Which if it's correct that the Bay line electrification is operational is managing to work without running out of juice. That must be around the same mileage as a unit will cover if continuing down from Cathays onto the City Line before it finds some juice again, suggesting that the comments by a regular poster that they won't be able to cover that journey are somewhat pessimistic?
Or does it mean the Bay line is now live and operational?
The unit testing done there this afternoon was operated on batteries. I took some video of it and popped it onto YouTube, showing the unit entering and exiting the station.
The unit testing done there this afternoon was operated on batteries. I took some video of it and popped it onto YouTube, showing the unit entering and exiting the station.
The unit testing done there this afternoon was operated on batteries. I took some video of it and popped it onto YouTube, showing the unit entering and exiting the station.
Also no sign of the station building, which is supposed to go on the platform.
Meanwhile at Butetown there’s some brick/blockwork going in to create the access stairs and clad the lift tower for the northbound platform on Bute St.
If I recall correctly there's a foot crossing at the northern end so presumably the arrangements can't be totally finished until the line goes over to line-of-sight operation.
If I recall correctly there's a foot crossing at the northern end so presumably the arrangements can't be totally finished until the line goes over to line-of-sight operation.
I think that's just got temprorary (but properly installed) fencing likewise the crossing at bute town has the same. Then they can just unbolt that once it's line of sight, which won't happen till late 2027 iirc.
I believe, and could be wrong, that is sitting in kit form, by the Travel Lodge opposite just off Hemingway Road. Of course that is all blocked off now for Arena works.
I think that's just got temprorary (but properly installed) fencing likewise the crossing at bute town has the same. Then they can just unbolt that once it's line of sight, which won't happen till late 2027 iirc.
Yes, that’s correct. A concrete slab with ramp and steps has been laid at the city end of Cardiff Bay for a future foot crossing of the line, but it stops short of Lloyd George Avenue and is fenced off at thd platform end. There is also supposed to be a new foot crossing between the two stations but there’s no sign of it as yet.
There is a critical engineering possession on the Bay branch this weekend, IF successful then 398 testing on the newly energised will commence during closes service (0100-0400) period next Monday onwards.
With the potential for a single “locked in” 398 doing Queen Street to the Bay shuttles / subject to unit and crew being available.
If the possession works aren’t successful and 150 will be used on Queen Street to Bay shuttles UFN.
At the present the OLE isn’t energised due to a fault which was realised some weeks ago when the original switch on was planned.
The move of signalling from Cardiff ROC to TfW Taff Well is planned for April 27, once this is done the plan is to push the Queen street remodelling forward and the new line of sight operation with 398s on the Bay.
This appeared at Queen Street yesterday, in public view on the platform fences. It's implying the blockade this weekend will not be for OLE testing. (I blanked out the contact details)
Is it possible that the wires can be energised during the possession, provided that they're de-energised before it's handed back to normal operation? The notice above is primarily about notifying rail staff about live wires during normal operation of the railway.
This appeared at Queen Street yesterday, in public view on the platform fences. It's implying the blockade this weekend will not be for OLE testing. (I blanked out the contact details)View attachment 204510
Well - someone is being misleading then……the information I have is the possession is to rectify faults and energise the limited OLE on the Bay.
They will be switched then, all being well then switched off with a block to electric traction during service hours, then switched on again after hours to allow 398 testing as per my initial post, all being well of course.
Well - someone is being misleading then……the information I have is the possession is to rectify faults and energise the limited OLE on the Bay.
They will be switched then, all being well then switched off with a block to electric traction during service hours, then switched on again after hours to allow 398 testing as per my initial post, all being well of course.
This appeared at Queen Street yesterday, in public view on the platform fences. It's implying the blockade this weekend will not be for OLE testing. (I blanked out the contact details)View attachment 204510
This sign is in relation to the “extensions lead” from the feeder station north of QS and the commencement of OLE on the Bay branch, the same is placed on the other extension leads up the Rhymney and TAM valleys.
Interesting! The signalling changes to support a second track won’t happen until next year, so it seems unlikely that both tracks will be used before then.
Interesting! The signalling changes to support a second track won’t happen until next year, so it seems unlikely that both tracks will be used before then.
Additional trains to / from Cardiff bay and the bay metro, it’s linked in with the remodel of QS.
Network Rail won’t accept the desired line of sight signalling method TfW want to use on the branch hence the need for recontrol of signalling to TfW prior to commissioning.
Additional trains to / from Cardiff bay and the bay metro, it’s linked in with the remodel of QS.
Network Rail won’t accept the desired line of sight signalling method TfW want to use on the branch hence the need for recontrol of signalling to TfW prior to commissioning.
Ah thanks for info just waiting for the train back from the bay now defo seems like a construction site down here. The 1st platform hasn’t got the overhead wires yet by looks of it only the second platform does.
And having looked at the TfW web site, I see: "Network Rail and Amey Infrastructure have been carrying out planned engineering works. Unfortunately we have been told the work will take longer than anticipated"
It doesn't seem a good look to me to take over infrastructure then act as if engineering work on it by their subcontractor is nothing to do with them.
I don't seem to recall press releases on how wonderful all the electrification work was with titles like "Amey Infrastructure completes electrification on the Valley Lines".
On a more positive note, when I used the rail replacement buses yesterday everything was going very smoothly, with staff helpful and friendly despite the heat.
== Doublepost prevention - post automatically merged: ==
Also, this morning they seem to have put a comprehensive set of bus ticket acceptance in place at presumably rather short notice so full marks to them for that.
And having looked at the TfW web site, I see: "Network Rail and Amey Infrastructure have been carrying out planned engineering works. Unfortunately we have been told the work will take longer than anticipated"
It doesn't seem a good look to me to take over infrastructure then act as if engineering work on it by their subcontractor is nothing to do with them.
I don't seem to recall press releases on how wonderful all the electrification work was with titles like "Amey Infrastructure completes electrification on the Valley Lines".
On a more positive note, when I used the rail replacement buses yesterday everything was going very smoothly, with staff helpful and friendly despite the heat.
== Doublepost prevention - post automatically merged: ==
Also, this morning they seem to have put a comprehensive set of bus ticket acceptance in place at presumably rather short notice so full marks to them for that.
Any details of what is actually overrunning as they're saying delays to end of day now (yet looking at things, don't see any processions etc), one thing I will give credit to Network Rail over Amey Infrastructure, when things go wrong on Network Rail infrastructure, it's resolved usually within a given X period of time (commonly a few hours at most). TfW/Amey default whenever something goes wrong on the CVL is end of day (then usually resolved overnight), it's not often it's as quickly resolved compared to NR. Recent example is the points failure at Heath Junction etc.