Lewes derailment - Thursday 13th August

Status
Not open for further replies.

Nicholas Lewis

Established Member
Joined
9 Aug 2019
Messages
8,009
Location
Surrey
Anyone know how the tests went?
Well NR are reporting its all good to reopen tomorrow

https://www.networkrailmediacentre....th-to-lewes-line-set-to-reopen-on-1-september

An extensive programme of work to rebuild and reinstate the railway has taken place allowing train services to resume.

The railway between Haywards Heath and Lewes will reopen to passenger services on Tuesday 1 September, following the successful completion of a major recovery operation and extensive repairs after the derailment near Lewes on Thursday 13 August.  

Engineers have now completed the recovery of the train and the extensive programme of work required to rebuild and reinstate the railway, allowing services to resume in time for the start of the new school term.

The route has also undergone a rigorous programme of engineering checks and safety assurance processes including successful test train operations, to ensure the railway is safe and reliable for customers. 

Since the derailment, teams from across the railway industry have worked around the clock to recover the train, remove damaged infrastructure and rebuild this section of railway. 
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

williamn

Established Member
Joined
22 May 2008
Messages
1,681
Trains seem to be operating relatively normally today albeit with some delays due to speed restrictions - I don't know whether that is on the reopened line or elsewhere.
 
Joined
7 Aug 2025
Messages
354
Location
Portsmouth
Trains seem to be operating relatively normally today albeit with some delays due to speed restrictions - I don't know whether that is on the reopened line or elsewhere.
Seems to be a lot all over the place - the Arun Line was basically closed on Friday!
 

williamn

Established Member
Joined
22 May 2008
Messages
1,681
Seemed to run at a normal speed past the incident site but there is a speed restriction on the up line after Plumpton.
 
Last edited:

Bald Rick

Veteran Member
Joined
28 Sep 2010
Messages
35,817
Trains seem to be operating relatively normally today albeit with some delays due to speed restrictions - I don't know whether that is on the reopened line or elsewhere.

Seemed to run at a normal speed past the incident site but there is a speed restricted on the up line after Plumpton.

It’s 50mph through the site, standard for any track renewal.
 