With the Midland Mainline electrification ‘paused’ indefinitely, I can’t help but feel that now is the perfect time to tackle one of the biggest pinch points on the Midland Mainline.
That being the section between Syston and Wigston.
This part of the route has several conflicting moves between passenger and freight services. Specifically between East Midlands Railway service staying on the mainline, with CrossCountry and most freight services using the East>West route, between Peterborough and Nuneaton.
In the past, there have been several ideas to resolve this. These being:
- Build an additional platform at Leicester, on the east side of the station, where the carriage sidings are located.
- Re-double the Up and Down slows from Wigston to Syston.
- Build a flyover or underpass at Wigston, to keep XC and freight services separate to the MML traffic.
- Upgrade signalling from three aspect to four aspect.
Of course these were only ideas and none of these have actually come into fruition.
My question is, what is likely to happen first - electrification or capacity improvements? Are there any actual cases or documentation to support these ideas?
That being the section between Syston and Wigston.
This part of the route has several conflicting moves between passenger and freight services. Specifically between East Midlands Railway service staying on the mainline, with CrossCountry and most freight services using the East>West route, between Peterborough and Nuneaton.
In the past, there have been several ideas to resolve this. These being:
- Build an additional platform at Leicester, on the east side of the station, where the carriage sidings are located.
- Re-double the Up and Down slows from Wigston to Syston.
- Build a flyover or underpass at Wigston, to keep XC and freight services separate to the MML traffic.
- Upgrade signalling from three aspect to four aspect.
Of course these were only ideas and none of these have actually come into fruition.
My question is, what is likely to happen first - electrification or capacity improvements? Are there any actual cases or documentation to support these ideas?