Excellent news all around.Looks like the line reopened on time after the latest blockade, well done to all involved on a successful operation!
Excellent news all around.Looks like the line reopened on time after the latest blockade, well done to all involved on a successful operation!
Excellent news all around.
Also weekend closures and diversions most of June.Still diversions this week though, but slightly quicker journey times than the past few weeks.
Also weekend closures and diversions most of June.
In a PWI (now REI) seminar a few years back, they said they were going to use a blockade strategy during summer months as schools and universities were out and conditions were more favourable for access amongst other considerations.Don't know why they can't block it off for longer but get more done at a time? Mind you, it's 30C or more out there today!
There is a good number of those already!In month blockade, is installing full electrification between Leeds and Dewsbury possible? Or is it just installing the masts they will be doing.
There is a good number of them around White Rose and Morley but Batley and Dewsbury area are yet to get them. I don't know if it's plausible to have all masts and wires up by the end of June.There is a good number of those already!
Given that there's no date for White Rose to replace Cottingley, I'd have said not; I think we were thinking that the (public) footbridge will need replacing as well, and Cottingley still being open (or not) will have an impact on where masts go. There would also be the need to make the connection outside Leeds Station, which might wait for a Christmas/New Year blockade.There is a good number of them around White Rose and Morley but Batley and Dewsbury area are yet to get them. I don't know if it's plausible to have all masts and wires up by the end of June.
Good points, thanks.Given that there's no date for White Rose to replace Cottingley, I'd have said not; I think we were thinking that the (public) footbridge will need replacing as well, and Cottingley still being open (or not) will have an impact on where masts go. There would also be the need to make the connection outside Leeds Station, which might wait for a Christmas/New Year blockade.

I think looking at Bradley to Huddersfield works. The main bits were drainage, moving the track, new junction and the Whitacre street Bridge (next to Deighton station). But piling for masts has happened where possible.In month blockade, is installing full electrification between Leeds and Dewsbury possible? Or is it just installing the masts they will be doing.
I don't think the fast line track will be laid until the whole fast line route is ready. There are several bits where track could be laid but none has appeared. The fast lines won't be any use until the Baker Viaduct is complete.Looks like the line reopened on time after the latest blockade, well done to all involved on a successful operation! Now the slow lines are in place we should start to see the new fast lines emerging soon.
Obviously, prep it first.
To facilitate upgrades as part of TRU, weekday and weekend services between Huddersfield and Leeds will be impacted throughout May and June.
Around this period, there will also be no train services through Huddersfield on weekends in April.
There will be changes to journey times and some customers may need to use a rail replacement bus for at least part of their journey. Brighouse station will be used as an interchange for those travelling to / from Huddersfield.
We will keep customers on trains wherever possible, either using our diversionary routes, or running as close as possible to the closure area
On the following dates, there will be no trains departing Huddersfield towards Dewsbury and Leeds. Services between Manchester and Leeds will be diverted via Hebden Bridge:
Saturday 6 & Sunday 7 June
Saturday 13 & Sunday 14 June
Saturday 20 & Sunday 21 June
On the following dates, there will be no trains through Dewsbury. Services will be diverted between Huddersfield and Leeds via Wakefield Kirkgate:
- Monday 1 to Friday 5 June
- Monday 8 to Friday 12 June
- Monday 15 to Friday 19 June
- Monday 22 to Friday 26 June
16 days at Gledholt Tunnel (immediately West of Huddersfield station) in September 2026I'm not sure what future blockades are planned.
Huddersfield additional platforms down as for early 2027.
Something to put the wakefields under the flyover.
Something to connect the Dewsbury end of the Baker viaduct. (maybe all at the same time)
Thornhill LNW for 37 days is that no direct TPEs to Manchester for that length of time with the Calder Valley taking the full load?16 days at Gledholt Tunnel (immediately West of Huddersfield station) in September 2026
9 days at Common Lane (Church Fenton) in October 2026
37 days at Huddersfield ("Huddersfield #2") in January 2027 (from Xmas 2026)
37 days at Thornhill LNW Jn in June 2027
There are two sets of 9 days and lots of weekends at Mirfield in 2027
After Huddersfield #2 is finished in January, nothing really happens there (Stalybridge - Heaton Lodge Jn) until the following Christmas. Plenty of preparatory weekends happening in 2026 however.
