Media statement: Bedford train crash – essential travel only as passengers warned to expect disruption for the majority of next week
Rail passengers planning to travel through Bedford next week are being warned by the rail industry to expect disruption to train services until the end of next week (28 June) and to only travel on this route if their journey is essential.
Following an incident on Friday (19 June) involving a collision between two East Midlands Railway (EMR) trains in the Bedford area, in which an EMR driver sadly died and many passengers were injured, the railway is expected to remain closed between Bedford and Luton for the rest of the week.
A complex recovery operation has begun to remove the damaged trains and carriages from the railway before engineers assess any damage and complete necessary repairs. The Overhead Line Equipment – the electrical wires that provide power to the electric trains – must be removed while a temporary access road and concrete foundation is constructed to support the operation of a crane.
Two 110 tonne rail-mounted Kirow Cranes will then lift the trains and carriages from the site before a road-mounted crane moves them onto a low loader – a heavy-duty, specialised trailer designed to carry extremely heavy equipment – to be transported away by road. Following this, engineers will then assess the track and make any repairs before reinstating the overhead lines and completing final safety checks ahead of reopening the railwa
It's not the first time that eyebrows will have been raised at an announcement that it will take at least a week.
Notwithstanding overhead power lines and the nature of modern signalling and telecoms, it does seem a long time. Accidents may be rare today, but is there no place for rail-borne cranes?