overcrowded. It deserves better than a two car diesel, but then a lot of lines can say that too.

I see that the adult return fare to Brighton via Tonbridge and Redhill (which takes around 2 hours 20 minutes) is £15 during this closure. Seems quite a good deal! :lol:
 

paul1609

Established Member
Joined
28 Jan 2006
Messages
7,992
Location
K
A balanced view of the works whats being carried out is in our local rail groups blog at : http://marshlinkaction.wordpress.com/
The rail groups view is that the condition of ORE tunnel has forced Network Rail in to carrying out some long overdue maintenance on the line that has been allowed to run down over a long period.
Unfortunately electrification of Marshlink is not as simple as it may seem as with the exception of Hastings and Ashford the station platforms are between 1 to 3 coaches long and a lot of the track is close to life expired.
Personally I think the time for DC electrification has now passed and we should be pushing for AC to become an extension of the High Speed Line as this is our natural route up to town now,

The 171s are apparently being used to test a new composite brake pad on the Brighton Main Line during the closure. Understand that if any 170s come on the market Southern will be looking to snap up an extra 2 units for conversion to more 171s for the Uckfield Line where passengers numbers have more than doubled since the 171s were introduced,

No units will be moving north anytime soon.
 

richardm

Member
Joined
29 Jan 2012
Messages
10
To be fair to the user groups and local MP, they knew about the blockade some months in advance. The question was never about whether Ore Tunnel would have to be closed for the work, rather that the service should have re-started as a shuttle between Rye and Ashford.

Unfortunately this wasn't deemed practical by the TOC because the drivers are based in Eastbourne, and the diesel units mainly at St Leonards.
 