Just a note to say that this thread is about the 230s with GWR. There is another thread here for discussion of potential future uses of the technology.
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

NewForest

Member
Joined
5 Jun 2013
Messages
10
Location
London UK
230001 not running today (Saturday)?

According to RTT Realtime Trains https://www.realtimetrains.co.uk/search/detailed/gb-nr:GFD/2026-02-14/0200-0159 the BEMU unit 230001 isn't running at all today (Saturday 14 Feb 26). The Greenford branch service appears to be operating all day with a two-car DMU no 165129.

At the grand launch two weeks ago, GWR indicated that the BEMU would operate the Saturday services. Does anyone know why 230001 didn't run today as planned?
 

D365

Veteran Member
Joined
29 Jun 2012
Messages
13,157
230001 not running today (Saturday)?

According to RTT Realtime Trains https://www.realtimetrains.co.uk/search/detailed/gb-nr:GFD/2026-02-14/0200-0159 the BEMU unit 230001 isn't running at all today (Saturday 14 Feb 26). The Greenford branch service appears to be operating all day with a two-car DMU no 165129.

At the grand launch two weeks ago, GWR indicated that the BEMU would operate the Saturday services. Does anyone know why 230001 didn't run today as planned?
230001 was not planned to run today. This is due to a Network Rail possession. I’m fairly sure this has been discussed upthread.
 

Peter Sarf

Established Member
Joined
12 Oct 2010
Messages
9,588
Location
Croydon
230001 not running today (Saturday)?

According to RTT Realtime Trains https://www.realtimetrains.co.uk/search/detailed/gb-nr:GFD/2026-02-14/0200-0159 the BEMU unit 230001 isn't running at all today (Saturday 14 Feb 26). The Greenford branch service appears to be operating all day with a two-car DMU no 165129.

At the grand launch two weeks ago, GWR indicated that the BEMU would operate the Saturday services. Does anyone know why 230001 didn't run today as planned?
Planner engineering work in the way of the sidings where 230001 is kept.

From this thread one week ago (07/02/2026)
As I understand it:

Planned to run on Sat 7/2/26
Won't run on Sat 14/2/26
Planned to run on Sat 21/2/26

Right?
And I think some other days.

The way to check is if the first service of the day is fed from Paddington then its a 165.
 

norbitonflyer

Established Member
Joined
24 Mar 2020
Messages
5,660
Location
SW London
230001 was not planned to run today. This is due to a Network Rail possession. I’m fairly sure this has been discussed upthread.
Indeed. See Post 995. It should be running next saturday (21st Feb) but not the following two (28th Feb, 7th March)

RTT then shows the first train on the branch to start from West ealing every saturday from 14th March to 16th May , but from Paddington on May 23rd and 30th, but check RTT nearer the time, rather than relying on my post still being correct if you are reading this in three months time!
 

317 forever

Established Member
Joined
21 Aug 2010
Messages
3,260
Location
North West
Indeed. See Post 995. It should be running next saturday (21st Feb) but not the following two (28th Feb, 7th March)

RTT then shows the first train on the branch to start from West ealing every saturday from 14th March to 16th May , but from Paddington on May 23rd and 30th, but check RTT nearer the time, rather than relying on my post still being correct if you are reading this in three months time!
This suggests that on March 28th it is currently intended to be a 230. That is when I shall be in the area.
 

rivervale

Member
Joined
28 Feb 2017
Messages
26
It doesn’t accelerate or brake the same as a turbo, it’s 15mph leaving Greenford until after the points at Greenford South, it doesn’t like sitting at that speed, going towards Greenford it won’t sit at 15 either so it’s a case of taking power and then shutting off annoyingly where as a turbo will just sit at 15 in notch 1
Uphill is easy - get to 15 mph then stick it in cruise control (notch 2) and it will stay at exactly 15 mph regardless of the gradient
 

Woods

Member
Joined
3 Sep 2021
Messages
187
Location
Guildford
It's just gone back to the depot...
It is the worst kind of fault to diagnose - an intermittent comms failure which stops the charging from happening. Some of the charges yesterday were successful and others were not. Maintenance Control soon decided, understandably, that it wasn't reliable enough so decided to substitute the Turbo back in. Investigations continue. Hopefully will be better next Saturday.
 

Prime586

Member
Joined
26 May 2023
Messages
286
Location
Knowsley
It is the worst kind of fault to diagnose - an intermittent comms failure which stops the charging from happening. Some of the charges yesterday were successful and others were not. Maintenance Control soon decided, understandably, that it wasn't reliable enough so decided to substitute the Turbo back in. Investigations continue. Hopefully will be better next Saturday.
I commented on the previous page that after studying the patents I was surprised about the crudeness of the signalling method used to control lthe charging system and it's potential suceptibilty to RFI/EMI. That would lbe the first place I would look.
 

Woods

Member
Joined
3 Sep 2021
Messages
187
Location
Guildford
The Battery Electric Storage System (BESS) element of the DfT fast charging system is nothing particularly novel - there are a number of companies who offer similar systems for EV charging stations where a HV connection to a substation is not avaialble (it's also fairly commonly used for depot fast charging of EV buses). The novel part of the patent is the conductor rails and their control system. I am surprised to read the charging control protocl is based on analogue frequency signals, though - I would have expected something a bit more modern and secure that would be less susceptible to RFI/EMI.
Ah yes, the system doesn't actually work like that. What was patented isn't what was eventually developed. Lots of changes to the interlock systems since then; reliance now on WiFi and optical sensors, not low frequency signals through the charging rails as was originally patented. Also, the patent had the charge rails being 'third and fourth rail' (like conventional LUL). The system as eventually realised didn't do it like that.
 

