ROCK RAIL EAST MIDLANDS PLC have posted their accounts for year ending 31/3/2026
https://find-and-update.company-inf...A1N2FkaXF6a2N4/document?format=pdf&download=0
Its a scanned document so salient points are
1. The manufacturing and supply agreement having previously been formerly varied in December 2023 was further amended in March 2026 to agree a new delivery programme.
2. 9 trains were accepted by Rock Rail at 31/3/26 - quite a difference to what EMR are diagraming
3. Hitachi handed over a further £19.2m in liquidated damages - add in £30.7m from previous years and thats £50m Hitachi have paid out.
4. The current lease ends in August 2027 - highly unlikely wont be extended of course as there really isnt any alternative even with current performance issues