What are the platform lengths at Winslow?
EWR have just announced that their plans have changed from 4-car platforms (106 metres) to 5-car platforms, but since Winslow will already have been built, will its platforms need to be extended?
All station plans already have passive provision for 202-metre-long platforms. Will platform extension, if necessary, happen before it opens, since there’s a delay with it being suitable for use anyway?
Chiltern Railways selected as operator for the first stage of East West Rail - Oxford to Milton Keynes
Update from Chiltern yesterday: https://www.chilternrailways.co.uk/oxford-to-miltonkeynes **East West Rail - Oxford to Milton Keynes – Passenger Service Update – November 2025** Since being announced as operator of the first stage of East West Rail between Oxford and Milton Keynes in March...
What are the platform lengths at Winslow?
EWR have just announced that their plans have changed from 4-car platforms (106 metres) to 5-car platforms, but since Winslow will already have been built, will its platforms need to be extended?
All station plans already have passive provision for 202-metre-long platforms. Will platform extension, if necessary, happen before it opens, since there’s a delay with it being suitable for use anyway?