East of Leeds weekends happening throughout 2026 and 2027 also.
It's an 'Eye of the Needle' or Mirfield - so nothing Manchester/Huddersfield - Leeds for 37 days.Thornhill LNW for 37 days is that no direct TPEs to Manchester for that length of time with the Calder Valley taking the full load?
Just to add more detail to the above:16 days at Gledholt Tunnel (immediately West of Huddersfield station) in September 2026
9 days at Common Lane (Church Fenton) in October 2026
37 days at Huddersfield ("Huddersfield #2") in January 2027 (from Xmas 2026)
37 days at Thornhill LNW Jn in June 2027
There are two sets of 9 days and lots of weekends at Mirfield in 2027
After Huddersfield #2 is finished in January, nothing really happens there (Stalybridge - Heaton Lodge Jn) until the following Christmas. Plenty of preparatory weekends happening in 2026 however.
East of Leeds weekends happening throughout 2026 and 2027 also.
It is yet we have to wait till the next decade to see any benefitsAll in all, 2026 is an absolutely huge year for the upgrade works.
Well the TRU should have started literal decades ago and been finished by now. We're seeing the consequences of years of postponement and redrafting, each time adding costs for no reason other than to put off actually doing the project.It is yet we have to wait till the next decade to see any benefits
I think it’s pretty poor that the only provision over the next month from Brighouse is a bus stopping at all stations to Leeds![]()
⚠️ Upcoming Closures and changes to services
Upgrading the Transpennine main line is a huge job. This means that, at times, we’ll need to close certain parts of the railway so we can make it more reliable and greener. When this happens, we’ll get you to where you’re going on a diversion route, or on a high quality bus or coach with comfy...thetrupgrade.co.uk
So basically all of June too. I had not realised.
Which one? There’s three they are working on at the moment. Ridge Road bridge between East Garforth and Micklefield is closed to road traffic and won’t be completed until December. Crawshaw’s bridge, between Garforth and Cross Gates was back in place but last time I drove the route work on the approaches either side still required work The third bridge - Austhorpe Lane bridge at Cross Gates which closed to road traffic in April is expected to be completed at the end of the year.Has the bridge near Garforth been finished yet
How are services affected?I think it’s pretty poor that the only provision over the next month from Brighouse is a bus stopping at all stations to Leeds
Which I imagine barely anyone will actually use as it takes longer to get to Leeds than the 254
There is nothing to Manchester either, the only service running is a 2 hourly shuttle to Bradford, I’m not massively sure why it can’t run hourly as normal as everything else on the Calder valley has a consistent hourly pattern.
I wouldn't say that's entirely fair. The project is not just redrafted. It's substantially bigger and different compared to the original work which was straight electrification. I don't doubt that they were putting it off in some respects, but it is several orders of magnitude larger now.Well the TRU should have started literal decades ago and been finished by now. We're seeing the consequences of years of postponement and redrafting, each time adding costs for no reason other than to put off actually doing the project.
It's amazing TRU is still happening, in that context. I'm very happy with all this progress even though the benefits are a few years away.
It's the one that was dismantled, restored and due for reinstatement at a greater clearance.Which one? There’s three they are working on at the moment. Ridge Road bridge between East Garforth and Micklefield is closed to road traffic and won’t be completed until December. Crawshaw’s bridge, between Garforth and Cross Gates was back in place but last time I drove the route work on the approaches either side still required work The third bridge - Austhorpe Lane bridge at Cross Gates which closed to road traffic in April is expected to be completed at the end of the year.
Hull hardly bring any away fans anyway so you could put the works right in the middle of their season.June is a good month next year because no football, especially with Hull's recent promotion back to the Prem.
It is, yet we have to wait till the next decade to see any benefits