Network Rail have today announced that routes between Charing Cross and London Bridge will be closed for a straight 22 day long closure. This follows the recent ‘Dartford blockade’ and the upcoming prolonged half term closure near Maidstone East
Trains will continue into London, it is not yet clear (or on RTT) if the Kent Fasts will be open as well. Some trains will divert to Cannon Street, Victoria and Blackfriars (during peak times). Some trains will terminate at London Bridge instead.
The new management of the Southeastern region seem to be happier with prolonged closures, following the recent Dartford Blockade, and the upcoming disruption via Maidstone East during the next half term. It definitely seems they might be ‘testing the waters’ with how long they can get away with one single prolonged closure. Can anyone say if there has been a longer closure of this route in recent times or if this is new behaviour?
Trains will continue into London, it is not yet clear (or on RTT) if the Kent Fasts will be open as well. Some trains will divert to Cannon Street, Victoria and Blackfriars (during peak times). Some trains will terminate at London Bridge instead.
Network Rail said:
The temporary closure of Charing Cross and Waterloo East stations will allow South Eastern Railway to carry out a package of essential improvements designed to make journeys safe and reliable for years to come. Engineers will replace 1,800 metres of life-expired track between Waterloo East and Charing Cross and deliver a series of upgrades to improve reliability, safety and long-term performance.
The track, last replaced in the early 1990s, is becoming increasingly unreliable and requires extensive maintenance to keep services running safely. In recent years, faults on the approaches to London Charing Cross have caused more than hundreds of hours of delays. Without intervention, these issues would continue to worsen, leading to more delays for passengers.
To make the most of the closure, the 22-day programme includes drainage improvements at Waterloo East, structural repairs to Hungerford Bridge, and the railway is continuing to develop plans to bring even more work into the access. Completing these works a continuous 22-day closure means customers will experience the benefits sooner and helps avoid a long series of weekend or bank holiday closures.
Engineers, planners and timetable specialists examined a wide range of delivery options. A continuous 22-day closure in the summer, when schools are off, commuter numbers are lower, and customers generally have more flexibility, is the least disruptive and most efficient way to complete the work.
The new management of the Southeastern region seem to be happier with prolonged closures, following the recent Dartford Blockade, and the upcoming disruption via Maidstone East during the next half term. It definitely seems they might be ‘testing the waters’ with how long they can get away with one single prolonged closure. Can anyone say if there has been a longer closure of this route in recent times or if this is new behaviour?