I thought it about time for a summary update.
Transpennine Railway Upgrade – route sections
• W1 – Manchester Victoria Stalybridge - Complete
• W2a – Stalybridge station - Complete
• W2b – Stalybridge – Marsden – in design
• W2c – Marsden to Huddersfield – in design
• W3 – Huddersfield- Ravensthorpe – major work in progress (TWAO)
• W4 – Ravensthorpe – Leeds – work in progress
• W5– Morley station – boots on the ground
• E1 – Church Fenton – Colton Jct – awaiting final commissioning
• E2 – Leeds station and to Crossgates – major work in progress
• E3 – Crossgates – Micklefield – major work in progress
• E4 – Micklefield – Church Fenton – major work in progress
Transpennine Railway Upgrade – route sections
• W1 – Manchester Victoria Stalybridge - Complete
• W2a – Stalybridge station - Complete
• W2b – Stalybridge – Marsden – in design
• W2c – Marsden to Huddersfield – in design
• W3 – Huddersfield- Ravensthorpe – major work in progress (TWAO)
• W4 – Ravensthorpe – Leeds – work in progress
• W5– Morley station – boots on the ground
• E1 – Church Fenton – Colton Jct – awaiting final commissioning
• E2 – Leeds station and to Crossgates – major work in progress
• E3 – Crossgates – Micklefield – major work in progress
• E4 – Micklefield – Church Fenton – major work in progress