Poplars Project Scope
The main duties performed by our team were the installations of:
Incorporating our in-house expertise, we also completed other infrastructure upgrades including Overhead Line (OLE) and Signalling & Telecoms (S&T) on the Up and Down Main Lines.
- Overhead line equipment (OLE), including new structures and foundations
- New and modified wire runs
- New electrical sections controlled by a blend of motorised and manual switches
- A neutral section
- Signalling alterations and updates
- Upgrade to existing bonding arrangements and cable routes
- Installation of new safety and operational signage
- Upgrade to platform fencing at Acton Mainline Station
Other upgrades include software and interface changes at the Rugby and Didcot control centres. The upgrades will also improve depot access for maintenance of the Elizabeth Line fleet and contribute to Network Rail’s decarbonisation strategy to allow for sustainable electric trains to run on this section of the network and between the North London Line and Great Western Main Line (GWML).
The Anglia side of the network was energised in early November 2025, while the Western side received their power upgrades on the 27th of December delivered in conjunction with the SRSA’s OOC Christmas blockade.
Full operational capability expected by Easter 2026, where these upgrades will link to the existing electrified sections at Acton Wells junction, connecting with the Acton Willesden Line and the Barking to Gospel Oak Line.