Prime586

Member
Joined
26 May 2023
Messages
286
Location
Knowsley
reliance now on WiFi and optical sensors
That doesn't sound much better, to be honest - WiFi isn't particularly great in contested environments where you can have mulitple APs fighting over channels (such as passengers stood on the platform with WiFi endpoints enabled on their phones), and optical sensors are not an ideal choice in external environments.

NFMI signalling would probably be the ideal option for Layer 1 this application and environment (and as it can securely carry audio they could have even used FSK or DTMF signalling for Layer 2), but it is not a cheap COTS solution.
 

norbitonflyer

Established Member
Joined
24 Mar 2020
Messages
5,660
Location
SW London
Ah yes, the system doesn't actually work like that. What was patented isn't what was eventually developed. Lots of changes to the interlock systems since then; reliance now on WiFi and optical sensors, not low frequency signals through the charging rails as was originally patented. Also, the patent had the charge rails being 'third and fourth rail' (like conventional LUL). The system as eventually realised didn't do it like that.
Just to be clear, what was eventually developed falls within the scope of the patent monopoly granted, which is defined by the patent claims (the bit at the end which actually defines the scope of the patent monopoly), although the arrangment actually installed at West Ealing differs in detail from the illustartive implemention depicted in the patent documents. The art of drafting a patent is to think beyond the thing the inventor has made to see what is essential to the idea and what is just the inventor's current (no pun intended!) way of implementing it. If the claims don't cover such variations, a competing product could use them without infringing the patent.

The main (broadest) claim simply refers to a charging rail (singular), a sensor, and a digital handshake process.

There is no limitation on how the sensing or handshake is done, or to a four rail system. These are covered in Claims 3 and 9, which are essentially back-up claims, to allow the patentee to fall back on a more limuited scope should his main claim be invalidated for any reason. (Both the presence of Claim 9, and the embodiment, make it clear that Claim 1, although only mentioning one charging rail, is not intended to be limited to arrangements with only one charging rail)

 

MotCO

Established Member
Joined
25 Aug 2014
Messages
6,080
That doesn't sound much better, to be honest - WiFi isn't particularly great in contested environments where you can have mulitple APs fighting over channels (such as passengers stood on the platform with WiFi endpoints enabled on their phones),
I assume that on the first weekend of operation, there were no charging issues. Then, I would have expected a lot of competing demands for WiFi with all the excited first day users sending messages on their mobiles etc. Unless something has been changed?
 

Woods

Member
Joined
3 Sep 2021
Messages
187
Location
Guildford
Just to be clear, what was eventually developed falls within the scope of the patent monopoly granted, which is defined by the patent claims (the bit at the end which actually defines the scope of the patent monopoly), although the arrangment actually installed at West Ealing differs in detail from the illustartive implemention depicted in the patent documents. The art of drafting a patent is to think beyond the thing the inventor has made to see what is essential to the idea and what is just the inventor's current (no pun intended!) way of implementing it. If the claims don't cover such variations, a competing product could use them without infringing the patent.

The main (broadest) claim simply refers to a charging rail (singular), a sensor, and a digital handshake process.

There is no limitation on how the sensing or handshake is done, or to a four rail system. These are covered in Claims 3 and 9, which are essentially back-up claims, to allow the patentee to fall back on a more limuited scope should his main claim be invalidated for any reason. (Both the presence of Claim 9, and the embodiment, make it clear that Claim 1, although only mentioning one charging rail, is not intended to be limited to arrangements with only one charging rail)

Thanks. Must admit I find these patents very hard to follow.
 

norbitonflyer

Established Member
Joined
24 Mar 2020
Messages
5,660
Location
SW London
Thanks. Must admit I find these patents very hard to follow.
After thirty years writing the things, it does get easier !

Basically a patent grants a temporary (max 20 year) monopoly on what is defined in the claims (which are the legal bit), and in particular the first claim, which has the broadest scope, in exchnage for a disclosure of how the invention might be performed. The disclosure forms the dual purpose of convincing the Patent Office that you know how to do it, and secondly to make the invention public to allow further developments to be made in that field, either under licence from the patentee during its term, or free to use after expiry.

Digression over - let's get back to West Ealing
 
Joined
21 Jan 2024
Messages
78
Location
London
It's just gone back to the depot...
I just tried to get the 11:10 but it isn’t running. The backup train is. 230001 is sat at platform 5 and has staff inside who look like they are working on something. The LED display on the front of the train says “GWR Test Train”
 

800301

Member
Joined
29 Dec 2022
Messages
522
Location
Essex
I just tried to get the 11:10 but it isn’t running. The backup train is. 230001 is sat at platform 5 and has staff inside who look like they are working on something. The LED display on the front of the train says “GWR Test Train”
The 230 only runs in service on certain Saturdays
 

Woods

Member
Joined
3 Sep 2021
Messages
187
Location
Guildford
I just tried to get the 11:10 but it isn’t running. The backup train is. 230001 is sat at platform 5 and has staff inside who look like they are working on something. The LED display on the front of the train says “GWR Test Train”
Fault-finding to try and determine the root cause of why it had charging issues on Saturday.

== Doublepost prevention - post automatically merged: ==

It's running and charging happily today, so far, touch wood.
 
Last edited: